City of Irvine v. County of Orange

238 Cal. App. 4th 526
CourtCalifornia Court of Appeal
DecidedJuly 6, 2015
DocketG049527
StatusPublished
Cited by14 cases

This text of 238 Cal. App. 4th 526 (City of Irvine v. County of Orange) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Irvine v. County of Orange, 238 Cal. App. 4th 526 (Cal. Ct. App. 2015).

Opinion

Opinion

BEDSWORTH, Acting R J.

I. INTRODUCTION

This is the third effort by the City of Irvine (Irvine) to stop a proposed expansion of the James A. Musick Facility (the Musick Facility, sometimes called the Musick jail expansion) to reach this court. In City of Lake Forest v. County of Orange (Dec. 8, 2000, G023884) (nonpub. opn.) (Musick I), the Cities of Irvine and Lake Forest challenged the 1996 certification of an environmental impact report (EIR 564) involving a proposed expansion of the Musick Facility from about 1,200 beds to 7,584 beds. Four aspects of EIR 564 were targeted in Musick L (1) the loss of agricultural land attendant *531 on the change of the facility from an “honor farm” to a relatively large jail facility; (2) the impact of the project on air quality; (3) the extra burdens on local government services in the area because of a need for extra police patrols and ambulances; and (4) the cumulative impact of the project in light of the planned—at the time—reuse of the adjacent El Toro Marine Air Station (the El Toro Base) as an international airport. In Musick I, this court overturned a trial court decision finding EIR 564 inadequate. We held EIR 564 did indeed adequately disclose the environmental impacts of the project. The 1996 project, however, did not go forward because the County of Orange (County) did not think it had the financial resources for it.

A decade or so later came the Criminal Justice Realignment Act of 2011 (see Stats. 2011, ch. 15, §§ 1, 450) which shifted responsibility for the custodial housing and post-release supervision of some felons from the state prison system to local jails and probation departments. (See Wofford v. Superior Court (2014) 230 Cal.App.4th 1023, 1032 [179 Cal.Rptr.3d 243].) Concomitant with realignment, legislation was passed making it easier for local government agencies to obtain state funds to build more local jail cells. (See City of Irvine v. County of Orange (2013) 221 Cal.App.4th 846, 852 [164 Cal.Rptr.3d 586] (Musick II).) The prospect of new funding revived the County’s plans for the Musick jail expansion, and the County applied for state funds for the project. Irvine reacted by challenging the County’s application for state funding of the expansion without a new EIR (environmental impact report), even though the County, at roughly the same time as the application, had certified a supplemental EIR (SEIR 564) dealing with the project in light of planned intervening changes in surrounding land uses. (See Musick II, supra, 221 Cal.App.4th at pp. 852-853.) In Musick II, this court concluded there was no need to prepare an EIR (or other appropriate environmental impact document) prior to merely applying for funds. (Id. at pp. 863-865.)

We now come to Musick III—this case—in which Irvine directly challenges SEIR 564. The project is still for 7,584 beds, though there is a minor reconfiguration of the actual jailhouse to be built. And some land, about 22 acres, that was going to continue to be farmed back in 1996 has been dropped for open space. There has been one big intervening change in surrounding land use, which is the scrapping of the proposed international airport at the former El Toro Base in favor of a “Great Park,” with some adjacent housing development.

In Musick III, Irvine presents several challenges to SEIR 564 that basically center on only two actual environmental effects: impacts on local traffic intersections and the loss of agricultural land. It turns out the problem of ascertaining the effect of the project on local traffic is a problem of variable *532 phasing. The project depends on state funding, and can only proceed as state funding becomes available, but that complicates the task of gauging the precise marginal interim effects on local traffic on an intersection-by-intersection basis. Irvine would have us hold that the County was obligated to calculate year-by-year, intersection-by-intersection, traffic impacts that would take into account all the various permutations derivable from the variables of project phasing and nearby residential construction in the Great Park area. That is not required. As we explain below, the Supreme Court’s opinion in Neighbors for Smart Rail v. Exposition Metro Line Construction Authority (2013) 57 Cal.4th 439 [160 Cal.Rptr.3d 1, 304 P.3d 499] (Metro Une) demonstrates that what Irvine did here—two traffic studies using baselines for traffic conditions in 2014 and 2030—was sufficient. And if not sufficient, not prejudicially insufficient.

As to the loss of agricultural land, the topic is well-trod territory in a county where there are few orange groves left and the cost of land makes commercial agriculture largely cost prohibitive. The County had discovered it was even too costly to grow its own food by 2009, so there is now no actual agriculture at the Musick Facility. Irvine quibbles with the conclusion of SEIR 564 that it is now virtually impossible to find 65 acres of prime agricultural land in Orange County to replace the. 65 acres that used to be farmed at the Musick Facility. As we explain, SEIR 564 more than adequately documented that the cost of land near the project site was $2 million per acre in 2012, and that was prior to the recovery from the Great Recession. (And the County average exceeds $308,000 per acre.) But agriculture is not competitive if the cost of land exceeds $60,000 per acre. Replacing what used to be farmed at the Musick Facility cannot be done at anything near a reasonable price.

All these considerations compel us to the conclusion SEIR 564 is legally unobjectionable.

II. FACTS

The Musick Facility consists of about 100 acres of unincorporated land in southern Orange County. Figure 5-1 from SEIR 564, reproduced below, taken from part of the traffic study in the report, nicely encapsulates its location in the county. As the airstrip markings in the upper left-hand quadrant of figure 5-1 show, the land is almost due east of the old El Toro Marine Base (the airstrip markings), which is now the Great Park area. When the Great Park and surrounding housing is finally built, the Musick Facility will represent a northeast boundary of Irvine. To the immediate north is hilly terrain (as indicated by the relative scarcity of street markings), and to the south is the City of Lake Forest. The numbers on the map represent traffic intersections studied in SEIR 564.

*533 [[Image here]]

The Musick Facility began in 1964 as an honor farm designed to allow inmates to work off sentences by doing agricultural work. The farm gave inmates the chance to do productive work, and at the same time grow food *534 for the County’s main jail plus other County facilities, such as the Orange-wood Children’s Home. Of the 100 acres at the site, 55 were “prime” farmland, and another 10 were farmable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson v. City of Lynwood CA2/4
California Court of Appeal, 2023
Aqualliance v. U.S. Bureau of Reclamation
287 F. Supp. 3d 969 (E.D. California, 2018)
L.A. Conservancy v. City of West Hollywood
California Court of Appeal, 2017
L.A. Conservancy v. City of W. Hollywood
226 Cal. Rptr. 3d 666 (California Court of Appeals, 5th District, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
238 Cal. App. 4th 526, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-irvine-v-county-of-orange-calctapp-2015.