City of Grafton v. Otter Tail Power Company

86 N.W.2d 197, 1957 N.D. LEXIS 167
CourtNorth Dakota Supreme Court
DecidedOctober 25, 1957
Docket7709
StatusPublished
Cited by6 cases

This text of 86 N.W.2d 197 (City of Grafton v. Otter Tail Power Company) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Grafton v. Otter Tail Power Company, 86 N.W.2d 197, 1957 N.D. LEXIS 167 (N.D. 1957).

Opinion

MORRIS, Judge.

Under date of March 31, 1955 the Otter Tail Power Company and the Board of Administration of the State of North Dakota entered into an agreement whereby the company agreed to furnish certain electric service to the State School at Grafton. The State School already had its own generating plant which furnished most of the electric energy normally needed by the School. The Board of Administration desired to provide standby electric service to be used in event of a breakdown or when steam boilers of the school generating plant were not in operation, and the State School being a possible preference user of electrical energy produced by the Federal Generating Plant at the Garrison Dam on the Missouri River, the Board desired to make arrangements for the transmission of such energy, such transmission being known as “wheeling service.” The agreement provides for the furnishing of “wheeling service” and supplemental and emergency service by the company.

The grounds on which the school is located are on the west edge of the City of Grafton, the west boundary of the grounds being coincident with the western limits of the city. • This boundary is formed by a section line. Along this section line is the usual section line township road. The city limits of Grafton were extended to include the school grounds in 1911. In 1926 the company constructed a transmission line running north and south on the west edge of the section line road. Thus the road lies between the transmission line and the grounds of the school.

The service agreed to be furnished by the company is to be rendered at the company’s transmission line. The Board of Administration agreed to construct a substation at the school and build a transmission line from it to the company’s transmission line on the west side of the road, a distance of approximately one-fourth mile, and to install suitable 'metering equipment. The company agreed to make such changes in its transmission line as were necessary to provide a suitable structure on which the line from the school could be connected to the company’s line and the company was to receive $1,030 to compensate it for making these changes in its facilities. It was also provided that:

“this agreement shall be of no force and effect unless and until it has been approved by the Public Service Commission of the State of North Dakota.”

The agreement bears the approval of the Public Service Commission under date of April 27, 1955.

For several years prior to the commencement of these proceedings the City of Grafton, through its municipal light plant, had provided some electric energy for use at the State School, and at the time of the hearing of these proceedings before the Commission was engaged in enlarging its plant with the result that it will be able to provide for the school’s maximum requirements for light and power.

During the early part of June, 1955 the City of Grafton filed a complaint against the Otter Tail Power Company with the Public Service Commission of the State of North Dakota wherein it sought an order requiring the Otter Tail Power Company to cease and desist from supplying or offering to supply electric power to the Grafton State School or any other person, firm, corporation or public institution situated within the corporate limits of the city. The Public Service Commission set July 14, 1955 at the Court House in Grafton as the time and place for hearing the complaint on its *200 merits and ■ notified the company accordingly.

The Otter Tail Power Company answered the complaint of the City of Grafton, set up its agreement with the Board of Administration and alleged that:

“pursuant to the terms of said agreement, the Board of Administration constructed, paid for, and owns the necessary substation, metering equipment, and lines to obtain electrical service, as provided therein, at a point of connection with Respondent’s 41.6 KV transmission line located outside of the corporate limits of the City of Grafton. The physical connection has'been made, and the Board of Administration is receiving service pursuant to said agreement. The Board of Administration has made a substantial investment in lines, substation, meters, and equipment under said agreement.”

The company asked that the Board of Administration be made a party to this proceeding and that the complaint be dismissed.. A hearing was had which resulted in an order of the Commission dated November 3, 1955 directing the company to cease and desist from furnishing either firm or emergency standby service to the Grafton State School on and after December 1, 1955.

The Board of Administration appeared orally at the hearing by its president and by mutual consent was made a party to this proceeding. Both the Board and the company appealed from the cease and desist order of the Commission to the District Court of Walsh County under the provisions of Chapter 28-32, NDRC 1943, being the Administrative Agencies Uniform Practice Act. After a trial in the District Court judgment was entered reversing the order of the Public Service Commission and remanding the case with instructions to dismiss the complaint and the proceedings thereon. From that judgment the City of Grafton appeals to the Supreme Court.

The appellant has set out twelve assignments of error, challenging certain findings of fact and legal conclusions of the trial court. They need not be set out here in detail. Their substance will be covered in our discussion of controlling points of controversy.

In 1904 an amendment to the State Constitution, Section 215, was adopted, providing that :

“there shall be located at or near the city of Grafton, in the county of Walsh, an institution for the feeble minded, on the grounds purchased by the secretary of the interior for a penitentiary building.”

Chapter 108, Session Laws N.D. 1903 was an act “to establish an Institution for the Feeble Minded and to Provide for its Support and Management.” The institution was placed under the control of a bpard of five trustees appointed by the governor with the advice and consent of the senate. Chapter 62, Session Laws N.D. 1911 created a Board of Control which was given full power to manage, control and govern, subject to certain limitations contained in the act, various state institutions including the School for the Feeble Minded. Chapter 71, Session Laws N.D. 1919 created the Board of Administration and transferred to it all of the powers and duties of the State Board of Education, State Board of Regents and the State Board of Control. Chapter 240, Session Laws N.D. 1933 changed the name of the institution for the feeble minded to “Grafton State School.” At the time this controversy arose Section 25-0102, NDRC 1943 provided that the Board of Administration should have general control and management of the State School. The general power of the Board of Administration to provide electric service for the State School is not challenged in this proceeding, but it is contended by the City of Grafton that the power of the Board to purchase electric light and power for the Grafton State School is limited in two respects. The first contention is that the Board can only contract with public utility corporations in accordance with the *201

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MCI Telecommunications Corp. v. Heitkamp
523 N.W.2d 548 (North Dakota Supreme Court, 1994)
Cass County Electric Cooperative, Inc. v. Northern States Power Co.
518 N.W.2d 216 (North Dakota Supreme Court, 1994)
Otter Tail Power Co. v. North Dakota Public Service Commission
354 N.W.2d 701 (North Dakota Supreme Court, 1984)
Montana-Dakota Utilities Co. v. Divide County School District No. 1
193 N.W.2d 723 (North Dakota Supreme Court, 1971)
Public Service Commission v. Montana-Dakota Utilities Co.
100 N.W.2d 140 (North Dakota Supreme Court, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
86 N.W.2d 197, 1957 N.D. LEXIS 167, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-grafton-v-otter-tail-power-company-nd-1957.