City of Forth Smith v. B&A Electric, Inc.

2023 Ark. App. 24
Court of Appeals of Arkansas·Decided January 25, 2023·Published

Opinion

Cite as 2023 Ark. App. 24 ARKANSAS COURT OF APPEALS DIVISION I

No. CV-21-569

CITY OF FORT SMITH Opinion Delivered January 25, 2023 APPELLANT

APPEAL FROM THE SEBASTIAN COUNTY CIRCUIT COURT,

V. FORT SMITH DISTRICT [NO. 66FCV-17-285]

B&A ELECTRIC, INC.; MEGEHEE FENCE CONTRACTING, LLC; GRIMES HONORABLE STEPHEN TABOR, DOZER SERVICE, INC.; JAMES JUDGE GRIFFITH; AND RIVER VALLEY SPORTS COMPLEX, INC.

APPELLEES REVERSED AND DISMISSED

WAYMOND M. BROWN, Judge

The City of Fort Smith (the City) appeals the Sebastian County Circuit Court’s entry of judgment against it following a jury verdict on breach-of-contract claims brought by appellees B&A Electric, Inc.; Megehee Fence Contracting, LLC; Grimes Dozer Service, Inc.; and James Griffith (the contractors), hired by third-party defendant River Valley Sports Complex, Inc. (RVSC). The City contends that the evidence was insufficient to support the judgment in favor of the contractors. We agree. Therefore, we reverse and dismiss this action.1

1 This is the third time this case has been before us—we dismissed it twice for lack of a final order. See City of Fort Smith v. B&A Electric, Inc., 2019 Ark. App. 575; City of Fort Smith v. B&A Electric, Inc., 2021 Ark. App. 334.

The City and RVSC entered into a written contract in March 2014 for the construction of a sports complex on city-owned land after RVSC principals Jake Files and Lee Webb presented the project to the city board. The City agreed to contribute up to $1.6 million in amounts payable when construction reached specific milestones. RVSC solicited donations to cover the remaining costs of the project. The contract required RVSC to complete the project by June 10, 2015, but stated that after construction was complete, the City would lease the complex back to RVSC for ten years.

RVSC began work on the project in 2014, and it hired the four appellees as contractors to provide materials and services. By the scheduled completion date, however, RVSC had not substantially completed the work. Work continued into 2016 as a result of two negotiated extensions granted by the City. The City paid RVSC over $1.08 million, but in early 2017, RVSC permanently ceased working on the project after having failed to meet the deadline extensions. When RVSC abandoned the project, it owed all four contractors payment for work and materials they had already provided. The contractors sought payment from RVSC, but RVSC did not have sufficient funds to pay. The contractors then sued the City for breach of contract and unjust enrichment. The City filed a third-party complaint against RVSC for breach of contract and contractual indemnity.

The case went to trial before a jury in September 2018. Terry Bailey, the bookkeeper and corporate secretary for Grimes Dozer Service, testified that she compiled and submitted invoices to RVSC between 2014 and 2016. She stated that Grimes had been paid for all the work performed except $12,977.50 for which it was seeking judgment against the City.

On cross-examination, Bailey stated that all the invoices were directed to Webb because its agreement was with RVSC. She said that it billed RVSC and received payments from RVSC. She denied ever receiving checks from the City. She testified that Grimes billed the City on advice from its attorney to do so after work on the project had stopped. She said that Grimes was not paid after July 2016 “because RVSC did not receive another draw from the City because RVSC had not completed the next phase, and there was no money to pay us.”

On redirect, Bailey stated that she knew the land was owned by the City and that in her mind, “the City would direct the money to RVSC and then to us.”

Brian Buzbee, part owner of B&A Electric, testified that he submitted budget numbers to the City to provide lights, poles, and concrete bases for the softball fields in 2014 and that the City subsequently passed a resolution with that bid exhibited. He stated that it received $40,000 as final payment, but it was expecting $100,000. He said that RVSC told B&A Electric that “we weren’t getting any more money from the City.” He testified that he met with his supplier, Upchurch Electric, and the city auditor, Tracey Shockley, and looked at the site and what had been done up to that point. He said that he subsequently pulled out all the panel “guts” and wiring it had installed to protect it from vandalism. He stated that it had completed all the work for which invoices were submitted to RVSC or the City. Buzbee testified that he attended a city board of directors meeting in March 2017 to inquire about why RVSC was not required to submit a performance bond and was told by Michael

Lorenz that “the City viewed it as a collaboration between the City and RVSC.” He stated that it is still owed $151,880 for which it was seeking judgment against the City.

On cross-examination, Buzbee testified that all the invoices were directed to Webb, never the City. He further testified, “We never received any document from the City indicating we had won a bid. We have no agreement with the City that it will be responsible for the goods and services we delivered to the project, but the City has possession of the boxes and light poles.”

On redirect, Buzbee stated that the City’s resolution referenced $458,000, the exact amount of B&A Electric’s bid. He contended that the City had not offered to pay B&A anything on the remaining balance.

James Griffith testified that he was hired by RVSC to do some woodwork for the project. He stated that he kept his costs at a certain level as requested by Webb. He said that he put up walls, set roof trusses, put roof decking in, and wrapped the buildings. He stated that he completed everything he was contracted to do and was still waiting to be paid the $20,337 for which he was seeking judgment against the City. He said that he contacted Webb for payment and attempted to contact the City three times, but the City never called back. He stated that although Webb was running the project, “we all believed the City was paying payments based on completion milestones.”

On cross-examination, Griffith stated that he gave a verbal bid to Webb and that he had no written agreement with the City to pay for his services. He stated that Webb

approved everything he did. He said that he realized he would not be paid when the City shut down the project. He further testified,

I put the responsibility on the City because it halted the project and stopped the funding. I decided to sue the City because the City controlled the money. I have no written or verbal agreement with the City. No representative of the City told me the City would cover my expenses for the project.

On redirect, Griffith said that it was common for him not to receive verbal or written agreements for payment. He stated that ordinarily, he could file a lien for nonpayment, but that is not an option against the City.

Shawn Megehee2 testified that he is the owner of Megehee Fence Contracting, LLC.

He said that he was asked by Webb to perform work for the project and that he was aware that the project was on land owned by the City. He said that his company installed all the fencing per the agreement. He also stated that he left materials in Webb’s yard and warehouse that subsequently disappeared. He testified that he billed RVSC for $45,482.08 but only received payment in the amount of $30,500. He was seeking judgment against the City for the remaining amount owed.

After the close of the contractors’ case, the City moved for directed verdict on both claims. The court denied the motion.

Jeff Dingham, deputy city administrator for the City of Fort Smith, testified that the City was initially contacted by Files and Webb in 2011 about a sports complex. He said that

2 The transcript reflects the last name as McGehee, but for purposes of this opinion, we will refer to it as Megehee.

Free access — add to your briefcase to read the full text and ask questions with AI

City of Forth Smith v. B&A Electric, Inc., 2023 Ark. App. 24 (Ark. Ct. App. 2023).

2023 Ark. App. 24 (City of Forth Smith v. B&A Electric, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Hardin v. Bishop
2013 Ark. 395 (Supreme Court of Arkansas, 2013)
City of Bryant v. Collins
386 S.W.3d 699 (Court of Appeals of Arkansas, 2011)
City of Fort Smith, Arkansas v. B & a Electric, Inc.
2019 Ark. App. 575 (Court of Appeals of Arkansas, 2019)
Mark Hunter v. Patricia A. Keck
2020 Ark. App. 233 (Court of Appeals of Arkansas, 2020)
City of Fort Smith, Arkansas v. B & a Electric, Inc.
2021 Ark. App. 334 (Court of Appeals of Arkansas, 2021)