City of Forth Smith v. B&A Electric, Inc.

2023 Ark. App. 24
CourtCourt of Appeals of Arkansas
DecidedJanuary 25, 2023
StatusPublished

This text of 2023 Ark. App. 24 (City of Forth Smith v. B&A Electric, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Forth Smith v. B&A Electric, Inc., 2023 Ark. App. 24 (Ark. Ct. App. 2023).

Opinion

Cite as 2023 Ark. App. 24 ARKANSAS COURT OF APPEALS DIVISION I No. CV-21-569

CITY OF FORT SMITH Opinion Delivered January 25, 2023 APPELLANT APPEAL FROM THE SEBASTIAN COUNTY CIRCUIT COURT, V. FORT SMITH DISTRICT [NO. 66FCV-17-285] B&A ELECTRIC, INC.; MEGEHEE FENCE CONTRACTING, LLC; GRIMES HONORABLE STEPHEN TABOR, DOZER SERVICE, INC.; JAMES JUDGE GRIFFITH; AND RIVER VALLEY SPORTS COMPLEX, INC. APPELLEES REVERSED AND DISMISSED

WAYMOND M. BROWN, Judge

The City of Fort Smith (the City) appeals the Sebastian County Circuit Court’s entry

of judgment against it following a jury verdict on breach-of-contract claims brought by

appellees B&A Electric, Inc.; Megehee Fence Contracting, LLC; Grimes Dozer Service, Inc.;

and James Griffith (the contractors), hired by third-party defendant River Valley Sports

Complex, Inc. (RVSC). The City contends that the evidence was insufficient to support the

judgment in favor of the contractors. We agree. Therefore, we reverse and dismiss this

action.1

1 This is the third time this case has been before us—we dismissed it twice for lack of a final order. See City of Fort Smith v. B&A Electric, Inc., 2019 Ark. App. 575; City of Fort Smith v. B&A Electric, Inc., 2021 Ark. App. 334. The City and RVSC entered into a written contract in March 2014 for the

construction of a sports complex on city-owned land after RVSC principals Jake Files and

Lee Webb presented the project to the city board. The City agreed to contribute up to $1.6

million in amounts payable when construction reached specific milestones. RVSC solicited

donations to cover the remaining costs of the project. The contract required RVSC to

complete the project by June 10, 2015, but stated that after construction was complete, the

City would lease the complex back to RVSC for ten years.

RVSC began work on the project in 2014, and it hired the four appellees as

contractors to provide materials and services. By the scheduled completion date, however,

RVSC had not substantially completed the work. Work continued into 2016 as a result of

two negotiated extensions granted by the City. The City paid RVSC over $1.08 million, but

in early 2017, RVSC permanently ceased working on the project after having failed to meet

the deadline extensions. When RVSC abandoned the project, it owed all four contractors

payment for work and materials they had already provided. The contractors sought payment

from RVSC, but RVSC did not have sufficient funds to pay. The contractors then sued the

City for breach of contract and unjust enrichment. The City filed a third-party complaint

against RVSC for breach of contract and contractual indemnity.

The case went to trial before a jury in September 2018. Terry Bailey, the bookkeeper

and corporate secretary for Grimes Dozer Service, testified that she compiled and submitted

invoices to RVSC between 2014 and 2016. She stated that Grimes had been paid for all the

work performed except $12,977.50 for which it was seeking judgment against the City.

2 On cross-examination, Bailey stated that all the invoices were directed to Webb

because its agreement was with RVSC. She said that it billed RVSC and received payments

from RVSC. She denied ever receiving checks from the City. She testified that Grimes

billed the City on advice from its attorney to do so after work on the project had stopped.

She said that Grimes was not paid after July 2016 “because RVSC did not receive another

draw from the City because RVSC had not completed the next phase, and there was no

money to pay us.”

On redirect, Bailey stated that she knew the land was owned by the City and that in

her mind, “the City would direct the money to RVSC and then to us.”

Brian Buzbee, part owner of B&A Electric, testified that he submitted budget

numbers to the City to provide lights, poles, and concrete bases for the softball fields in 2014

and that the City subsequently passed a resolution with that bid exhibited. He stated that it

received $40,000 as final payment, but it was expecting $100,000. He said that RVSC told

B&A Electric that “we weren’t getting any more money from the City.” He testified that he

met with his supplier, Upchurch Electric, and the city auditor, Tracey Shockley, and looked

at the site and what had been done up to that point. He said that he subsequently pulled

out all the panel “guts” and wiring it had installed to protect it from vandalism. He stated

that it had completed all the work for which invoices were submitted to RVSC or the City.

Buzbee testified that he attended a city board of directors meeting in March 2017 to inquire

about why RVSC was not required to submit a performance bond and was told by Michael

3 Lorenz that “the City viewed it as a collaboration between the City and RVSC.” He stated

that it is still owed $151,880 for which it was seeking judgment against the City.

On cross-examination, Buzbee testified that all the invoices were directed to Webb,

never the City. He further testified, “We never received any document from the City

indicating we had won a bid. We have no agreement with the City that it will be responsible

for the goods and services we delivered to the project, but the City has possession of the

boxes and light poles.”

On redirect, Buzbee stated that the City’s resolution referenced $458,000, the exact

amount of B&A Electric’s bid. He contended that the City had not offered to pay B&A

anything on the remaining balance.

James Griffith testified that he was hired by RVSC to do some woodwork for the

project. He stated that he kept his costs at a certain level as requested by Webb. He said

that he put up walls, set roof trusses, put roof decking in, and wrapped the buildings. He

stated that he completed everything he was contracted to do and was still waiting to be paid

the $20,337 for which he was seeking judgment against the City. He said that he contacted

Webb for payment and attempted to contact the City three times, but the City never called

back. He stated that although Webb was running the project, “we all believed the City was

paying payments based on completion milestones.”

On cross-examination, Griffith stated that he gave a verbal bid to Webb and that he

had no written agreement with the City to pay for his services. He stated that Webb

4 approved everything he did. He said that he realized he would not be paid when the City

shut down the project. He further testified,

I put the responsibility on the City because it halted the project and stopped the funding. I decided to sue the City because the City controlled the money. I have no written or verbal agreement with the City. No representative of the City told me the City would cover my expenses for the project.

On redirect, Griffith said that it was common for him not to receive verbal or written

agreements for payment. He stated that ordinarily, he could file a lien for nonpayment, but

that is not an option against the City.

Shawn Megehee2 testified that he is the owner of Megehee Fence Contracting, LLC.

He said that he was asked by Webb to perform work for the project and that he was aware

that the project was on land owned by the City. He said that his company installed all the

fencing per the agreement. He also stated that he left materials in Webb’s yard and

warehouse that subsequently disappeared. He testified that he billed RVSC for $45,482.08

but only received payment in the amount of $30,500.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hardin v. Bishop
2013 Ark. 395 (Supreme Court of Arkansas, 2013)
City of Bryant v. Collins
386 S.W.3d 699 (Court of Appeals of Arkansas, 2011)
City of Fort Smith, Arkansas v. B & a Electric, Inc.
2019 Ark. App. 575 (Court of Appeals of Arkansas, 2019)
Mark Hunter v. Patricia A. Keck
2020 Ark. App. 233 (Court of Appeals of Arkansas, 2020)
City of Fort Smith, Arkansas v. B & a Electric, Inc.
2021 Ark. App. 334 (Court of Appeals of Arkansas, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
2023 Ark. App. 24, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-forth-smith-v-ba-electric-inc-arkctapp-2023.