City of Fort Smith, Arkansas v. B & a Electric, Inc.
This text of 2019 Ark. App. 575 (City of Fort Smith, Arkansas v. B & a Electric, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Cite as 2019 Ark. App. 575 Digitally signed by Elizabeth ARKANSAS COURT OF APPEALS Perry Date: 2022.08.09 10:53:47 DIVISION III -05'00' No. CV-19-66 Adobe Acrobat version: 2022.001.20169 Opinion Delivered December 4, 2019 CITY OF FORT SMITH, ARKANSAS APPEAL FROM THE SEBASTIAN APPELLANT COUNTY CIRCUIT COURT, FORT SMITH DISTRICT V. [NO. 66FCV-17-285]
B & A ELECTRIC, INC.; MEGEHEE HONORABLE STEPHEN TABOR, FENCE CONTRACTING, LLC; GRIMES JUDGE DOZER SERVICE, INC.; JAMES GRIFFITH; AND RIVER VALLEY SPORTS COMPLEX, INC. DISMISSED WITHOUT PREJUDICE
APPELLEES
LARRY D. VAUGHT, Judge
The City of Fort Smith (the City) appeals the Sebastian County Circuit Court’s entry of
judgment against it for breach of contract in favor of B & A Electric, Inc.; Megehee Fence
Contracting, LLC; Grimes Dozer Service, Inc.; and James Griffith (the contractors), who were
hired by River Valley Sports Complex (RVSC) to construct a sports complex on City-owned
land. We dismiss this appeal without prejudice for lack of a final order.
The City and RVSC entered into a written contract in March 2014 for the construction
of a sports complex on City-owned land after RVSC principals Jake Files and Lee Webb
presented the project to the city board. The City agreed to contribute up to $1.6 million in
amounts payable when construction reached specific milestones. RVSC solicited donations to
cover the remaining costs of the project. The contract required RVSC to complete the project by June 10, 2015, but stated that after construction was complete, the City would lease the
complex back to RVSC for ten years.
RVSC began work on the project in 2014, and it hired the four appellees as contractors
to provide materials and services. By the scheduled completion date, however, RVSC had not
substantially completed the work. Work continued into 2016 as a result of two negotiated
extensions granted by the City. The City paid RVSC over $1.08 million, but in early 2017,
RVSC permanently ceased working on the project after having failed to meet the second
deadline extension. When RVSC abandoned the project, it owed all four contractors payment
for work and materials they had already provided. The contractors sought payment from
RVSC, but RVSC did not have sufficient funds to pay. The contractors then sued the City for
breach of contract and unjust enrichment. The City filed a third-party complaint against RVSC
for breach of contract and contractual indemnity.
The case went to trial before a jury. After the close of the contractors’ case, the City
moved for directed verdict on both claims. The court denied the motion. At the close of all
evidence, the City renewed its motion, which the court again denied. The jury returned verdicts
in favor of the contractors for the full amount of their requested damages on both their
breach-of-contract claims and their unjust-enrichment claims. The jury found in favor of
RVSC on the City’s third-party claims. The parties agreed that the jury’s verdicts granting relief
to the contractors on their breach-of-contract claims and unjust-enrichment claims were
incompatible, and with the consent of the parties, the court entered judgment against the City
on only the contractors’ breach-of-contract claims.
The court’s order, which erroneously stated that it had granted a directed verdict in
favor of RVSC and had dismissed the third-party complaint against it, went on to enter 2 judgment against the City on the contractors’ contract claims. The order does not address the
unjust-enrichment claim.
We must dismiss this appeal without prejudice for lack of a final and appealable order.
The court’s judgment does not mention or dispose of the contractors’ unjust-enrichment
claims. The City acknowledges in its brief that “there is—strictly speaking—no final judgment
on the unjust enrichment claims to appeal.” Moreover, both parties argue the merits of the
unjust-enrichment claims.
The Arkansas Supreme Court has repeatedly held that pursuant to Rule 54(b) of the
Arkansas Rules of Civil Procedure, an order is not final that adjudicates fewer than all the
claims or the rights and liabilities of fewer than all the parties. Bulsara v. Watkins, 2010 Ark.
453, at 5. In Bulsara, the jury found in favor of the defendant, Dr. Watkins, and the court
entered judgment dismissing with prejudice Bulsara’s claim against Dr. Watkins, but the
court’s judgment failed to address Dr. Watkins’s cross-claim against third-party defendant, St.
Vincent Doctor’s Hospital. The Arkansas Supreme Court dismissed the appeal without
prejudice due to lack of a final order, citing Rule 2(a)(1) of the Arkansas Rules of Appellate
Procedure–Civil, which provides that an appeal may be taken only from a final judgment or
decree entered by the trial court. Id. at 5. Consequently, we lack jurisdiction to decide the
merits of the present case because the order being appealed failed to dispose of the
contractors’ unjust-enrichment claims.
Dismissed without prejudice.
SWITZER and MURPHY, JJ., agree.
Gilker & Jones, P.A., by: Michael R. Jones, for appellant.
Walters, Gaston, Allison & Parker, by: Derick Allison, for appellees. 3
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
2019 Ark. App. 575, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-fort-smith-arkansas-v-b-a-electric-inc-arkctapp-2019.