City of Flint v. Chrisdom Properties, Ltd

770 N.W.2d 888, 283 Mich. App. 494
CourtMichigan Court of Appeals
DecidedApril 21, 2009
DocketDocket 283245
StatusPublished
Cited by10 cases

This text of 770 N.W.2d 888 (City of Flint v. Chrisdom Properties, Ltd) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Flint v. Chrisdom Properties, Ltd, 770 N.W.2d 888, 283 Mich. App. 494 (Mich. Ct. App. 2009).

Opinion

Davis, J.

Plaintiff/counter-defendant city of Flint (Flint) appeals as of right the trial court’s judgment in favor of defendants/counter-plaintiffs Chrisdom Properties, Ltd, and James Crawley (Chrisdom and Crawley). 1 We affirm.

This case arises out of a downtown housing development in the city of Flint. Trial testimony was lengthy and detailed, but, in a nutshell, Flint and Chrisdom entered into a loan agreement under which Flint extended $1.8 million from the federal Department of *496 Housing and Urban Development to Chrisdom for the purpose of converting two buildings into condominiums. One of those buildings was already owned by Crawley and 100 percent renter-occupied as a high-end apartment building and the other was an immediately adjacent dilapidated structure that Crawley had to purchase.

The loan agreement was poorly structured from the outset. However, Flint — indeed, the same department of the city that had been responsible for the loan — then inexplicably held up the issuance of a building permit to Chrisdom for 13 months after the Building Code Board of Appeals found that Chrisdom was entirely in compliance. Flint offered no justification for this; however, as a result, construction work could not be performed efficiently. Any possibility that the work could be performed within the timetable of the construction loan was abrogated by Flint. 2

It is worth noting that Crawley testified without contradiction that he had been involved in contracting in Flint for over 40 years and had been issued hundreds of permits. The normal amount of time to obtain a permit never exceeded two weeks. Also, the State Con *497 struction Code requires the issuance of a permit within 15 days after an application. MCL 125.1511. Flint argues that this deadline applies only when the application conforms to the code, but the year-long delay here was after the board of appeals determined that the Manhattan Place project was in compliance.

Additionally, Flint refused to allow any individual condominium units — some of which, having originally been apartments, were ready for sale — to be released from the general mortgage for sale to potential buyers. The construction loan agreement contained no provision governing such releases, but such releases are common in condominium construction projects, and the documents did imply that they should be granted. Further, the contract between the parties provided that Flint was to receive 100 percent of the condominium sale proceeds until such time as the loan made to the contractor was paid in full, which was an unusually good deal for the lender. Moreover, Flint was repeatedly advised that the only way its loan could be repaid was by selling the individual condominium units. Crawley testified that if he could have sold the existing units, he would have paid off the loan and have enough left over to finish the entire project.

Flint did not at any time attempt to provide any sort of justification for withholding the building permit or individual condominium releases short of asserting that it was not technically required to do so. Ultimately, Crawley and Chrisdom ran out of money, by which time Crawley had spent some $200,000 of his own money on the project and had gone without rental income from the now-empty apartment building for several years. 3 *498 Flint agreed to, and did, loan Chrisdom an additional $359,465, but it had still not issued a building permit, and Crawley explained that it would still be insufficient to complete the project unless individual condominium units were released from the general hen, which release was again denied.

Flint commenced the instant suit against defendants on November 3, 2004, generally alleging breach of contract and seeking foreclosure of the mortgage. Defendants counterclaimed on March 8, 2005, alleging breach of contract and slander. Midway through the trial, the trial court permitted defendants to amend their defenses and affirmative defenses to include frustration of purpose and impossibility, noting that the addition of those theories would not be prejudicial to Flint. 4 The trial court ultimately agreed with Chrisdom and Crawley that Flint had frustrated the purpose of the contract and breached the contract. The trial court then released Chrisdom and Crawley from any obligations under the loans or mortgages to Flint and awarded an additional cash amount, albeit with the expectation that it would be used to pay at least two known outstanding subcontractor liens. This appeal followed.

“We review the trial court’s findings of fact in a bench trial for clear error and conduct a review de novo of the court’s conclusions of law.” Chapdelaine v Sochocki, 247 Mich App 167, 169; 635 NW2d 339 (2001). “When reviewing a grant of equitable relief, an appellate court will set aside a trial court’s factual findings only if they are clearly erroneous, but whether equitable relief is proper under those facts is a question of law that an appellate court *499 reviews de novo.” McDonald v Farm Bureau Ins Co, 480 Mich 191, 197; 747 NW2d 811 (2008). This Court reviews de novo as a question of law the proper interpretation of a contract, including a trial court’s determination whether contractual language is ambiguous. Klapp v United Ins Group Agency, Inc, 468 Mich 459, 463; 663 NW2d 447 (2003).

Little published caselaw exists in Michigan on the doctrine of “frustration of purpose.” The parties agree that the only real leading case on point is Liggett Restaurant Group, Inc v City of Pontiac, 260 Mich App 127; 676 NW2d 633 (2003). There, this Court explained that “[illustration of purpose is generally asserted where ‘a change in circumstances makes one party’s performance virtually worthless to the other, frustrating his purpose in making the contract.’ ” Liggett Restaurant Group, supra at 133-134, quoting Restatement Contracts, 2d, § 265, comment a, p 335. Furthermore, “ ‘[t]he frustration must be so severe that it is not fairly to be regarded as within the risks that he assumed under the contract’ ” and “ ‘the non-occurrence of the frustrating event must have been a basic assumption on which the contract was made.’ ” Id. at 135, quoting Restatement, § 265, comment a, p 335. It is undisputed that Flint did two things: (1) delayed the issuance of a building permit by more than a year after the Board of Appeals determined that the buildings were actually in compliance, which prevented Chrisdom from proceeding in a timely fashion to meet the contract’s time requirements; and (2) refused to release individual ready-to-sell condominium units from the general lien despite being repeatedly advised that there was no other way to pay off the mortgage or to complete the project.

Flint primarily argues that Chrisdom assumed the risk that no building permit would be issued because such delays are predictable and Chrisdom represented *500

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Resource Point LLC v. Addolux LLC
Michigan Court of Appeals, 2018
Grand/Sakwa of Northfield, LLC v. Northfield Township
304 Mich. App. 137 (Michigan Court of Appeals, 2014)
System Soft Technologies, LLC v. Artemis Technologies, Inc.
837 N.W.2d 449 (Michigan Court of Appeals, 2013)
Sal-Mar Royal Village, LLC v. Macomb County Treasurer
836 N.W.2d 236 (Michigan Court of Appeals, 2013)
31800 Wick Road Holdings, LLC v. Future Lodging-Airport, Inc.
848 F. Supp. 2d 757 (E.D. Michigan, 2012)
Butler v. Wayne County
798 N.W.2d 37 (Michigan Court of Appeals, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
770 N.W.2d 888, 283 Mich. App. 494, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-flint-v-chrisdom-properties-ltd-michctapp-2009.