City of Cleveland v. Cleveland Electric Illuminating Co.

684 N.E.2d 343, 115 Ohio App. 3d 1
CourtOhio Court of Appeals
DecidedSeptember 30, 1996
DocketNo. 69584.
StatusPublished
Cited by52 cases

This text of 684 N.E.2d 343 (City of Cleveland v. Cleveland Electric Illuminating Co.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Cleveland v. Cleveland Electric Illuminating Co., 684 N.E.2d 343, 115 Ohio App. 3d 1 (Ohio Ct. App. 1996).

Opinions

Karpinski, Judge.

Plaintiffs-appellants, city of Cleveland and American Municipal Power-Ohio (“AMP-Ohio”), appeal from the judgment of the trial court dismissing the case for lack of jurisdiction. Plaintiffs filed their complaint for declaratory and injunctive relief against defendant-appellee, Cleveland Electric Illuminating Company (“CEI”). The dispute arose when CEI refused to commit to transmitting a guaranteed level of power as requested by Cleveland Public Power (“CPP”) for the month of June 1995. The reason CEI gave for refusing was that one of its generating facilities was not operational because of repairs. Dismissing the complaint, the lower court apparently reasoned that the dispute was under the exclusive jurisdiction of the Federal Energy Regulatory Commission (“FERC”). For the reasons that follow, the judgment of the lower court is reversed and remanded.

According to plaintiffs’ brief, AMP-Ohio is a “not-for-profit Ohio corporation which is comprised of 77 Ohio municipalities that own and operate municipal electric utilities. AMP-Ohio supplies power and energy to some of its members, including CPP, and acts as agent for its members by acquiring power and energy as well as arranging for the transmission of the supplies to its member municipalities. AMP-Ohio serves as both a direct seller of power to its members and as an agent for the municipalities in arranging wholesale purchases of power and the subsequent transmission of power.”

CPP, which is a member of AMP-Ohio, is a municipal utility company owned and operated by the city of Cleveland. CEI is a privately owned utility company which generates electrical power. While CPP purchases some power (five percent) from CEI, the bulk of CPP’s power (ninety-five percent) is purchased *6 from sources other than CEI and sent to CPP through CEI transmission lines — a process known as “wheeling.” Because CPP is surrounded by CEI’s system, CPP is dependent upon CEI for transmission of power. For this wheeling service, CPP pays a service fee to CEI, which is the owner of the transmission lines used to wheel the electrical power.

CPP and CEI have experienced a litigious history together. In 1979 the Nuclear Regulatory Commission found that CEI committed antitrust violations. The NRC approved the licenses for the Davis-Besse and Perry nuclear power plants on the condition, inter alia, that CEI wheel power to various municipally owned utilities, including CPP. Toledo Edison Co. (1979), 10 NRC 265, at 398-401 and 406. The current agreement under which CEI provides power to CPP is the “CEI-Cleveland Agreement for Installation and Operation of a 138 kV Synchronous Interconnection” dated October 18, 1985.

The heart of this dispute is CPP’s request for a commitment by CEI to transmit, on a firm basis, power generated by other utility companies. 1 In June 1994, CPP reserved seventy-two megawatts (“MW”) of firm transmission service. In May 1995, CPP requested, and CEI agreed to provide, one hundred twenty-five MW of firm transmission service. Later, on May 11, 1995, CPP requested an additional sixty-two MW of firm service. Thus, the total requested firm transmission service was one hundred eighty-seven MW.

CEI informed CPP that it would provide twenty-five MW of the additionally requested sixty-two MW on a firm basis. This would leave thirty-seven MW of the requested one hundred eighty-seven MW on a nonfirm basis. CEI claimed that the denial to provide the last thirty-seven MW on a firm basis was for only five weeks because one of its power-generating facilities, Ashtabula # 5 Unit, was out of service.

CPP argues that the following portion of the October 18, 1985 agreement is central to this dispute. Section 3(a) of this agreement states as follows:

“TECO [Toledo Edison Company] and CEI shall each engage in wheeling under appropriate tariffs and at the request of AMP-0 and its members, as long as such requested wheeling is not to a retail customer, and such wheeling shall be provided on a daily, weekly, monthly or annual basis at the request of AMP-0 or its members. TECO and CEI further agree that such wheeling service shall be available with respect to any unused capacity on the transmission lines of either, the use of which will not jeopardize the utility’s transmission system. In the event that a reduction in wheeling service due to lack of capacity becomes *7 necessary, reductions in service will be made to AMP-0 or its members on a non-discriminatory basis sicbject to constraints imposed by actual operating conditions. It is also understood that TECO’s and CEI’s obligations to wheel power pursuant to this paragraph of the agreement include the provision for transmission service into, out of, or through their service territories, including between points wholly within the service territory of either of them.” (Emphasis added.)

CPP contends that the refusal to provide the entire requested firm service amounted to a reduction on a discriminatory basis prohibited by the agreement. CPP argues that the refusal to provide the requested amount is discriminatory because, in the event the amount of production is lessened, the reduction in service will be borne entirely by CPP and its customers. CEI counters that this dispute is controlled by certain tariffs, as opposed to the agreement. 2

On May 31, 1995, CPP filed a complaint in common pleas court seeking injunctive and declaratory relief to enforce the contract between CPP and CEI. After a hearing, the common pleas court, on June 2,1995, denied the motion for a temporary restraining order (“TRO”). The trial court did not explain the basis for its decision. On August 23, 1995, the court granted CEI’s motion to dismiss, for lack of jurisdiction. The city and AMP-Ohio timely appealed, raising three assignments of error as follows:

“I. The lower court erred in finding that it did not have jurisdiction to grant immediate injunctive relief to enforce a contract between utility companies and municipal electric utilities.
“II. The lower court erred in finding that it did not have jurisdiction to interpret and enforce a contract between utility companies and municipal electric utilities.
“HI. The lower court erred in dismissing an action for lack of jurisdiction when the court had concurrent jurisdiction over the subject matter.”

These three assignments will be discussed together because each raises the issue of whether the trial court has jurisdiction over this matter. The standard of review when a complaint is dismissed under Civ.R. 12(B)(1) is “whether any cause of action cognizable by the forum has been raised.” State ex rel. Bush v. Spurlock (1989), 42 Ohio St.3d 77, 80, 537 N.E.2d 641, 644.

*8 CEI argues that the question in the breach of contract issue is now moot. CEI could continue, however, to refuse to transmit power each time it is requested, and the question of whether CEI breached its contractual obligation could return. Mootness, therefore, is avoided because this is an issue capable of repetition yet evading review. See

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Apple-Chamberlain v. Apple
2025 Ohio 5388 (Ohio Court of Appeals, 2025)
Twang, L.L.C. v. Cincinnati
2024 Ohio 6077 (Ohio Court of Appeals, 2024)
Columbus v. State
2023 Ohio 2858 (Ohio Court of Appeals, 2023)
Redding v. United States Parachute Assn., Inc.
2023 Ohio 884 (Ohio Court of Appeals, 2023)
Khemsara v. Ohio Veterinary Med. Licensing Bd.
2022 Ohio 833 (Ohio Court of Appeals, 2022)
MetroHealth Sys. v. Khandelwal
2022 Ohio 77 (Ohio Court of Appeals, 2022)
State ex rel. Bowling v. DeWine
2021 Ohio 2902 (Ohio Court of Appeals, 2021)
Gionino's Pizzeria, Inc. v. Reynolds
2021 Ohio 1289 (Ohio Court of Appeals, 2021)
Newburgh Hts. v. State
2021 Ohio 61 (Ohio Court of Appeals, 2021)
Ohio Democratic Party v. LaRose
2020 Ohio 4778 (Ohio Court of Appeals, 2020)
Lamar Advantage GP Co. v. City of Cincinnati
114 N.E.3d 805 (Court of Common Pleas of Ohio, Hamilton County, 2018)
Intralot, Inc. v. Blair
2018 Ohio 3873 (Ohio Court of Appeals, 2018)
AIDS Taskforce of Greater Cleveland v. Ohio Dept. of Health
2018 Ohio 2727 (Ohio Court of Appeals, 2018)
Graham v. City of Lakewood
113 N.E.3d 44 (Court of Appeals of Ohio, Eighth District, Cuyahoga County, 2018)
Gardner v. Vill. of Windham
2017 Ohio 5632 (Ohio Court of Appeals, 2017)
Youngstown City School Dist. Bd. of Edn. v. State
2017 Ohio 555 (Ohio Court of Appeals, 2017)
Connor Group v. Raney
2016 Ohio 2959 (Ohio Court of Appeals, 2016)
Bromberg v. Carter
2016 Ohio 2966 (Ohio Court of Appeals, 2016)
Newcomer v. Roan
2016 Ohio 541 (Ohio Court of Appeals, 2016)
Byers DiPaola Castle, L.L.C. v. Portage Cty. Commrs.
2015 Ohio 3089 (Ohio Court of Appeals, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
684 N.E.2d 343, 115 Ohio App. 3d 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-cleveland-v-cleveland-electric-illuminating-co-ohioctapp-1996.