City of Chubbuck v. City of Pocatello

899 P.2d 411, 127 Idaho 198
CourtIdaho Supreme Court
DecidedMarch 28, 1995
Docket20941, 21253
StatusPublished
Cited by59 cases

This text of 899 P.2d 411 (City of Chubbuck v. City of Pocatello) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Chubbuck v. City of Pocatello, 899 P.2d 411, 127 Idaho 198 (Idaho 1995).

Opinion

REINHARDT, Justice Pro Tem.

I.

BACKGROUND AND FACTS

In 1972, the City of Chubbuck (Chubbuck) and the City of Pocatello (Pocatello) entered into a wastewater treatment contract. Under the terms of the contract, Chubbuck developed a wastewater collection system to deliver Chubbuck’s wastewater to Pocatello, where the wastewater was treated at the Pocatello wastewater treatment facility.

In 1983, after the original contract expired, Chubbuck and Pocatello entered into a new contract. Although the terms of the new contract allowed the Pocatello City Council to set wastewater treatment rates by resolution, Pocatello’s authority was limited to setting rates that provide sufficient revenue for Po-catello to recoup its allocated cost of service. Under the terms of the contract, the allocated cost of service was to be determined by a three-year study conducted by the Black and Veatch engineering firm. The study was conducted to assist Pocatello in setting water and wastewater treatment rates. From the effective date of the contract, December 1, 1983, through 1990, Pocatello charged Chub-buck wastewater treatment rates sufficient to recoup an eleven percent rate of return on the allocated cost of treatment determined in the 1983 Black and Veatch study.

In 1989, Pocatello hired Black and Veatch to conduct another study to appraise the cost of service allocation for providing wastewater treatment to various customers, including Chubbuck. The second study, which was completed in 1990, differed from the 1988 *200 study in two significant respects. First, the rate of return on investment recommended in the 1990 study was three percent lower than the rate of return proposed in the 1983 study. This difference apparently reflects a change in prevailing interest rates between 1983 and 1990. The second difference between the studies was the method used to calculate the value of the treatment facility. The 1983 study was based on the net value of the treatment facility. The 1990 study based the cost of service allocation on the total value of the plant. This difference in valuation increased the estimated capital investment in the facility from $4,683,000 under the 1983 study to $12,790,500 under the 1990 study. Although offset somewhat by the decreased rate of return, this valuation resulted in an increase in the rate Chubbuck residents were charged for wastewater treatment.

Chubbuck filed a notice of claim with the Pocatello City Clerk and then filed this action against Pocatello in district court. Chubbuck alleged four causes of action against Pocatello. In its complaint, Chub-buck claimed: (1) that Pocatello breached the contract by charging rates that were not “based upon the 1983 Black and Veatch study,” as required by the contract; (2) that Pocatello violated the Revenue Bond Act by operating the facility primarily as a source of revenue; (3) that, in violation of federal regulations, Pocatello used factors other than actual wastewater use as the basis of its rates; and (4) that Pocatello charged a rate in excess of that authorized by statute. Based on the above, essentially undisputed evidence, Pocatello and Chubbuck filed cross-motions for summary judgment. The district court granted summary judgment in favor of Poca-tello, holding that the record revealed no disputed issues of material fact and Pocatello was entitled to judgment as a matter of law on all four causes of action stated by Chub-buck.

The district court also awarded attorney fees to Pocatello under I.C. § 12-120(3). After a subsequent hearing before a different district judge on the issue of costs and attorney fees, Pocatello was awarded $1,058.70 for costs as a matter of right, $8,415.41 for discretionary costs, and $30,000 for attorney fees. Chubbuck appeals the summary judgment in favor of Pocatello, claiming that the trial court erred in either concluding that Pocatello did not breach the contract with Chubbuck or in concluding that Chubbuck was not entitled to relief on the alternative grounds of quasi-estoppel. Chubbuck also appeals the dismissal of Chubbuek’s objection to the award of costs and attorney fees to Pocatello.

II.

STANDARD OF REVIEW

Rule 56(c) of the Idaho Rules of Civil Procedure direct the trial court to enter summary judgment “when the pleadings, depositions, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” When this Court reviews the trial court’s ruling on such a motion, this Court employs the same standard properly employed by the trial court when originally ruling on the motion. Friel v. Boise City Hous. Auth., 126 Idaho 484, 485, 887 P.2d 29, 30 (1994). Both this Court and the district court must liberally construe the record in favor of the party opposing the motion, drawing all reasonable inferences and conclusions supported by the record in favor of that party. Id.; Farm Credit Bank of Spokane v. Stevenson, 125 Idaho 270, 272, 869 P.2d 1365, 1367 (1994).

The standard applied when ruling on or reviewing the ruling on a motion for summary judgment is not lessened simply because both parties have moved for summary judgment. Kromrei v. AID Ins. Co., 110 Idaho 549, 551, 716 P.2d 1321, 1323 (1986); Farmer’s Ins. of Idaho v. Brown, 97 Idaho 380, 381-82, 544 P.2d 1150, 1151-52 (1976). However, when both parties move for summary judgment on the same issues and legal theories based on the same, essentially uncontroverted facts, the record is unlikely to reveal any genuine issue of material fact. See Kromrei 110 Idaho at 551, 716 P.2d at 1323 (“However, where, as in the present case, both parties have moved for summary judgment based on the same evi- *201 dentiary facts and the same issues and theories, they have effectively stipulated that there is no genuine issue of material fact and summary judgment is therefor appropriate.”)- In order to determine whether either party is entitled to summary judgment, this Court must examine each motion separately, reviewing the record and the reasonable inferences that can be drawn from it in favor of each party’s opposition to the motions for summary judgment.

III.

POCATELLO BREACHED THE WASTEWATER TREATMENT CONTRACT

If the terms of a contract are clear and unambiguous, the interpretation of the contract’s meaning is a question of law. E.g., Ada County Assessor v. Taylor, 124 Idaho 550, 553, 861 P.2d 1215, 1218 (1993). If, on the other hand, the terms of a contract are ambiguous, the interpretation of that contract’s meaning is a question of fact. Id.; Bondy v. Levy, 121 Idaho 993, 997, 829 P.2d 1342, 1346 (1992).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marquette v. Falck
Idaho Court of Appeals, 2024
Lipps v. Nye
Idaho Court of Appeals, 2024
Weitz v. Weitz
477 P.3d 987 (Idaho Supreme Court, 2020)
Manwaring Investments, L.C. v. City of Blackfoot
405 P.3d 22 (Idaho Supreme Court, 2017)
Jerry Machado v. Charles L. Ryan
280 P.3d 715 (Idaho Supreme Court, 2012)
McDevitt v. Sportsman's Warehouse, Inc.
255 P.3d 1166 (Idaho Supreme Court, 2011)
Van v. Portneuf Medical Center
212 P.3d 982 (Idaho Supreme Court, 2009)
Best Hill Coalition v. HALKO, LLC
172 P.3d 1088 (Idaho Supreme Court, 2007)
Lane Ranch Partnership v. City of Sun Valley
166 P.3d 374 (Idaho Supreme Court, 2007)
Potts Construction Co. v. North Kootenai Water District
116 P.3d 8 (Idaho Supreme Court, 2005)
McKay v. Boise Project Board of Control
111 P.3d 148 (Idaho Supreme Court, 2005)
Shawver v. Huckleberry Estates, L.L.C.
93 P.3d 685 (Idaho Supreme Court, 2004)
McColm-Traska v. Baker
88 P.3d 767 (Idaho Supreme Court, 2004)
Pinehaven Planning Board v. Brooks
70 P.3d 664 (Idaho Supreme Court, 2003)
Farrell v. Board of Com'rs, Lemhi County
64 P.3d 304 (Idaho Supreme Court, 2002)
Canty v. Idaho State Tax Commission
59 P.3d 983 (Idaho Supreme Court, 2002)
D & M Country Estates Homeowners Ass'n v. Romriell
59 P.3d 965 (Idaho Supreme Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
899 P.2d 411, 127 Idaho 198, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-chubbuck-v-city-of-pocatello-idaho-1995.