City of Chicago v. Water Pipe Extension

Procedural entryThis page is a short order in City of Chicago v. Water Pipe Extension. Read the opinion of the Court — 302 Ill. App. 3d 940
Appellate Court of Illinois·Decided January 29, 1999·No. 1-97-3538·Published

Opinion

SIXTH DIVISION  

JANUARY 29, 1999

Nos. 1-97-3538 and 1-97-3539 (Consolidated)

CITY OF CHICAGO, ) APPEAL FROM THE

a municipal corporation, ) CIRCUIT COURT

) OF COOK COUNTY.

Plaintiff-Appellant/ )

Cross-Appellee, )

)

v. ) No. 95 CH 8461

WATER PIPE EXTENSION, BUREAU OF )

ENGINEERING LABORERS' LOCAL NO. 1092, )

) HONORABLE

Defendant-Appellee/ ) AARON JAFFE,

Cross-Appellant. ) JUDGE PRESIDING.

PRESIDING JUSTICE CAMPBELL delivered the opinion of the court:

Plaintiff City of Chicago (City) appeals an order of the circuit court of Cook County denying its petition to vacate part of an arbitration award rendered in a labor arbitration between the City and defendant Water Pipe Extension, Bureau of Engineer­

ing Laborers' Local No. 1092 (Union, Local 1092).  Defendant cross-appeals the trial court's order denying the Union's peti­

tion to vacate a different part of the same arbitration award that was decided in favor of the City.

The record on appeal indicates the following facts.  The City is an Illinois municipal corporation and a "public employer" within the meaning of the Illinois Public Labor Relations Act (Act) (5 ILCS 315/3(o) (West 1994)).  Local 1092 is a "labor organization" within the meaning of the Act (5 ILCS 315/3(i) (West 1994)).  

The City and the Union are parties to a collective bargain­

ing agreement (CBA), which became effective January 1, 1992.  This case primarily involves Article 9 of the CBA, which address­

es "Hours of Work and Overtime."  Section 9.1 of the CBA states the purpose of Article 9:

"This Article is intended to define the workweek, establish schedules and serve as the basis for the calculation of overtime.  It shall not be construes as a guarantee of work or hours for any day or week except as ex­pressly provided herein.  Under no circum­

stances shall hours be changed solely to avoid the payment of overtime."

Section 9.3.2 of the CBA, which addresses changes of work shifts and schedules, provides in part that:

"Whenever the City believes it is neces­

sary to temporarily change (a) a scheduled shift assignment or (b) the starting time for such assignment outside the *** normal start­

ing times for shifts the Union shall be given at least ten (10) days notice and shall be ad­vised as to the reason for the changes(s) and the dura­tion thereof.  In an emergency situa­tion the City shall give as much notice as possible.  As soon as the tempo­rary necessity is alleviated normal assignment and scheduling shall be resumed.

* * * * *

The appropriate rate of overtime shall be applicable to all hours worked before or after an employee's regular­ly assigned shift and no starting time or shift sched­ule will be estab­lished or altered for the purpose of avoiding payment of overtime."

Section 9.7.1 of the CBA addresses payment for overtime work.  Generally, all work in excess of 8 hours in a workday is to be paid at 1 ½ times the standard pay rate.  Work in excess of 10 ½ hours in a workday is to be paid at 2 times the standard pay rate.  The first 8 hours of a sixth workday in a workweek is to be paid at 1 ½ times the standard pay rate, and 2 times the standard rate thereafter.  Work performed on a seventh workday in a work week is to be paid at 2 times the standard rate.

Section 9.12 of the CBA addresses "Degree Days," providing in part as follows:

"(a) Locals 1001 and 76.  In accordance with cur­rent practice, in Departments which historically cur­tailed operations due to low temperature and/or other weather factors, the Standard Temperature Station will be the Air­

port determined by the Department.  A depart­

ment will not change the traditional historic factors at which its operators have been curtailed without notice to and consul­tation with the Union.

(b)  This section shall not apply to Local 1092."

On or about February 3 and March 14, 1994, the Union filed grievances against the City, alleging violations of the CBA.  Grievance 1994-3 alleged that on or about January 17, 1994, the City's Water Department temporarily changed shifts for laborers to two 12 hour shifts, failed to notify the Union of the change and paid the employees only the regular pay for the first 8 hours of each shift.  Grievances 1994-5 and 1994-6 alleged that the City's Sewer Department and Water Department, respectively, temporarily changed the shifts of laborers "assigned to snow removal under Phase III, effective February 23, 1994," and these employees were not paid overtime for the shifts worked or regular pay for shifts lost due to the alteration or cancellation of shifts.

On February 1, 1995, the grievances were submitted to arbi­

tration before Edwin H. Benn.  The record shows that between 1989 and 1994, Benn issued 3 awards in arbitrating 14 prior shift change grievances between the parties.  Benn heard the 3 griev­

ances at issue in this case on February 1 and 27, 1995.

The testimony at the hearing establishes that on January 17, 1994, the temperature was between 15 and 20 degrees below zero, with wind chills falling between 50 and 60 degrees below zero.  Joseph Gagliano, the Deputy Commissioner of Operations in the Sewer Department, with responsibility for managing the Mainte­

nance Division handling sewer cleaning and repair, and Deputy Commis­sioner Dennis Connolly decided to shut down operations for January 18, 1994, and to "take one day at a time."

Gagliano telephoned Union Secretary Treasurer Robert LoVerde to inform him that Gagliano was considering knocking off the employees with a "NW" (no work) or vacation day.  Connolly told LoVerde that a facsimile would be sent notifying him of the deci­

sion for January 18 and possibly January 19.  Operations were ultimately cancelled for both days.  Gagliano testified, however, that no one called the Union to inform it of the decision regard­

ing January 19, 1994.

On January 19, 1994, Gagliano received a telephone call from Robert Magnuson of the Water Department, who stated that an exces­sive number of water main breaks caused by the cold weather re­quired the assistance of 30 laborers and 10 hoisting engineers from 8 p.m. to 8 a.m.  Gagliano testified that he telephoned LoVerde to notify the Union of shift changes that would be re­quired to accommodate this need.  In his testimony, LoVerde ini­

tially denied receiving a call from Gagliano on January 19, 1994, but later stated that he did not recall receiving a call from Gagliano, but may have.

On February 23, 1994, between 10 a.m. and 10:30 a.m., Gagli­

ano was notified that "Phase III snow removal" was being activat­

ed.  "Phase III snow removal" is declared when a snowfall is between 7 and 11 inches, and requires the cooperation of a number of City Departments under the direction of the Department of Streets and Sanitation.

Free access — add to your briefcase to read the full text and ask questions with AI

City of Chicago v. Water Pipe Extension, (Ill. Ct. App. 1999).

City of Chicago v. Water Pipe Extension (City of Chicago v. Water Pipe Extension) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related