City of Chesterfield v. Frederich Construction Inc. and Traveler's Casualty and Surety Company of America

475 S.W.3d 708, 2015 Mo. App. LEXIS 439
CourtMissouri Court of Appeals
DecidedApril 21, 2015
DocketED101916
StatusPublished
Cited by2 cases

This text of 475 S.W.3d 708 (City of Chesterfield v. Frederich Construction Inc. and Traveler's Casualty and Surety Company of America) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Chesterfield v. Frederich Construction Inc. and Traveler's Casualty and Surety Company of America, 475 S.W.3d 708, 2015 Mo. App. LEXIS 439 (Mo. Ct. App. 2015).

Opinion

Gary M. Gaertner, Jr., Judge

Introduction

The City of Chesterfield (City) appeals the judgment of the trial court confirming an arbitration award that included an award of attorneys’ fees against the City. The City argues the arbitrators exceeded their authority in awarding attorneys’ fees. We affirm.

Background

The City hired Respondent Frederich Construction, Inc. (FCI) to be the general contractor on two construction projects for the City. The City and FCI executed separate contracts for each of the two projects on June 16, 2009 and December 8, 2009, respectively. Respondent' Traveler’s Casualty and Surety Company of America (Travelers) was the surety for FCI under both contracts. Both contracts contained provisions stating that all disputes between the parties would be subject to arbitration under the Construction Industry Arbitration Rules of the American Arbitration Association (AAA).

Disputes arose under both contracts, and the parties submitted them to arbitration in accordance with their agreements. The arbitrators resolved both disputes in favor of FCI. The first award, dated September 24, -2012, included attorneys’ fees of $50,000. The trial court confirmed the award on April 29, 2013, and the City did not appeal that judgment.

In the second arbitration award, dated May 28, 2013 (Final Award), the arbitrators also awarded attorneys’ fees to FCI in the amount of $279,037. The City filed a petition in interpleader and a motion to vacate the Final Award’s grant of attorneys’ fees in the trial court. The City argued that the arbitrators exceeded their authority in awarding attorneys’ fees in the Final Award because the contract between the City and FCI contained no provision allowing for attorneys’ fees, and AAA rules did not authorize such fees under the circumstances. The trial court denied the City’s motion- to vacate attorneys’ fees and confirmed the Final Award. This appeal follows.

Standard of Review

“Given the purposes of arbitration as an alternative to litigation, judicial oversight of arbitration'is narrow and strictly limited.” Behnen v. A.G. Edwards & Sons. Inc., 285 S.W.3d 777, 779 (MoApp.E.D.2009). Section 435.405.1 1 contains the only grounds upon which a court may vacate an arbitration award. Doyle v. Thomas, 109 S.W.3d 215, 219 (Mo.App.E.D.2003) (court' is limited to specific grounds laid out in statute). “Section 435.405.1- sets *710 forth five possible grounds for vacating an arbitration award, only one of which is relevant here: . “where ... [t]he arbitrators exceeded their powers.” Section 435.405.1(3).

Whether the arbitrators exceeded their powers is a legal question we review de novo: Behnen, 285 S.W.3d at 779. However, we may not vacate an award simply because we would have interpreted the agreement or the facts differently. See Sheffield Assembly of God Church, Inc. v. Am. Ins. Co., 870 S.W.2d 926, 931 (Mo.App.W.D.1994) (citing Lorenzini v. Group Health Plan, Inc., 753 S.W.2d 106, 108 (Mo.App.E.D.1988)) (“[m]istakes of law [or] fact ... are not a sufficient reason to vacate an award”). Section 435.405.1(5) states “the fact that the relief was such that it could not or would not be granted by a court of law or equity is not ground for vacating or refusing to confirm the award.” See Behnen, 285 S.W.3d at 780 n. 4 (noting clause from subsection (5) applies to all of Section 435.405.1 as a whole). We may vacate the award based on an excess of the arbitrators’ power “only if the' arbitrators decided matters which were beyond the scope of the agreement or were clearly not submitted to them.” Id. at 779.

Discussion

The City raises two points on appeal, both contesting the trial court’s confirmation of the award of attorneys’ fees contained in the Final Award. In both points, the, City argues the trial court erred in confirming the Final Award because the arbitrators exceeded their authority in awarding attorneys’ fees. Thus, we address both points together.

Here, in the Final Award, the arbitrar tors noted that there was no contractual provision specifically authorizing an award of attorneys’ fees, nor was there statutory authority for such an award. The arbitrators also noted that no special circumstances were present that would justify an award of attorneys’ fees.. The arbitrators ultimately concluded they were authorized to resolve the issue of attorneys’ fees because the contract incorporated AAA rules, which allow arbitrators to award attorneys' fees where all parties request them. We agree.

First, the parties agree that their contract incorporated AAA rules. Specifically, AAA Rule R-45 addresses awards of attorneys’ fees as follows:

(d) The award of the arbitrator may include:
[[Image here]]
(ii) an award of attorneys’ fees if all parties have requested such an award —

It was undisputed that FCI requested attorneys’ fees. Additionally, the arbitrators found that the City requested attorneys’ fees twice: in the prayers for relief of the City’s amended answer and counterclaim, respectively. The City’s answer contained the following prayer for relief:

WHEREFORE, the ... City requests that FCI’s claims be denied in their entirety, and that the City be granted an award of the relief prayed -for by the City’s Counterclaim, including ... attorneys’ fees ..., to which the City may be entitled pursuant to the AAA Construction Industry Arbitration Rules.

In the City's counterclaim, the prayer for relief contained seven different requests, denominated A through G, the last two of which are relevant:

F. The costs and expenses of this proceeding, including but not limited to all AAA fees, expenses and arbitrator compensation as provided by AAA Rule[] R-45....
G. The City’s reasonable attorney fees, expert witness fees, and all other ex *711 penses and costs incurred and to be incurred by the City in connection with this arbitration proceeding.

The City disputed this finding in the trial court because the arbitrators also entered Scheduling and Procedure Order No. 1 (Procedure Order), which provided that “[a]ny party seeking an award of attorney’s fees or costs following the interim award shall file, its application stating its ... request within ten (10) days of the issuance of the interim award.” The City argued that it never requested attorneys’ fees in accordance with this order, but rather after the panel’s interim award in favor of FCI, the City has only disputed that the arbitrators were authorized to award attorneys’ fees.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
475 S.W.3d 708, 2015 Mo. App. LEXIS 439, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-chesterfield-v-frederich-construction-inc-and-travelers-casualty-moctapp-2015.