This text of 159 S.E. 38 (City of Charleston v. Public Service Commission) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Charleston v. Public Service Commission, 159 S.E. 38, 110 W. Va. 245, 1931 W. Va. LEXIS 62 (W. Va. 1931).

Opinion

Hatcher, Judge:

This hearing involves orders entered by the Public Service Commission on August 16th and December 4, 1930. The orders were entered in an investigation by the commission of the rates charged the protestants for gas by United Fuel Gas Company. The result of the investigation is a very substantial increase in the rates. The majority of the commission *247 (hereinafter referred to as the commission for the sake of brevity) fixed the fair value of the utility’s property as on December 31, 1928, as follows :

Production system . $15,146,352
Transmission system . 17,793,598
Distribution system . 3,935,193
General property . 951,254
$37,826,397
Going concern value . 3,171,021
$40,997,418
Leaseholds .... 7,914,037
Total ... $48,911,455

Included in the valuation of the physical property ($37,-826,397) are allowances for general overheads of 20% on the cost of labor and materials in the transmission system and of 17% on such cost in the other three items. The going concern value is “10% of the estimated value of labor and materials in the plant depreciated, and exclusive of land and general overheads.” (Statement of commission). The value accorded the leaseholds is their “adjusted” book value. The commission estimated that $12,200,000 (of the $48,911,455) was the value of the utility’s property appropriated to the use of consumers within the state. On the property so appropriated $109,800 was allowed for depreciation, and $506,-300 for amortization. Tariff rates for consumers were then approved, which after furnishing enough revenue to pay operating expenses, including taxes, should also provide the allowances for depreciation and amortization and a net return of 8% to the utility.

The duty imposed upon the commission in cases such as this is that it shall “enter such orders as may be just and lawful.” Code 1923, chapter 15-0, section 2. 'A like charge is given to this Court upon appeal, as the statutory injunction to us differs only in words: ‘ ‘ The court shall decide the matter in controversy as may seem to be just and right.” Code, supra, section 17. Despite the obvious legislative invi *248 tation to us to become a fact finding body, we have persistently held that because the commission is “experienced in rates and familiar with the intricacies of rate making” we will ordinarily not substitute our judgment for that of the commission on controverted evidence. Town v. Gas Co., 103 W. Va. 526, 529. Our position was clearly stated in Gas Co. v. Commission, 101 W. Va. 63: “An order of the Public Service Commission fixing rates to be charged by a public service utility, within the constitutional and legislative power of the commission, will not be disturbed unless it appears that the finding of fact on which the order is based is contrary to evidence, or without evidence, or there has been mis-appli-cation of legal principles: and where there is a substantial conflict of evidence on any question of fact, the probative value accorded by the commission to such evidence will not be disturbed.”

The statistician of the commission, Mr. E. V. Williamson, made a thorough investigation of the utility and reported that the original cost of its physical properties -was $36,183,-011 (not'depreciated). Mr. John Jirgal, an expert accountant, engaged by the protestante, fixed that cost from the books of the utility at $37,916,873 (not depreciated). The opinion of the majority of the commission reflects no consideration whatever of the Williamson and Jirgal reports so far as they deal with this subject. Mr. F. IT. Lerch, Jr. (of Ford, Bacon & Davis, engineers) filed a valuation report on behalf of the utility, in which he estimated the cost of reproducing new the physical properties of the utility at $53,972,197, as on December 31, 1928. Of this sum, the estimate for general overhead charges was $9,847,102 and for labor and material, $44,125,095 which was depreciated to $32,-846,1.25. Mr. Lerch fixed the going value of the utility at $5,397,220 or 10% of his estimated reproduction cost new. Mr. J. Paul Blundon, an experienced engineer, filed a similar report on behalf of the protestants in which he estimated the reproduction cost, new, of the same property at $42,286,-901. Of this estimate $5,188,314 was for'general overheads, and $37,098,587 for labor, and material which he depreciated to $22,069,430. We find no estimate of going value by Mr. *249 Blundon, but Mr. Earl L. Carter, an experienced engineer, appearing for protestants, estimated the going value at $4,500,000. The commission (as shown by its opinion) adopted the estimates of Mr. Lereb of the costs of material and labor (without general overheads) requisite to reconstruct new, the physical properties of the utility. The commission also adopted bis calculation of depreciation except as to an increase of $854,804 on a certain well equipment account, to meet the decision in the Clarksburg Light & Heat Company case, P. U. R. 1928 B 290, 313. Much of the briefs of the contestants is devoted to an attack upon the qualifications and conclusions of Mr. Lereb, and to the support of Mr. Blundon. The utility responds warmly in kind, attacking Mr. Blundon and supporting Mr. Lereb. Both of these gentlemen are evidently competent .and of very high standing. The wide divergencies between them may be accounted for on the supposition that, without volition, neither could be entirely “unmindful of bis client’s interest.” Light Co. v. State (N. H.) 120 Atl. 689. Be that as it may, we would not be so inconsistent with the position stated above as to pass generally on the merits of the Lereh-Blundon controversy. Nor is it necessary to go into details, because it was improper for the commission to base the valuation of the physical properties exclusively upon reconstruction cost, new, less depreciation. “ * * * the cost of reproduction, new, less depreciation, is to be accepted merely as an element and not as the standard of value.” City v. The Commission, 101 W. Va. 378, 381. “The cost of reproduction new should not be made the basis of a gas plant rate valuation, although it will be given some weight.” Springfield v. Gas & Elec. Co., P. U. R. (Illinois) 1916C 281.

The commission seems to have been led into this error partly by the belief that a similar appraisal of this utility’s property by Ford, Bacon & Davis “formed the basis for the commission’s findings in the 1924 rate ease.” This belief is not borne out by the opinion in that ease. That opinion states expressly that “the use to which this physical property is put, the book cost, the historical cost estimate, the reproduction cost new, less depreciation estimates” were all con *250 sidered. See p. 276, 2 P. S. C. of W. Va.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chesapeake & Potomac Telephone Co. v. Public Service Commission
300 S.E.2d 607 (West Virginia Supreme Court, 1982)
Monongahela Power Co. v. Public Service Comm.
276 S.E.2d 179 (West Virginia Supreme Court, 1981)
Preston County Light & Power Co. v. Public Service Commission
297 F. Supp. 759 (S.D. West Virginia, 1969)
Western Maryland Railway Co. v. Public Service Commission
106 S.E.2d 923 (West Virginia Supreme Court, 1959)
Miller v. Huntington & Ohio Bridge Co.
15 S.E.2d 687 (West Virginia Supreme Court, 1941)
City of Wheeling v. Natural Gas Co. of West Virginia
175 S.E. 339 (West Virginia Supreme Court, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
159 S.E. 38, 110 W. Va. 245, 1931 W. Va. LEXIS 62, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-charleston-v-public-service-commission-wva-1931.