City of Carmel-by-the-Sea v. United States Department of Transportation

123 F.3d 1142
Court of Appeals for the Ninth Circuit·Decided August 19, 1997·No. No. 94-16234·Published·Cited by 9 cases

Opinions

BEEZER, Circuit Judge:

ORDER

The Opinion filed September 13, 1996, is withdrawn.

OPINION

This appeal arises from the proposed realignment of California State Highway 1 from the City of Carmel-by-the-Sea to nearby Hatton Canyon. The responsible governmental agencies studied this proposal and others and issued an Environmental Impact Statement/Report as required by state and federal law.

Plaintiffs City of Carmel-by-the-Sea, Monterey Peninsula Regional Park District, Hatton Canyon Coalition and Sierra Club challenged the adequacy of this statement/report under the National Environmental Policy Act, California Environmental Quality Act and Executive Orders 11988 and 11990. The district court granted summary judgment in favor of the defendants. Plaintiffs filed this timely appeal.

We have jurisdiction pursuant to 28 U.S.C. § 1291. We affirm in part, reverse in part and remand.

I

California State Highway 1 (Highway 1) extends from San Clemente in Orange County to Rockport in Mendocino County, California. Over an approximately three-mile stretch through the City of Carmel-by-the-Sea (City of Carmel), motorists traveling on Highway 1 confront severe congestion at peak hours. Highway 1 begins as a four-lane divided highway at the northern end of this section, near the Highway 68 interchange. As Highway 1 passes through the City of Carmel it funnels into a two-lane undivided highway, south of Ocean Avenue. Over the next several miles Highway 1 is controlled, [1148] and congested, by three traffic lights and numerous flanking intersections and driveways. The lack of sufficient left-turning lanes adds to the traffic problem.

California transportation officials list this stretch of Highway 1 as: “one of the most heavily traveled two-lane highways in the State.” 7 SAR 2083.1 This section of Highway 1 is also dangerous: the rate of traffic accidents in this two-lane section of Highway 1 exceeds the state average. 24 SAR 7652. In 1990, traffic reached an average of 40,000 cars per day and an average of 60,000 cars per day at one location on this stretch. 24 SAR 7650. This volume increases during weekends and the summer months. 24 SAR 7651.

Highway l’s traffic problems date back to the late 1940’s. No one today disputes the need for improvements; rather, disagreement centers on how best to achieve those improvements. Variations on two alternative proposals have dominated the list of solutions for forty years: (1) widen Highway 1 or (2) build a new route. The primary location identified for a new route was, and remains, Hatton Canyon, a pristine “wilderness” area east of the City of Carmel. Disagreement over these alternatives has resulted, unwittingly, in the exercise of a third option: no action.

The Highway 1 debate has been both public and passionate. The 10,000-page administrative record is replete with evidence of the detailed and emotional attention this issue has received. Further complicating the process, several localities, agencies and environmental groups involved have reversed their positions on the issue over time. Many who once supported the Hatton Canyon proposal now vigorously oppose it. They argue that the proposal will destroy Hatton Canyon’s unique ecosystem while only saving motorists a few minutes of driving time at peak hours. Not surprisingly proponents of the Hatton Canyon proposal dismiss this as hyperbole, and note instead that the Hatton Canyon project will ameliorate traffic congestion, accident rates and air quality, while maintaining the rural and scenic character of Highway 1.

In 1984, the California Department of Transportation (Caltrans) and the Federal Highway Administration began serving jointly as the “lead agencies” on the project. In 1986 they published a combined Draft Environmental Impact Statement/ Environmental Impact Report as required by the National Environmental Policy Act, 42 U.S.C. §§ 4321 et seq., and the California Environmental Quality Act, Cal.Pub.Res.Code § 21000 et seq.2 The Draft Environmental Impact Statement/Report’s stated purpose was to: “improve the capacity of Highway 1 and reduce crossing and turning conflicts associated with several local streets and private driveways.” 11 SAR 3121. Several alternatives — primarily variations on the Hatton Canyon and Highway 1 proposals — were analyzed. 11 SAR 3129-52.

The Draft Environmental Impact Statement/Report generated numerous comments from citizens, federal and state agencies, and environmental groups, among others. The Hatton Canyon Coalition, a plaintiff here, submitted a report prepared by Wilbur Smith Associates, an engineering firm, and Skidmore, Owings & Merrill, an arehitec-ture/planning firm (Smith Report), which recommended converting Highway 1 into a four-lane highway with two major interchanges. 24 SAR 7389-87.

In 1991, the Federal Highway Administration and Caltrans issued their Final Environmental Impact Statement/Report. The report/statement addressed many of the comments submitted in response to the [1149] Draft Environmental Impact Statement/Report and generally provided a more focused analysis. The Final Environmental Impact Statement/Report’s “Purpose and Need” section, for example, defined more precisely the desired Level of Service, an industry traffic category, setting Level of Service C as a project goal. 24 SAR 7648. Level of Service C refers to a category of “traffic service,” which describes traffic flow. Traffic conditions are ranked between Level of Service A (“free flow, with low volumes and high speeds”) and Level of Service F (“forced flow operation at low speeds, where volumes are below capacity”).3

The Environmental Impact Statement/Report recommended the adoption of Alternative 1C Modified, the Hatton Canyon realignment. This proposal includes a hew 57-foot bridge over the Carmel River, two new interchanges and the widening of an intersecting road. 24 SAR 7633. The estimated cost for this proposal was approximately $33.5 million. 24 SAR 7662.

Free access — add to your briefcase to read the full text and ask questions with AI

City of Carmel-by-the-Sea v. United States Department of Transportation, 123 F.3d 1142 (9th Cir. 1997).

123 F.3d 1142 (City of Carmel-by-the-Sea v. United States Department of Transportation) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

City of Ridgeland v. National Park Service
253 F. Supp. 2d 888 (S.D. Mississippi, 2002)
Kettle Range Conservation Group v. United States Forest Service
148 F. Supp. 2d 1107 (E.D. Washington, 2001)
Middle Rio Grande Conservancy District v. Babbitt
206 F. Supp. 2d 1156 (D. New Mexico, 2000)
Sierra Club v. United States
23 F. Supp. 2d 1132 (N.D. California, 1998)
Friends Of Southeast's Future v. Morrison
153 F.3d 1059 (Ninth Circuit, 1998)