City of Canton v. Public Utilities Commission

407 N.E.2d 9, 63 Ohio St. 2d 76, 17 Ohio Op. 3d 46, 1980 Ohio LEXIS 774
CourtOhio Supreme Court
DecidedJuly 9, 1980
DocketNos. 79-1032 and 79-1033
StatusPublished
Cited by11 cases

This text of 407 N.E.2d 9 (City of Canton v. Public Utilities Commission) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Canton v. Public Utilities Commission, 407 N.E.2d 9, 63 Ohio St. 2d 76, 17 Ohio Op. 3d 46, 1980 Ohio LEXIS 774 (Ohio 1980).

Opinions

Per Curiam.

The principal issue presented for resolution is whether the dedicated facilities method used by the [79]*79commission to allocate rate base property and expenses to Kaiser and Ormet was reasonable and lawful. R. C. 4903.13. Appellants argue that the dedicated facilities or direct assignment approach to allocating rate base property and expenses to Kaiser and Ormet is unreasonable, as this approach is justified only where the property allocated to the ratepayer is exclusively used by that ratepayer. Furthermore, appellants challenge this allocation procedure on the basis that it fails to allocate sufficient costs to Kaiser and Ormet, thereby causing other ratepayers to subsidize operations of Ohio Power for which they receive no benefit.

In Ohio Edison Co. v. Pub. Util. Comm. (1962), 173 Ohio St. 478, this court recognized, at page 483, that the determination of the proper method of allocation for a public utility is a controversial problem for which no one standard may be imposed. Thus, it was concluded in Ohio Edison, at page 484, that, * * *as long as the method [of allocation] chosen by the commission is not unreasonable, this court should not disturb it.” It was noted further that, in such matters, the appropriate question is not whether the method of allocation used is the best method, but it is “whether the method of allocation used***by the commission is reasonable.” Id.

The commission’s staff, upon completing its investigation into the instant application as required by R. C. 4909.19, filed its report with the commission and concluded that, upon a review of the special contracts between Ohio Power and Kaiser and Ormet, “the dedicated*** [facilities] method of exclusion, as opposed to the peak responsibility method of exclusion,” was the appropriate one. During the hearing, staff witness William F. Fox explicated the staff’s rationale for adopting this approach:

“After reviewing the history of both Kaiser’s and Ormet’s relations with Ohio Power and considering the character of their load characteristics, the Staff is of the opinion that the other jurisdictional customers have benefited over the years due to the existence of these contracts. At the time the contracts were entered into, the dedicated plant method resulted in higher charges to Kaiser and Ormet than the existing average cost per MW to other customers. As additional and more expensive plant was added to serve these [80]*80other customers, but not directly Kaiser and Ormet, the average cost per MW is now higher than the dedicated plant charges. Staff is of the opinion that the dedicated plant concept was proper and accepted in the past and it is still proper today and should be accepted for purposes of this proceeding.”

The commission, in adopting the staff approach, based its conclusion in part upon its previous opinion and order in case No. 75-161-EL-SLF, wherein it reviewed the contracts between Ohio Power and Kaiser and Ormet.1 Because the provisions of these contracts as currently in effect called for the use of the dedicated facilities approach in pricing service delivered to these industrial users, the commission concluded that use of this approach does not constitute an unreasonable basis to determine costs in the allocation process. Based upon an analysis of this concept as used in the past by Ohio Power and other industrial power users, the commission determined that the dedicated facilities method was appropriate, notwithstanding the fact that the property directly assigned to Kaiser and Ormet was not exclusively used by these companies. This conclusion, insofar as it was applicable to Ormet, was supported by the testimony of appellants’ chief witness, Dr. Caroline M. Smith, who conceded that this allocation procedure was to some extent justified for Ormet based upon the “historical development of the Ohio Power-Ormet Relationship.” Therefore, upon a review of the evidence submitted, we are not convinced under the facts at bar that the dedicated facilities allocation method must by definition be [81]*81limited to those instances where the ratepayer is served exclusively by identifiable plant or property of the utility.

As a secondary challenge to the allocation method employed by the commission, appellants argue that the dedicated facilities allocation method fails to remove from the rate base all costs attributable to service delivered to Kaiser and Ormet. Appellants argue that the commission’s use of this allocation procedure has the effect of shifting costs of service attributable to Kaiser and Ormet to Ohio Power’s remaining ratepayers in violation of R. C. 4905.33 and 4905.35.2

Staff witness Fox testified that before the staff accepted the applicant’s proposal to exclude Kaiser and Ormet by direct assignment, “the Staff spent a large amount of time reviewing much of the data and testimony filed in case No. 75-161-EL-SLF,” as well as the “resulting Opinion and Order.” Fox indicated that the commission found “ ‘***the dedicated facilities concept as employed in the subject contracts does assign cost to Ormet and Kaiser on a basis related to cost causation.***It is apparent that if there were ever customers who’s [sic] power needs warranted special arrangements with a utility, Ormet and Kaiser would have to be viewed as prime candidates. Certainly the extent and nature of their service requirements set them apart from the generality of Ohio Power’s customers and provide a reasonable basis for classifying them for rate purposes. The contracts under which Ormet and Kaiser are billed are carefully drafted instruments which were entered into only after exclusive arm’s length negotiations between highly sophisticated parties. The rights and obligations detailed therein [82]*82represent a balancing of interests and needs of those parties and the Commission seriously doubts if such a balance would be struck or maintained if these customers were served pursuant to general rate schedules.’ ”

When queried relative to whether the ratepayers in the instant case were bearing any burden (costs) associated with the service delivered pursuant to the Kaiser and Ormet contracts, witness Fox stated, in essence, that they were not. This testimony conflicts with the testimony submitted by appellants’ expert, Smith, who stated in summary that the allocation procedure adopted by the staff, and thereafter by the commission, resulted in “excessive revenue burdens to jurisdictional customers whose rates are affected by this proceeding.”

Upon a review of the evidence in the record, we do not conclude that the allocation procedure employed by the commission in these proceedings violated the provisions of R. C. 4905.33 or 4905.35. Whether the allocation method in fact shifted costs from the special contracts to the jurisdictional ratepayers is an evidentiary question. “This court with regard to evidentiary matters does not review a finding and order of the commission de novo. Where conflicting evidence is presented to the commission with regard to a matter at issue, the commission’s determination will not be disturbed unless the party who challenges that finding demonstrates that it is manifestly against the weight of the evidence and so clearly unsupported by the record in the cause as to demonstrate misapprehension, mistake, or willful disregard of duty.” Masury Water Co. v. Pub. Util. Comm. (1979), 58 Ohio St. 2d 147, 148-149.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Columbus Southern Power Co. v. Pub. Util. Comm.
1993 Ohio 67 (Ohio Supreme Court, 1993)
Columbus Southern Power Co. v. Public Utilities Commission
620 N.E.2d 835 (Ohio Supreme Court, 1993)
Consumers' Counsel v. Pub. Util. Comm.
1992 Ohio 122 (Ohio Supreme Court, 1992)
United States v. Aloi
773 F. Supp. 55 (N.D. Ohio, 1991)
Allen v. Public Utilities Commission
532 N.E.2d 1307 (Ohio Supreme Court, 1988)
Porter v. Miller
468 N.E.2d 134 (Ohio Court of Appeals, 1983)
Sandefur Co. v. Jones
458 N.E.2d 390 (Ohio Court of Appeals, 1982)
GMS Management Co. v. Axe
449 N.E.2d 43 (City of Cleveland Municipal Court, 1982)
Office of Consumers' Counsel v. Public Utilities Commission
413 N.E.2d 799 (Ohio Supreme Court, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
407 N.E.2d 9, 63 Ohio St. 2d 76, 17 Ohio Op. 3d 46, 1980 Ohio LEXIS 774, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-canton-v-public-utilities-commission-ohio-1980.