City of Burlington v. Zurn Industries, Inc.

135 F. Supp. 2d 454, 2001 U.S. Dist. LEXIS 4743, 2001 WL 285849
CourtDistrict Court, D. Vermont
DecidedMarch 21, 2001
Docket1:99-cv-00404
StatusPublished
Cited by7 cases

This text of 135 F. Supp. 2d 454 (City of Burlington v. Zurn Industries, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Burlington v. Zurn Industries, Inc., 135 F. Supp. 2d 454, 2001 U.S. Dist. LEXIS 4743, 2001 WL 285849 (D. Vt. 2001).

Opinion

Opinion and Order

(Papers 46 and 49)

MURTHA, Chief Judge.

The City of Burlington (City) has brought this action alleging that Defendants Zurn Industries, Inc., Zurn EPC Services, Inc., Aalborg Industries, Inc. (collectively Zurn) and Hartford Steam Boiler Inspection and Insurance Company (Hartford) breached their contract with the City when Defendants sold, installed and certified for inspection a faulty economizer boiler system in the City’s wood-fired steam generator. The City also contends that Zurn acted negligently in performing under the contract and in subsequently failing to discover the boiler’s defects. Finally, it contends that, after an inspection of the boiler, Zurn and Hartford negligently misrepresented that the boiler complied with the ASME Boiler and Pressure Vessel Code.

Defendant Zurn Industries, Inc. moves for summary judgment pursuant to Fed. R.Civ.P. 56(c), asserting that under the terms reached in earlier negotiations, the City released Zurn from all future claims involving “any equipment” related to the boiler. Zurn also argues that the City’s claims are barred by a contract provision that t required any breach of contract claims be brought within 18 months of the completion and initial firing of the boiler. Zurn further argues that because the City *457 was on notice of the boiler problems by 1988, its 1999 claims are barred by the state statute of limitations. See 12 V.S.A. § 511. Finally, Zurn contends that the City’s negligence claims are barred because Vermont law does not permit negligence claims where the alleged injury is purely economic.

In its cross motion for summary judgment, the City requests that Zurn’s affirmative defense of release from liability as the result of Burlington Electric Department’s Performance Supervisor Thomas Carr’s assurances should be dismissed as a matter of law.

For the reasons set forth below, Zurn’s motion for summary judgment is DENIED in part and GRANTED in part. The City’s cross motion is DENIED.

Background

In 1982, the City and BED finalized a purchase order agreement (# 102) with Zurn to design, manufacture and erect an economizer boiler for the City’s wood-fired steam generator, the McNeil Station. The economizer consisted of metal tubing which Zurn welded together to create the boiler. Zurn completed the work in February 1984 and the boiler began operating in March. The agreement specified that all causes of action arising as a result of the contract must be brought within 18 months of the completion of the erection and initial firing of the boiler.

Between September 1984 and April 1986, Zurn and the City worked through a number of outstanding issues relating to each party’s performance requirements under the contract. After negotiations, the parties apparently resolved these issues. On April 23, 1986, BED’S Production Superintendent, Thomas Carr, provided Zurn with a letter which stated:

In consideration of the concessions given by Zurn Industries in this matter, as mutually agreed to in our meeting on 1 April 1986, B.E.D. releases Zurn from any further obligation to bear costs associated with -the malfunction or failure to perform of any equipment furnished by Zurn on B.E.D. Purchase Order #102.

Paper 47 at 4.

In February 1987, the economizer leaked for the first time in the area where the tubes had been welded. A second leak, again at a weld, occurred in July 1988. John Irving, BED’s plant manager, reported the leaks in the station’s monthly operating reports. Irving noted that he believed the leaks were the result of weld failures attributable to faulty installation. 'Thereafter, the weld leaks apparently began to increase in frequency with 27 weld failures occurring between April 1995 and March 1999. BED performed a radio-graphic examination of the welds and discovered that the leaks resulted from a lack of full weld penetration. All 516 welds in the boiler’s lower section revealed a lack of full penetration.

Analysis

I. Summary Judgment Standard

Summary judgment is appropriate if “there is no genuine issue as to any material fact, and ... the moving party is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(c). This standard places the initial burden on the moving party to identify “those portions of the ‘pleadings, depositions, answers to interrogatories, and admissions on file, together with affidavits, if any,’ which it believes demonstrate the absence of a genuine issue of material fact.” Celotex Corp. v. Catrett, 477 U.S. 317, 323, 106 S.Ct. 2548, 2553, 91 L.Ed.2d 265 (1986) (quoting Fed.R.Civ.P. 56(c)). Once the moving party has demonstrated the absence of any genuine issue of *458 material fact, the non-moving party “must set forth specific facts showing that there is a genuine issue for trial.” Fed.R.Civ.P. 56(c). The court must read all facts in the light most favorable to the non-moving party. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 254, 106 S.Ct. 2505, 2513, 91 L.Ed.2d 202 (1986).

II. Breach of Contract

Neither party disputes the viability of the contract or the' failure of the welds. Rather Zurn asserts the City executed a release that effectively prevented the City from bringing any future suit against Zurn relating to its performance under the contract. In the alternative, Zurn argues that either the contractual time limitation on litigation or the state statute of limitations on contract actions, bars the suit.

A. The Release

The City argues that Zurn’s release defense is ineffective because BED’s board never authorized Carr to release Zurn from future obligations to bear costs associated with the malfunction or failure to perform of any equipment furnished by Zurn on BED Purchase Order # 102. On this basis, the City contends the Court should dismiss the defense. Zurn contests the City’s assertion, claiming the facts and circumstances surrounding Carr’s actions indicated that he had the authority to sign a release on behalf of BED and, therefore, because the City has released Zurn from liability, the Court should grant summary judgment on its behalf.

“As a general rule, the knowledge of an agent acting within the scope of his or her authority is chargeable to the principal, regardless of whether that knowledge is actually communicated.” Sawyer v. Crowell, 151 Vt. 287, 559 A.2d 687, 690 (1989). Actual authority may be express or implied.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moffitt v. Icynene, Inc.
407 F. Supp. 2d 591 (D. Vermont, 2005)
Town of Hartland v. Amerada Hess Corp.
399 F. Supp. 2d 242 (S.D. New York, 2005)
In Re Methyl Tertiary Butyl Ether (Mtbe) Products
399 F. Supp. 2d 242 (S.D. New York, 2005)
City of Burlington v. Zurn Industries, Inc.
73 F. App'x 504 (Second Circuit, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
135 F. Supp. 2d 454, 2001 U.S. Dist. LEXIS 4743, 2001 WL 285849, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-burlington-v-zurn-industries-inc-vtd-2001.