City of Benton v. Arkansas Soil & Water Conservation Commission

45 S.W.3d 805, 345 Ark. 249, 2001 Ark. LEXIS 356
CourtSupreme Court of Arkansas
DecidedJune 14, 2001
Docket01-00060
StatusPublished
Cited by19 cases

This text of 45 S.W.3d 805 (City of Benton v. Arkansas Soil & Water Conservation Commission) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Benton v. Arkansas Soil & Water Conservation Commission, 45 S.W.3d 805, 345 Ark. 249, 2001 Ark. LEXIS 356 (Ark. 2001).

Opinion

Annabelle Clinton Imber, Justice.

In January 1999, the City of Malvern submitted an application to the Arkansas Soil and Water Conservation Commission (“Commission”) seeking a determination of compliance with the Arkansas Water Plan. The water development project for which the City sought approval (hereinafter “Malvern Project”) was developed through the joint efforts of the City of Malvern, the Salem Water Users Association, the Southwest Water Users Association, and the Town of Tull. 1 Through the Malvern Project, these entities proposed to construct water treatment facilities and pipelines carrying water from the Ouachita River to the City of Malvern and to rural areas of Saline, Grant, and Garland Counties. The City of Benton and Saline County officials objected to the inclusion of rural Saline County in the areas to be serviced by the Malvern Project.

Before approving the Malvern Project, the Commission conducted three public hearings. First, on March 25, 1999, the Commission conducted a hearing at its headquarters in Little Rock. Following this hearing, the Commission’s staff issued its report to the Commission’s Executive Director, J. Randy Young, on July 12, 1999, recommending approval of the Malvern Project. Executive Director Young did not approve the project immediately, but opted instead to call two additional public meetings. On July 28, 1999, the Commission held a public hearing in Benton at which the Mayor of Benton and other representatives of Saline County and the City of Benton were present. The following day, a hearing was conducted in Malvern. Notice of these hearings was published in the Benton Courier and the Malvern Daily Record on July 16, 1999.

On August 6, 1999, the Commission’s Executive Director entered a Final Determination of Arkansas Water Plan Compliance, finding that the Malvern Project complied with the Arkansas Water Plan. The City of Benton and Saline County appealed that determination by the Executive Director to the full Commission. After a hearing before the full Commission on October 28, 1999, the Commission upheld and adopted the Executive Director’s Final Determination. The City of Benton and Saline County then appealed that decision to the Pulaski County Circuit Court. The Commission’s Final Determination was affirmed by the circuit court on October 3, 2000. The City of Benton and Saline County, appellants herein, now seek review of the Commission’s Final Determination in this court. They contend that the Final Determination is flawed as a result of several procedural irregularities that violated the Administrative Procedure Act and deprived them of constitutionally afforded due process. They further allege that the performance of administrative, regulatory, and adjudicative duties by the Executive Director and his staff created “bias and or at least an appearance of bias,” and that the Executive Director accepted and relied upon improper ex parte communications in making his final determination. Other points of error raised by the appellants include assertions that (1) the Commission failed to determine the status of the Salem Water Users Association, the Southwest Water Users Association, and the Quad County Facilities Board for the Town of Tull; (2) the Commission failed to refer environmental questions to the Arkansas Department of Environmental Quality and the Arkansas Pollution Control and Ecology Commission; and, (3) the Executive Director has an inherent conflict of interest due to his position on the Arkansas Pollution Control and Ecology Commission. Finally, appellants argue that the Pulaski County Circuit Court erred by denying their motion to enforce an agreed stay order entered by the court on April 3, 2000.

I. Standard of Review

It is not the role of the circuit courts or the appellate courts to conduct a de novo review of the record when reviewing an agency’s decision pursuant to the Administrative Procedure Act. Arkansas Dep’t of Human Servs. v. Thompson, 331 Ark. 181, 187, 959 S.W.2d 46 (1998). We review the case only to ascertain whether there is substantial evidence to support the agency’s decision 2 or whether the decision runs afoul of one of the other criteria set out in Ark. Code Ann. § 25-15-212(h) (Repl. 1999). Id.

Where the agency’s failure to follow its own procedural rules is urged on appeal, the applicable question on review is “whether the Commission’s decision is based upon unlawful procedure.” Stueart v. Arkansas State Police Comm’n, 329 Ark. 46, 50-51, 945 S.W.2d 377 (1997) (citing Regional Health Care Facilities, Inc. v. Rose Care, Inc., 322 Ark. 767, 912 S.W.2d 409 (1995)). “It has become axiomatic that an agency is bound by its own regulations.” Id. (quoting Panhandle Eastern Pipeline Co. v. F.E.R.C., 613 F.2d 1120 (D.C. Cir. 1979)). Thus, the decision of an administrative agency may be reversed if the substantial rights of the petitioner have been prejudiced because the administrative findings from which appeal is taken were made upon unlawful procedure. Id.

II. Violations of Due Process and the Administrative Procedure Act

Appellants assert several procedural violations that allegedly occurred during the hearings below and caused the loss of their substantial rights. First, appellants argue that the Commission failed to conduct a full and fair hearing regarding the Malvern Project. According to appellants, the hearings conducted were inadequate in four aspects: (1) the hearings were conducted in a quasi-legislative manner rather than a quasi-judicial manner; (2) notice was inadequate; (3) the Executive Director had already made his decision before the July hearings; and (4) the Executive Director inappropriately received and relied upon ex parte communications.

A. Quasi-Judicial Review

The proceedings below arose out of an application by the City of Malvern for a determination that its water development project complied with the Arkansas Water Plan.

No political subdivision or agency of the state shall spend any state funds on or engage in any water development project . . . until a preliminary survey and report therefor which sets forth the purpose of the project, the benefits to be expected, the general nature of the works of improvement, the necessity, feasibility, and the estimated cost thereof is filed with the commission and is approved by the commission to be in compliance with the plan.

Ark. Code Ann. § 15-22-504(e) (Repl. 2000). “The approval or disapproval of the application shall constitute an adjudication under the Arkansas Administrative Procedures Act. All action taken and all hearings conducted on the question of approval of the application shall be in compliance with the Arkansas Administrative Procedures Act.” S.W.C.C. Rule 604.1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

All Creatures Animal Hospital, Inc. v. Finova Capital Corp.
374 S.W.3d 38 (Court of Appeals of Arkansas, 2010)
Parkman v. Sex Offender Screening & Risk Assessment Committee
2009 Ark. 205 (Supreme Court of Arkansas, 2009)
Tucker v. Arkansas Office of Child Support Enforcement
247 S.W.3d 485 (Supreme Court of Arkansas, 2007)
Great Lakes Chemical Corp. v. Bruner
243 S.W.3d 285 (Supreme Court of Arkansas, 2006)
Ganey v. Kawasaki Motors Corp., U.S.A.
234 S.W.3d 838 (Supreme Court of Arkansas, 2006)
Pilcher v. Suttle Equipment Co.
223 S.W.3d 789 (Supreme Court of Arkansas, 2006)
Taylor v. Hamilton
205 S.W.3d 149 (Court of Appeals of Arkansas, 2005)
Rodriguez v. Arkansas Department of Human Services
200 S.W.3d 431 (Supreme Court of Arkansas, 2004)
Ginsburg v. Ginsburg
195 S.W.3d 898 (Supreme Court of Arkansas, 2004)
Arkansas Department of Human Services v. Campbell
189 S.W.3d 495 (Court of Appeals of Arkansas, 2004)
Omni Holding & Development Corp. v. 3D.S.A., Inc.
156 S.W.3d 228 (Supreme Court of Arkansas, 2004)
Rigsby v. Rigsby
149 S.W.3d 318 (Supreme Court of Arkansas, 2004)
Tsann Kuen Enterprises Co. v. Campbell
129 S.W.3d 822 (Supreme Court of Arkansas, 2003)
H.T. Hackney Co. v. Davis
120 S.W.3d 79 (Supreme Court of Arkansas, 2003)
Carter v. Four Seasons Funding Corp.
97 S.W.3d 387 (Supreme Court of Arkansas, 2003)
Barnes v. Everett
95 S.W.3d 740 (Supreme Court of Arkansas, 2003)
Arkansas Soil & Water Conservation Commission v. City of Bentonville
92 S.W.3d 47 (Supreme Court of Arkansas, 2002)
Opinion No.
Arkansas Attorney General Reports, 2002

Cite This Page — Counsel Stack

Bluebook (online)
45 S.W.3d 805, 345 Ark. 249, 2001 Ark. LEXIS 356, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-benton-v-arkansas-soil-water-conservation-commission-ark-2001.