City of Baldwin, Georgia v. Woodard & Curran

CourtCourt of Appeals of Georgia
DecidedJuly 11, 2012
DocketA12A0620
StatusPublished

This text of City of Baldwin, Georgia v. Woodard & Curran (City of Baldwin, Georgia v. Woodard & Curran) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Baldwin, Georgia v. Woodard & Curran, (Ga. Ct. App. 2012).

Opinion

FOURTH DIVISION DOYLE, P. J., ANDREWS and BOGGS, JJ.

NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. (Court of Appeals Rule 4 (b) and Rule 37 (b), February 21, 2008) http://www.gaappeals.us/rules/

July 11, 2012

In the Court of Appeals of Georgia A12A0620. CITY OF BALDWIN v. WOODARD & CURRAN, INC.

ANDREWS, Judge.

The City of Baldwin, Georgia (City) appeals after a jury awarded Woodard &

Curran, Inc. (W&C) $203,000 on its claim for money owed under a contract to

provide services for the City’s wastewater treatment plant. Because there was

sufficient evidence to support the award, we affirm.

The record shows that W&C sued for breach of a contract under which it was

to be paid for engineering and design services for the City’s water system (May

contract). W&C claimed that it provided supporting engineering documents for the

City’s application for government stimulus funds to improve the City’s wastewater

treatment plant under the May contract and also under a proposal submitted on June 15, 2009 (June proposal). The June proposal was signed by the mayor under

“authorization to proceed,” and provided that W&C would be paid a sum “not to

exceed $210,000.00.” In the alternative, the complaint asked for damages of

$203,870.44 as the value of the services provided to the City.

The City’s position was that it paid the $5,000 owed under the May contract

and that was the total amount due. The City stated in its Answer that the mayor’s

signing of the June proposal was an ultra vires act and was not binding on the City

because it was not approved by a quorum of the city council. The City also stated that

the June 2009 proposal was to secure funding and C&W failed to secure the funding;

therefore, the City was unable to proceed with the project.

The case went to trial and the evidence at trial, viewed in the light most

favorable to the jury’s verdict,1 was that W&C began operating the City’s wastewater

treatment plant in January 2008. In conjunction with an application for funding to

help improve the plant, W&C agreed to “provide the supporting engineering

documents . . . in order to convert this project from ‘fundable’ to ‘funded’ for a Lump

Sum fee of $5,000. . . . Under separate covers we will be preparing a scope, budget

and schedule for the actual design work for the Headwords (sic) and associated

1 Ferman v. Bailey, 292 Ga. App. 288, 289 (664 SE2d 285) (2008).

2 improvements (including the Design Development Report for the overall plant) and

also will submit a grant application to Rural Development to fund the development

of a capital master plan for the water and wastewater systems. Additional engineering

fees will only be contracted once funding has been committed.”

Brent Bridges, a senior vice-president with W&C testified that the $5,000, as

stated in the proposal, was to be paid for the documents to support the funding

application for stimulus money. The second part of the proposal agreed to in the May

2009 contract, was not covered by the $5,000 and involved supplying the design

engineering necessary to apply for funding.

The senior project manager at W&C testified that pursuant to the second part

of the May contract, there was a meeting with the Mayor and two city council

members and they authorized the second project of the May contract and authorized

payment of $210,000 for that work.

At this meeting with the mayor and council members, W&C was told to

proceed with the work necessary to continue the application process. This work

included hiring surveyors, hiring geo-technical core drillers, getting bids for the work,

and completing the design plans.

3 After the mayor signed the authorization to proceed, and as the work

progressed, the project engineer was asked to attend a city council meeting and

update the mayor and city council on the work that W&C was doing. The engineer

stated that he attended the meeting and described the work that was being done and

the status of the permits, applications, designs, specifications and reports. He testified

that the City owed W&C approximately $203,000 for this work.

The mayor who signed the June proposal testified that it was his understanding

that the full amount contracted for was the $5,000 and any additional engineering fees

would be contracted for once the funding was committed. The mayor said that he

signed the proposal for the additional work but did not date it because he could not

obligate the City by himself and it would have to be voted on by the council and

reviewed by the city attorney.

The mayor testified as to the benefit to the City if improvements were made to

the wastewater treatment plant, stating that improvements to the headworks would

have averted the possibility of substantial fines from the EPD. The mayor

acknowledged that he knew W&C was doing engineering work for the City in order

to obtain the stimulus money, and agreed that there was no question that W&C was

going to continue doing work for the City towards applying for the stimulus money.

4 The mayor said that he knew that deadlines existed and knew that the project must be

“shovel-ready by November 1[, 2009].”2

The mayor acknowledged that there was a council meeting attended by W&C

representatives in September at which the mayor and council were told that W&C was

going to have to do “engineering” for the project. The mayor said that he knew at that

time that “there was a good deal more to be done.” In addition, a tape was played for

the jury of this September meeting of the city council at which W&C told the council

about the work that had been completed and the work that still needed to be done in

order to file the application for funds.

The jury returned a verdict in favor of W&C in the amount of $203,000. The

City now appeals.

“Where a jury returns a verdict and it has the approval of the trial judge, the

same must be affirmed on appeal if there is any evidence to support it as the jurors are

the sole and exclusive judges of the weight and credit given the evidence. . . . The

appellate court must construe the evidence with every inference and presumption in

favor of upholding the verdict, and after judgment, the evidence must be construed

2 It appears that, through no fault of W&C, the stimulus funds were exhausted before the City submitted its application.

5 to uphold the verdict even where the evidence is in conflict. As long as there is some

evidence to support the verdict, the denial of defendant’s motions for new trial and

[j.n.o.v.] will not be disturbed.” Lofty v. Fuller, 223 Ga. App. 95, 97 (477 SE2d 30)

(1996).

1. The City contends that the trial court erred in allowing the claim for quantum

meruit to go to the jury. First, we note that the verdict form does not show whether

the award was made on the breach of contract claim or whether it was made on the

basis of the quantum meruit claim. The City did not request special findings and did

not object to the verdict form. This Court will not speculate as to the findings of fact

supporting the verdict. All Risk Ins. Agency v. Southern Bell Tel. &c. Co., 182 Ga.

App. 190, 192 (355 SE2d 465) (1987).

Further, we reject the City’s argument that H. G. Brown Family, L.P. v. City of

Villa Rica, 278 Ga.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Gainesville v. Edwards
145 S.E.2d 715 (Court of Appeals of Georgia, 1965)
Lofty v. Fuller
477 S.E.2d 30 (Court of Appeals of Georgia, 1996)
Knoxville Medical Investors, Ltd v. National Healthcorp L.P.
385 S.E.2d 110 (Court of Appeals of Georgia, 1989)
All Risk Insurance Agency, Inc. v. Southern Bell Telephone & Telegraph Co.
355 S.E.2d 465 (Court of Appeals of Georgia, 1987)
Cole v. Webb
598 S.E.2d 886 (Court of Appeals of Georgia, 2004)
Advance Security, Inc. v. Superior Surgical Manufacturing Co.
399 S.E.2d 488 (Court of Appeals of Georgia, 1990)
Waugh v. Waugh
595 S.E.2d 647 (Court of Appeals of Georgia, 2004)
Ferman v. Bailey
664 S.E.2d 285 (Court of Appeals of Georgia, 2008)
Walston & Associates, Inc. v. City of Atlanta
480 S.E.2d 917 (Court of Appeals of Georgia, 1997)
Hollifield v. Monte Vista Biblical Gardens, Inc.
553 S.E.2d 662 (Court of Appeals of Georgia, 2001)
Langford v. Robinson
612 S.E.2d 552 (Court of Appeals of Georgia, 2005)
PMS Construction Co. v. DeKalb County
257 S.E.2d 285 (Supreme Court of Georgia, 1979)
Amstead v. McFarland
650 S.E.2d 737 (Court of Appeals of Georgia, 2007)
Department of Transportation v. Patten Seed Co.
660 S.E.2d 30 (Court of Appeals of Georgia, 2008)
Touche Ross & Co. v. DASD CORP.
292 S.E.2d 84 (Court of Appeals of Georgia, 1982)
City of Saint Marys v. Stottler Stagg & Associates, Inc.
292 S.E.2d 868 (Court of Appeals of Georgia, 1982)
McLean v. Continental Wingate Co.
442 S.E.2d 276 (Court of Appeals of Georgia, 1994)
Nelson & Hill, P.A. v. Wood
537 S.E.2d 670 (Court of Appeals of Georgia, 2000)
GREER, KLOSIK AND DAUGHERTY v. Yetman
496 S.E.2d 693 (Supreme Court of Georgia, 1998)
H. G. Brown Family Ltd. Partnership v. City of Villa Rica
607 S.E.2d 883 (Supreme Court of Georgia, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
City of Baldwin, Georgia v. Woodard & Curran, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-baldwin-georgia-v-woodard-curran-gactapp-2012.