FOURTH DIVISION DOYLE, P. J., ANDREWS and BOGGS, JJ.
NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. (Court of Appeals Rule 4 (b) and Rule 37 (b), February 21, 2008) http://www.gaappeals.us/rules/
July 11, 2012
In the Court of Appeals of Georgia A12A0620. CITY OF BALDWIN v. WOODARD & CURRAN, INC.
ANDREWS, Judge.
The City of Baldwin, Georgia (City) appeals after a jury awarded Woodard &
Curran, Inc. (W&C) $203,000 on its claim for money owed under a contract to
provide services for the City’s wastewater treatment plant. Because there was
sufficient evidence to support the award, we affirm.
The record shows that W&C sued for breach of a contract under which it was
to be paid for engineering and design services for the City’s water system (May
contract). W&C claimed that it provided supporting engineering documents for the
City’s application for government stimulus funds to improve the City’s wastewater
treatment plant under the May contract and also under a proposal submitted on June 15, 2009 (June proposal). The June proposal was signed by the mayor under
“authorization to proceed,” and provided that W&C would be paid a sum “not to
exceed $210,000.00.” In the alternative, the complaint asked for damages of
$203,870.44 as the value of the services provided to the City.
The City’s position was that it paid the $5,000 owed under the May contract
and that was the total amount due. The City stated in its Answer that the mayor’s
signing of the June proposal was an ultra vires act and was not binding on the City
because it was not approved by a quorum of the city council. The City also stated that
the June 2009 proposal was to secure funding and C&W failed to secure the funding;
therefore, the City was unable to proceed with the project.
The case went to trial and the evidence at trial, viewed in the light most
favorable to the jury’s verdict,1 was that W&C began operating the City’s wastewater
treatment plant in January 2008. In conjunction with an application for funding to
help improve the plant, W&C agreed to “provide the supporting engineering
documents . . . in order to convert this project from ‘fundable’ to ‘funded’ for a Lump
Sum fee of $5,000. . . . Under separate covers we will be preparing a scope, budget
and schedule for the actual design work for the Headwords (sic) and associated
1 Ferman v. Bailey, 292 Ga. App. 288, 289 (664 SE2d 285) (2008).
2 improvements (including the Design Development Report for the overall plant) and
also will submit a grant application to Rural Development to fund the development
of a capital master plan for the water and wastewater systems. Additional engineering
fees will only be contracted once funding has been committed.”
Brent Bridges, a senior vice-president with W&C testified that the $5,000, as
stated in the proposal, was to be paid for the documents to support the funding
application for stimulus money. The second part of the proposal agreed to in the May
2009 contract, was not covered by the $5,000 and involved supplying the design
engineering necessary to apply for funding.
The senior project manager at W&C testified that pursuant to the second part
of the May contract, there was a meeting with the Mayor and two city council
members and they authorized the second project of the May contract and authorized
payment of $210,000 for that work.
At this meeting with the mayor and council members, W&C was told to
proceed with the work necessary to continue the application process. This work
included hiring surveyors, hiring geo-technical core drillers, getting bids for the work,
and completing the design plans.
3 After the mayor signed the authorization to proceed, and as the work
progressed, the project engineer was asked to attend a city council meeting and
update the mayor and city council on the work that W&C was doing. The engineer
stated that he attended the meeting and described the work that was being done and
the status of the permits, applications, designs, specifications and reports. He testified
that the City owed W&C approximately $203,000 for this work.
The mayor who signed the June proposal testified that it was his understanding
that the full amount contracted for was the $5,000 and any additional engineering fees
would be contracted for once the funding was committed. The mayor said that he
signed the proposal for the additional work but did not date it because he could not
obligate the City by himself and it would have to be voted on by the council and
reviewed by the city attorney.
The mayor testified as to the benefit to the City if improvements were made to
the wastewater treatment plant, stating that improvements to the headworks would
have averted the possibility of substantial fines from the EPD. The mayor
acknowledged that he knew W&C was doing engineering work for the City in order
to obtain the stimulus money, and agreed that there was no question that W&C was
going to continue doing work for the City towards applying for the stimulus money.
4 The mayor said that he knew that deadlines existed and knew that the project must be
“shovel-ready by November 1[, 2009].”2
The mayor acknowledged that there was a council meeting attended by W&C
representatives in September at which the mayor and council were told that W&C was
going to have to do “engineering” for the project. The mayor said that he knew at that
time that “there was a good deal more to be done.” In addition, a tape was played for
the jury of this September meeting of the city council at which W&C told the council
about the work that had been completed and the work that still needed to be done in
order to file the application for funds.
The jury returned a verdict in favor of W&C in the amount of $203,000. The
City now appeals.
“Where a jury returns a verdict and it has the approval of the trial judge, the
same must be affirmed on appeal if there is any evidence to support it as the jurors are
the sole and exclusive judges of the weight and credit given the evidence. . . . The
appellate court must construe the evidence with every inference and presumption in
favor of upholding the verdict, and after judgment, the evidence must be construed
2 It appears that, through no fault of W&C, the stimulus funds were exhausted before the City submitted its application.
5 to uphold the verdict even where the evidence is in conflict. As long as there is some
evidence to support the verdict, the denial of defendant’s motions for new trial and
[j.n.o.v.] will not be disturbed.” Lofty v. Fuller, 223 Ga. App. 95, 97 (477 SE2d 30)
(1996).
1. The City contends that the trial court erred in allowing the claim for quantum
meruit to go to the jury. First, we note that the verdict form does not show whether
the award was made on the breach of contract claim or whether it was made on the
basis of the quantum meruit claim. The City did not request special findings and did
not object to the verdict form. This Court will not speculate as to the findings of fact
supporting the verdict. All Risk Ins. Agency v. Southern Bell Tel. &c. Co., 182 Ga.
App. 190, 192 (355 SE2d 465) (1987).
Further, we reject the City’s argument that H. G. Brown Family, L.P. v. City of
Villa Rica, 278 Ga.
Free access — add to your briefcase to read the full text and ask questions with AI
FOURTH DIVISION DOYLE, P. J., ANDREWS and BOGGS, JJ.
NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. (Court of Appeals Rule 4 (b) and Rule 37 (b), February 21, 2008) http://www.gaappeals.us/rules/
July 11, 2012
In the Court of Appeals of Georgia A12A0620. CITY OF BALDWIN v. WOODARD & CURRAN, INC.
ANDREWS, Judge.
The City of Baldwin, Georgia (City) appeals after a jury awarded Woodard &
Curran, Inc. (W&C) $203,000 on its claim for money owed under a contract to
provide services for the City’s wastewater treatment plant. Because there was
sufficient evidence to support the award, we affirm.
The record shows that W&C sued for breach of a contract under which it was
to be paid for engineering and design services for the City’s water system (May
contract). W&C claimed that it provided supporting engineering documents for the
City’s application for government stimulus funds to improve the City’s wastewater
treatment plant under the May contract and also under a proposal submitted on June 15, 2009 (June proposal). The June proposal was signed by the mayor under
“authorization to proceed,” and provided that W&C would be paid a sum “not to
exceed $210,000.00.” In the alternative, the complaint asked for damages of
$203,870.44 as the value of the services provided to the City.
The City’s position was that it paid the $5,000 owed under the May contract
and that was the total amount due. The City stated in its Answer that the mayor’s
signing of the June proposal was an ultra vires act and was not binding on the City
because it was not approved by a quorum of the city council. The City also stated that
the June 2009 proposal was to secure funding and C&W failed to secure the funding;
therefore, the City was unable to proceed with the project.
The case went to trial and the evidence at trial, viewed in the light most
favorable to the jury’s verdict,1 was that W&C began operating the City’s wastewater
treatment plant in January 2008. In conjunction with an application for funding to
help improve the plant, W&C agreed to “provide the supporting engineering
documents . . . in order to convert this project from ‘fundable’ to ‘funded’ for a Lump
Sum fee of $5,000. . . . Under separate covers we will be preparing a scope, budget
and schedule for the actual design work for the Headwords (sic) and associated
1 Ferman v. Bailey, 292 Ga. App. 288, 289 (664 SE2d 285) (2008).
2 improvements (including the Design Development Report for the overall plant) and
also will submit a grant application to Rural Development to fund the development
of a capital master plan for the water and wastewater systems. Additional engineering
fees will only be contracted once funding has been committed.”
Brent Bridges, a senior vice-president with W&C testified that the $5,000, as
stated in the proposal, was to be paid for the documents to support the funding
application for stimulus money. The second part of the proposal agreed to in the May
2009 contract, was not covered by the $5,000 and involved supplying the design
engineering necessary to apply for funding.
The senior project manager at W&C testified that pursuant to the second part
of the May contract, there was a meeting with the Mayor and two city council
members and they authorized the second project of the May contract and authorized
payment of $210,000 for that work.
At this meeting with the mayor and council members, W&C was told to
proceed with the work necessary to continue the application process. This work
included hiring surveyors, hiring geo-technical core drillers, getting bids for the work,
and completing the design plans.
3 After the mayor signed the authorization to proceed, and as the work
progressed, the project engineer was asked to attend a city council meeting and
update the mayor and city council on the work that W&C was doing. The engineer
stated that he attended the meeting and described the work that was being done and
the status of the permits, applications, designs, specifications and reports. He testified
that the City owed W&C approximately $203,000 for this work.
The mayor who signed the June proposal testified that it was his understanding
that the full amount contracted for was the $5,000 and any additional engineering fees
would be contracted for once the funding was committed. The mayor said that he
signed the proposal for the additional work but did not date it because he could not
obligate the City by himself and it would have to be voted on by the council and
reviewed by the city attorney.
The mayor testified as to the benefit to the City if improvements were made to
the wastewater treatment plant, stating that improvements to the headworks would
have averted the possibility of substantial fines from the EPD. The mayor
acknowledged that he knew W&C was doing engineering work for the City in order
to obtain the stimulus money, and agreed that there was no question that W&C was
going to continue doing work for the City towards applying for the stimulus money.
4 The mayor said that he knew that deadlines existed and knew that the project must be
“shovel-ready by November 1[, 2009].”2
The mayor acknowledged that there was a council meeting attended by W&C
representatives in September at which the mayor and council were told that W&C was
going to have to do “engineering” for the project. The mayor said that he knew at that
time that “there was a good deal more to be done.” In addition, a tape was played for
the jury of this September meeting of the city council at which W&C told the council
about the work that had been completed and the work that still needed to be done in
order to file the application for funds.
The jury returned a verdict in favor of W&C in the amount of $203,000. The
City now appeals.
“Where a jury returns a verdict and it has the approval of the trial judge, the
same must be affirmed on appeal if there is any evidence to support it as the jurors are
the sole and exclusive judges of the weight and credit given the evidence. . . . The
appellate court must construe the evidence with every inference and presumption in
favor of upholding the verdict, and after judgment, the evidence must be construed
2 It appears that, through no fault of W&C, the stimulus funds were exhausted before the City submitted its application.
5 to uphold the verdict even where the evidence is in conflict. As long as there is some
evidence to support the verdict, the denial of defendant’s motions for new trial and
[j.n.o.v.] will not be disturbed.” Lofty v. Fuller, 223 Ga. App. 95, 97 (477 SE2d 30)
(1996).
1. The City contends that the trial court erred in allowing the claim for quantum
meruit to go to the jury. First, we note that the verdict form does not show whether
the award was made on the breach of contract claim or whether it was made on the
basis of the quantum meruit claim. The City did not request special findings and did
not object to the verdict form. This Court will not speculate as to the findings of fact
supporting the verdict. All Risk Ins. Agency v. Southern Bell Tel. &c. Co., 182 Ga.
App. 190, 192 (355 SE2d 465) (1987).
Further, we reject the City’s argument that H. G. Brown Family, L.P. v. City of
Villa Rica, 278 Ga. 819 (607 SE2d 883) (2005), precludes claims of quantum meruit
and unjust enrichment where an alleged contract between the municipality and a
contractor is ultra vires and void. Although the trial court held that the June proposal
was not a valid contract because it was not approved by a quorum of the city council,
the City overlooks the fact that there was evidence submitted to the jury that the work
was done in accordance with the May contract, which was a valid contract.
6 Further, it is well-settled law that “[w]here, as here, an ‘agreement’ exists to
perform lawful services for a municipality but it is not otherwise enforceable as a
valid express contract, a recovery in quantum meruit is authorized to the extent of the
value of the benefit that the municipality receives.” Walston & Assoc. v. City of
Atlanta, 224 Ga. App. 482, 483 (480 SE2d 917) (1997); City of St. Marys v. Stottler
Stagg & Assoc., 163 Ga. App. 45, 46 (292 SE2d 868) (1982); City of Dallas v. White,
182 Ga. App. 782, 783 (357 SE2d 125) (1987).
The City argues that it can no longer be held liable under the quasi-contractual
theory of quantum meruit because the Supreme Court’s holding in H. G. Brown,
impliedly overruled the above cases. In H. G. Brown, the Court held that because the
contract was not approved by a quorum of the city council before being signed by the
mayor, “the City acted with a total absence of power and in direct contradiction to the
strictures of its charter. Where, as here, a municipality contracts with a total absence
of power, it is not estopped from denying the resulting agreement’s validity.” Id. at
821.3 The City argues that in light of H. G. Brown, the reasoning in City of St. Marys
v. Stottler, supra, no longer applies. In Stottler, this Court held:
3 H. G. Brown did not involve a claim of quantum meruit; the City made all payments due under the contract. Rather, H. G. Brown filed a petition for mandamus to compel the City to validate the contract. Id. at 819.
7 Quantum meruit is not available when a county is the defendant. This result is dictated by the statutory requirements for establishing a contract with a county. See Code Ann. § 23-1701 [now OCGA § 36-10- 1] and Division 1. (Emphasis supplied.) PMS Const. Co., 243 Ga. at 872 [257 SE2d 285], supra. We know of no “statutory requirements” for establishing a contract with a municipality which are comparable to those cited in PMS Const. Co. as precluding a quantum meruit recovery against a county. Indeed it appears to have long been the law that, under certain circumstances, quantum meruit is an available remedy against a municipality. Since the city could have legally contracted for the service it received, it would seem that an implied contract would arise to pay a reasonable value for such beneficial service. We find no decision in Georgia to prohibit it; and the many cases hereinabove cited and others, under the ‘common-honesty rule,’ intimate the liability of the city.
Id. at 47. (citations and punctuation omitted).
Contrary to the City’s argument, there are still no statutory requirements for
establishing a contract with a city. There is therefore, no reason to conclude that
Stottler has been impliedly overruled.
2. The City also argues that the trial court erred in denying its motion for
directed verdict on the claim for quantum meruit. “On appeal from the denial of a
motion for a directed verdict or for j.n.o.v., we construe the evidence in the light most
favorable to the party opposing the motion, and the standard of review is whether
8 there is any evidence to support the jury’s verdict.” Terrell v. Pippart, 314 Ga. App.
483, n. 1 (724 SE2d 802) (2012).
The essential elements of a claim for quantum meruit are: (1) the performance
of valuable services; (2) accepted by the recipient or at his request; (3) the failure to
compensate the provider would be unjust; and (4) the provider expected
compensation at the time services were rendered. Parris Props. v. Nichols, 305 Ga.
App. 734, 735 (700 SE2d 848) (2010). The evidence, as outlined above was sufficient
to allow this claim to go to the jury.
Nevertheless, the City argues that the trial court erred in admitting evidence of
the plaintiff’s labor costs because this was not evidence of the value of the work to
the City. The award in a quantum meruit claim is based on the “reasonable value” of
the work. Zampatti v. Tradebank Intl. &c. Corp., 235 Ga. App. 333, 340 (508 SE2d
750) (1998). “The finder of fact must determine in what amount the party receiving
was benefitted or enriched by the materials and services.” Langford v. Robinson, 272
Ga. App. 376, 380 (612 SE2d 552) (2005). In other words, for a plaintiff to recover
on a claim for quantum meruit, the jury must find that the plaintiff performed services
valuable to the defendant and that the defendant accepted those services. When that
is shown, a promise is implied to pay the reasonable value of the services. OCGA §
9 9-2-7; Nelson & Hill, P.A. v. Wood, 245 Ga. App. 60, 62 (537 SE2d 670) (2000). “A
party cannot receive and retain the benefit of another’s labor without the duty to pay
for the reasonable value of the work.” Langford, supra at 380.
In this case, the value of the work was the City’s opportunity to apply for
stimulus grant money. It is true that “the reasonable value which the provider is
entitled to recover in quantum meruit is not the value of the labor but the value of the
benefit resulting from such labor to the recipient.” Hollifield v. Monte Vista Biblical
Gardens, 251 Ga. App. 124, 130 (553 SE2d 662) (2001). Here, the mayor responded
“Yes” when asked: “[Y]ou were satisfied then and you’re satisfied now that the City
of Baldwin would benefit greatly from the improvements to this wastewater treatment
plant?” Further, “Because it would have taken a big risk off the table. Is that correct?”
Answer: “That is correct.” Question: “And millions of dollars, I believe you told me?”
Answer: “It had potential, depending on what the fines were from EPD.”
Thus, in reaching its determination, the jury could find that the benefit
conferred was the result of W&C’s labor in putting together the application. There
was therefore, some evidence that the value to the City was the opportunity to secure
funds for renovation of the wastewater treatment plant.
10 This situation is similar to instances where an attorney is discharged prior to
earning a contingency fee and this Court has held that the attorney is entitled to
recover fees from the client based on quantum meruit. See, e.g., Amstead v.
McFarland, 287 Ga. App. 135, 137 (650 SE2d 737) (2007). In those cases, the
measure of damages is reasonable attorney fees. See Greer, Klosik & Daugherty v.
Yetman, 269 Ga. 271, 274 (496 SE2d 693) (1998). Likewise, the fees charged for the
time and effort expended by W&C were relevant to the value of the services rendered
and the trial court did not err in admitting this evidence.
3. Next, the City argues that the trial court erred in allowing into evidence the
June proposal. We disagree. The June proposal was relevant to W&C’s claim for
quantum meruit in that it detailed the scope of work to be carried out and it formed
the basis for the updates given by W&C to the city council on the work being done.
“Where the contract could have been, but was not, properly authorized, but the
representative officials in whom the right to so contract is vested have knowledge of
work which is being done on the authorization of one of themselves, allow it to
continue, and thereafter accept the benefits thereof on behalf of the city, an implied
ratification results which will render the governmental unit liable for the reasonable
value of the goods or services so received and used by it.” City of Gainesville v.
11 Edwards, 112 Ga. App. 672, 674 (145 SE2d 715) (1965). Accordingly, the June
proposal was admissible and the trial court did not abuse its discretion in admitting
it.
Further, the trial court gave a limiting instruction informing the jury that the
June proposal was “not enforceable as a contract, and you should not consider it as
such.” The court stated “[t]hat document is admitted for the limited purposes of
showing that certain officials of the City knew that the plaintiff was performing work
on behalf of the City, what work was being done . . ., and that the plaintiff expected
to be paid or compensated for that work.” There was no error.
4. Next the City claims the trial court erred in allowing the jury to consider a
breach of contract theory with regard to the second portion of the May contract which
stated that additional services would be provided “[u]nder separate covers.” “The test
of an enforceable contract is whether it is expressed in language sufficiently plain and
explicit to convey what the parties agreed upon.” Advance Security v. Superior
Surgical Mfg. Co., 197 Ga. App. 769, 771 (399 SE2d 488) (1990); Touche Ross &
Co. v. DASD Corp., 162 Ga. App. 438 (292 SE2d 84) (1982). Moreover, “[i]t is well-
settled that the policy of the law is against the destruction of contracts on the ground
of uncertainty if it is possible in the light of the circumstances under which the
12 contract was made to determine the reasonable intention of the parties.” Touche Ross,
supra at 439-440. “A contract will not be held unenforceable for indefiniteness
because its performance is, as to particular details, left open to subsequent agreement
of the parties. This is especially true where the contract provides the guidelines for
the subsequent agreement.” Knoxville Med. Investors v. Nat. Healthcorp, 192 Ga.
App. 460, 462-463 (385 SE2d 110) (1989).
Because this is an appeal from the denial of a directed verdict, we review this
under the “any evidence” standard. See Cole v. Webb, 267 Ga. App. 174, 176 (598
SE2d 886) (2004). In this case, there was sufficient evidence to allow this issue to go
to the jury. Although the contract did not specify the amount to be paid W&C for
additional work because the work was ongoing, there is nothing to show that the
parties, based upon their past dealings, would not have been able to agree upon the
fair price for W&C’s services. See McLean v. Continental Wingate Co., 212 Ga. App.
356, 359 (442 SE2d 276) (1994) (not unenforceable merely because the agreement
did not contain a formula for the calculation of the profits to which McLean was
entitled under its terms). “[I]t is only when the indefiniteness of the subject matter is
so extreme as not to present anything upon which the contract may operate in a
definite manner that the contract is rendered void.” Waugh v. Waugh, 265 Ga. App.
13 799, 801 (595 SE2d 647) (2004). See Quadron Software Intl. Corp. v. Plotseneder,
256 Ga. App. 284, 289 (568 SE2d 178) (2002) (although parties left certain terms to
be negotiated in the future, there was sufficient evidence from which the jury could
find there was an enforceable contract); Touche Ross, supra at 440 (provision that
“[d]etailed tasks will be mutually agreed [upon] . . . as the work progresses” does not
destroy the requisite certainty for a valid agreement).
5. Next, the City claims that the trial court erred in charging the jury that a city
may be held liable for value of the benefit received and also erred in failing to charge
the jury that a city can only contract in the method prescribed in its charter. In light
of our holdings above, we need not address this enumeration.
6. In its last enumeration, the City contends that the trial court erred in charging
the jury on implied ratification and in failing to charge the jury that a party cannot
accept services of which it is not aware, and the knowledge of an individual with no
power to bind the city cannot be imputed to the City.
There was no error in the jury charge on implied ratification because it was a
correct statement of the law and also was adjusted to the evidence at trial. See, e.g.,
Thompson v. Princell, 304 Ga. App. 256, 262 (696 SE2d 91) (2010).
14 The record shows that the City requested the following charge: “I charge you
that a party may not accept services of which it was totally unaware. When an
individual who had no authority to obligate the defendant on any contract with the
plaintiff such that his dealings with the plaintiff were beyond the scope of his
authority, the individual’s knowledge of plaintiff’s services cannot be imputed to the
defendant as a matter of law.”
“As we have held, if any portion of a requested charge is inapt, incorrect,
misleading, confusing, argumentative, not precisely adjusted or tailored, or not
reasonably raised or authorized by the evidence, denial of the charge request is
proper.” Dept. of Transp. v. Patten Seed Co., 290 Ga. App. 532, 535-536 (660 SE2d
30) (2008). Here, the requested charge was argumentative and not adjusted to the
evidence as set out above. There was no error.
Judgment affirmed. Doyle, P. J., and Boggs, J., concur.