City of Allentown v. Ott

85 Pa. Super. 210, 1925 Pa. Super. LEXIS 242
Superior Court of Pennsylvania·Decided December 2, 1924·No. Appeal, 51·Published·Cited by 5 cases

Opinion

Opinion by

Linn, J.,

This appeal involves the validity of a municipal claim filed by the City of Allentown to the use of a contractor for paving and curbing part of 19th Street along land of appellee, after a trial in which the learned court below denied recovery on two grounds: holding (1) that the claim was a second, and therefore unauthorized, assessment under the ordinance providing for the improvement; and, (2) that the amount claimed was not calculated on the foot-front basis as required by the ordinance, but was obtained by multiplying the paved area in front of the abutting property (to the centre-line of the street) by the contract price per square yard.

Allentown is a city of the third class. In 1916 the city council passed an ordinance providing for the paving, and setting of curbs, on a number of designated streets, one of them, 19th Street from Liberty Street to Roth Avenue. The appellee, with Other abutting owners, had signed and filed the required petition for the improvement. The ordinance provided for obtaining proposals to do the work; for paying for it by assessments on abutting property; for assignment by the city to the contractor of such assessments in full payment, with authority, in the name of the city, to file liens therefor and to collect the cost. The ordinance also provided that upon approval of the work by designated city authorities, and after and in accordance with notice to the abutting owner, that the assessment should be made by the .city engineer by the foot-front method and by assigning to each lot the actual cost of the curbing in front thereof. The ordinance was followed by resolution of the city, council awarding the contract to improve all the streets designated in the ordinance, to, the Barber As *213 phalt Paving Company, the use-plaintiff, in accordance with its proposal; a .contract dated April 29, 1916, so providing was' executed and delivered. Various unit prices applicable in different contingencies, were specified in the contract, but the prices applicable on 19,th Street were $1.89 per square yard for paving and 50c per linear foot, for the curb. Work was begun. The area to be paved in 19th Street (about 5,185 linear feet) was 22,278 sq. yds. On November 7, 1917, after about 5,676 sq. yds. had been paved, (about 1,344 linear feet of street), and when the curb had been put in for the entire distance from Liberty Street to Eoth Avenue, the work was stopped. Two reasons were assigned by appellant for the cessation of work; as appellee concedes one of them, reference to that is sufficient; his brief states “the appellee admits that the paving was postponed by sewer construction on the part of thé city ,.....” The evidence justifies the conclusion that the city authorities thereupon treated what had been done up to that time as a completed improvement, for in January, 1918, the real estate abutting on the then paved portion was assessed and liened for the cost of the improvement in front thereof, pursuant to the contract; the filing of those liens was- an assertion by the city that the paving of the 1,344 feet of street was a completed improvement, and each claim filed, we assume, contained the statutory averment that the city engineer had certified to the completion of the improvement. Those liens are not before us, though there is evidence that they were filed. From the time when work was stopped until 1920, no paving was done on the remainder of the section covered by the ordinance, but it was not repealed; the ordinance remained in force.

On June 21,1919, a resolution was adopted, notifying the contractor to discontinue all work under the contract, and this was followed on May 24, 1920, by a resolution formally rescinding the contract. The rescission-was accepted by the contractor.

*214 Paving of the remainder of the nnpaved section of 19th Street was not resumed until August, 1920, when, pursuant to a resolution of July 26, 1920, the municipal officers were directed to advertise for bids to do it. By resolution, approved August 9, 1920, the contract was awarded to the same contractor, — the use-plaintiff— pursuant to a new bid received in response to advertisement, and a contract dated August 12, 1920, was executed and delivered. The price per square yard of paving was $4.46. These resolutions of the city council, each duly approved by the mayor and certified by the city clerk, were produced by the city clerk, who testified they were, or were taken from, the “official records” of the city; they had the legislative effect of ordinances duly passed, approved and recorded: Third Class City Act of June 27,1913, P. L. 568, art. VI, sec. 6, P. L. 592; Marshall v. Mayor, etc. of Allegheny, 59 Pa. 455, 462; Fuller v. Scranton, 18 W. N. C. 18; Wain v. Phila., 99 Pa. 330, 337; Roudebush v. Meadville, 241 Pa. 261, 263-4.

Free access — add to your briefcase to read the full text and ask questions with AI

City of Allentown v. Ott, 85 Pa. Super. 210, 1925 Pa. Super. LEXIS 242 (Pa. Ct. App. 1924).

85 Pa. Super. 210 (City of Allentown v. Ott) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Commonwealth v. Parker
644 A.2d 1245 (Superior Court of Pennsylvania, 1994)
Lawrence Park Township v. Nacera
6 Pa. D. & C.2d 666 (Erie County Court Common Pleas, 1955)
Spring Garden Township v. Logan
27 A.2d 419 (Superior Court of Pennsylvania, 1942)
Spramelli v. Boro. of Punxsutawney
157 A. 522 (Superior Court of Pennsylvania, 1931)
Allentown v. Heyman
136 A. 859 (Supreme Court of Pennsylvania, 1927)