City of Allentown v. Ott

85 Pa. Super. 210, 1925 Pa. Super. LEXIS 242
CourtSuperior Court of Pennsylvania
DecidedDecember 2, 1924
DocketAppeal, 51
StatusPublished
Cited by5 cases

This text of 85 Pa. Super. 210 (City of Allentown v. Ott) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Allentown v. Ott, 85 Pa. Super. 210, 1925 Pa. Super. LEXIS 242 (Pa. Ct. App. 1924).

Opinion

Opinion by

Linn, J.,

This appeal involves the validity of a municipal claim filed by the City of Allentown to the use of a contractor for paving and curbing part of 19th Street along land of appellee, after a trial in which the learned court below denied recovery on two grounds: holding (1) that the claim was a second, and therefore unauthorized, assessment under the ordinance providing for the improvement; and, (2) that the amount claimed was not calculated on the foot-front basis as required by the ordinance, but was obtained by multiplying the paved area in front of the abutting property (to the centre-line of the street) by the contract price per square yard.

Allentown is a city of the third class. In 1916 the city council passed an ordinance providing for the paving, and setting of curbs, on a number of designated streets, one of them, 19th Street from Liberty Street to Roth Avenue. The appellee, with Other abutting owners, had signed and filed the required petition for the improvement. The ordinance provided for obtaining proposals to do the work; for paying for it by assessments on abutting property; for assignment by the city to the contractor of such assessments in full payment, with authority, in the name of the city, to file liens therefor and to collect the cost. The ordinance also provided that upon approval of the work by designated city authorities, and after and in accordance with notice to the abutting owner, that the assessment should be made by the .city engineer by the foot-front method and by assigning to each lot the actual cost of the curbing in front thereof. The ordinance was followed by resolution of the city, council awarding the contract to improve all the streets designated in the ordinance, to, the Barber As *213 phalt Paving Company, the use-plaintiff, in accordance with its proposal; a .contract dated April 29, 1916, so providing was' executed and delivered. Various unit prices applicable in different contingencies, were specified in the contract, but the prices applicable on 19,th Street were $1.89 per square yard for paving and 50c per linear foot, for the curb. Work was begun. The area to be paved in 19th Street (about 5,185 linear feet) was 22,278 sq. yds. On November 7, 1917, after about 5,676 sq. yds. had been paved, (about 1,344 linear feet of street), and when the curb had been put in for the entire distance from Liberty Street to Eoth Avenue, the work was stopped. Two reasons were assigned by appellant for the cessation of work; as appellee concedes one of them, reference to that is sufficient; his brief states “the appellee admits that the paving was postponed by sewer construction on the part of thé city ,.....” The evidence justifies the conclusion that the city authorities thereupon treated what had been done up to that time as a completed improvement, for in January, 1918, the real estate abutting on the then paved portion was assessed and liened for the cost of the improvement in front thereof, pursuant to the contract; the filing of those liens was- an assertion by the city that the paving of the 1,344 feet of street was a completed improvement, and each claim filed, we assume, contained the statutory averment that the city engineer had certified to the completion of the improvement. Those liens are not before us, though there is evidence that they were filed. From the time when work was stopped until 1920, no paving was done on the remainder of the section covered by the ordinance, but it was not repealed; the ordinance remained in force.

On June 21,1919, a resolution was adopted, notifying the contractor to discontinue all work under the contract, and this was followed on May 24, 1920, by a resolution formally rescinding the contract. The rescission-was accepted by the contractor.

*214 Paving of the remainder of the nnpaved section of 19th Street was not resumed until August, 1920, when, pursuant to a resolution of July 26, 1920, the municipal officers were directed to advertise for bids to do it. By resolution, approved August 9, 1920, the contract was awarded to the same contractor, — the use-plaintiff— pursuant to a new bid received in response to advertisement, and a contract dated August 12, 1920, was executed and delivered. The price per square yard of paving was $4.46. These resolutions of the city council, each duly approved by the mayor and certified by the city clerk, were produced by the city clerk, who testified they were, or were taken from, the “official records” of the city; they had the legislative effect of ordinances duly passed, approved and recorded: Third Class City Act of June 27,1913, P. L. 568, art. VI, sec. 6, P. L. 592; Marshall v. Mayor, etc. of Allegheny, 59 Pa. 455, 462; Fuller v. Scranton, 18 W. N. C. 18; Wain v. Phila., 99 Pa. 330, 337; Roudebush v. Meadville, 241 Pa. 261, 263-4.

The paving under the contract of August, 1920, was completed on November 10,1920, and was approved and accepted. Thereupon, in compliance with the mandate of the ordinance for the collection of the cost by assessment on the foot-front basis, the city engineer and the proper authorities then assessed the cost of the paving under the contract of 1920 against the real estate on 19th Street abutting on the paving done under that contract. In doing so, however, appellee says (and the learned court below held) that they erroneously charged this abutting real estate with the cost per square yard of paving the area in front of the property (to the centre of the street), thereby charging a sum in excess of what would have been chargeable by dividing the cost of the paving done under the second contract on the foot-front basis. There is not sufficient evidence in the record to enable us to determine whether the amount charged is greater or not. After stating that the claim is filed for *215 paving the cartway of the street with asphalt, on the west side thereof, in front of the property of appellee, the claim as filed states: “The amount of assessment for which this claim is filed and the costs thereof, is as follows : To 212.63 sq. yds. of cartway paving with asphalt at $4.46 per sq. yd., $947.89; 240 sq. ft. gutter at 45c, $108; 152.13 linear feet curb at 50c, $76.06, [making a total of] $1,131.96.” But as Judge Porter said of an averment quite like that in a lien which came before this court in Phila. v. Ramsay, 72 Pa. Superior Ct. 185, at 190, “This is not an allegation that the number of square yards of paving mentioned was done directly in front of defendant’s property, it is simply an averment that the property of the defendant was liable to pay for that number of square yards of pavement at the price stated, the averment is not that the paving was assessed but that [the cost] was assessed against the property.” If the paved section of the street involved in the second contract was of uniform width, so that a rectangle was .paved, (street intersections being payable by the city) the foot|-front rule applied to the total cost will result in the same sum as the product of the area directly in front of the property multiplied by the price per square yard.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commonwealth v. Parker
644 A.2d 1245 (Superior Court of Pennsylvania, 1994)
Lawrence Park Township v. Nacera
6 Pa. D. & C.2d 666 (Erie County Court Common Pleas, 1955)
Spring Garden Township v. Logan
27 A.2d 419 (Superior Court of Pennsylvania, 1942)
Spramelli v. Boro. of Punxsutawney
157 A. 522 (Superior Court of Pennsylvania, 1931)
Allentown v. Heyman
136 A. 859 (Supreme Court of Pennsylvania, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
85 Pa. Super. 210, 1925 Pa. Super. LEXIS 242, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-allentown-v-ott-pasuperct-1924.