Supreme Court of Florida ____________
Nos. SC2022-1733, SC2022-1735, SC2022-1745, SC2022-1748, & SC2022-1777 ____________
CITIZENS OF THE STATE OF FLORIDA, etc., Appellant,
vs.
ANDREW GILES FAY, etc., et al., Appellees.
November 14, 2024
COURIEL, J.
We have for review final orders of the Public Service
Commission approving proposals from four electric utility
companies to improve the power grid’s ability to withstand extreme
weather. These initiatives are the first of their kind, submitted by
the utility companies pursuant to section 366.96, Florida Statutes,
which became law in 2019. 1 The Office of Public Counsel (OPC)
challenged the orders below and appeals the Commission’s approval
1. We have jurisdiction. See art. V, § 3(b)(2), Fla. Const.; § 366.10, Fla. Stat. (2021). of them here, arguing that the Commission erred in its
interpretation of the statute and impaired the fairness of the
proceedings below by granting the utilities’ motions to strike
portions of an expert’s testimony.
We decide that the Commission correctly reviewed and
approved the utilities’ proposals after concluding that they are in
the public interest. Also, the Commission did not abuse its
discretion in striking the expert testimony at issue.
I
Finding it in the state’s interest to strengthen electric utility
infrastructure to withstand extreme weather conditions, the
Legislature enacted—in section 366.96, Florida Statutes (the SPP
Statute)—a comprehensive program requiring public utilities to
make adequate preparations for storms, allowing the utilities to
recover some of the costs of those preparations from rate-paying
customers. See ch. 19-158, Laws of Fla. Each public utility
company must submit a Storm Protection Plan (SPP) “for the
overhead hardening and increased resilience of electric
transmission and distribution facilities, undergrounding of electric
distribution facilities, and vegetation management.” § 366.96(2)(b),
-2- Fla. Stat. (2021). These improvements—intended to increase the
resiliency of the electric grid, reduce outages, and improve their
response times during extreme weather—are collectively called
“storm hardening.” See generally § 366.96, Fla. Stat.
The SPP Statute requires each public utility to file an SPP with
the Commission, laying out its proposals in this regard for the next
decade. “Each plan must explain the systematic approach the
utility will follow to achieve the objectives of reducing restoration
costs and outage times associated with extreme weather events and
enhancing reliability.” § 366.96(3), Fla. Stat.
SPPs are subject to approval by the Public Service
Commission. The Commission reviews each SPP every three years
during the plan’s ten-year coverage period. At each three-year
mark, the Commission must determine if it is in the public interest
to approve the SPP measures proposed for the upcoming period.
See § 366.96(5)-(6), Fla. Stat. In its review of each SPP, the
Commission considers:
(a) The extent to which the plan is expected to reduce restoration costs and outage times associated with extreme weather events and enhance reliability, including whether the plan prioritizes areas of lower reliability performance.
-3- (b) The extent to which storm protection of transmission and distribution infrastructure is feasible, reasonable, or practical in certain areas of the utility’s service territory, including, but not limited to, flood zones and rural areas. (c) The estimated costs and benefits to the utility and its customers of making the improvements proposed in the plan. (d) The estimated annual rate impact resulting from implementation of the plan during the first 3 years addressed in the plan.
§ 366.96(4), Fla. Stat.
The Commission’s approval or denial of each SPP must occur
within 180 days of its submission. Once the Commission has
approved a plan, “proceeding with actions to implement the plan
shall not constitute or be evidence of imprudence” by the utility.
§ 366.96(7), Fla. Stat.
The SPP Statute does not define “prudence” or “imprudence.”
However, chapter 366 of our statutes—the one relating to public
utilities—refers to prudence or its cognates 24 times, often in
describing costs. See, e.g., § 366.95(1), Fla. Stat. (2021) (“The
commission shall issue a financing order authorizing the financing
of reasonable and prudent nuclear asset-recovery costs . . . .”);
§ 366.93(2), Fla. Stat. (2021) (“Such mechanisms must be designed
to promote utility investment in nuclear or integrated gasification
-4- combined cycle power plants and allow for the recovery in rates of
all prudently incurred costs . . . .”); § 366.91(3), Fla. Stat. (2021)
(“Prudent and reasonable costs associated with a renewable energy
contract shall be recovered from the ratepayers . . . .”).
The SPP Statute directs the Commission to adopt rules to
guide how it is administered. So in January 2020, the Commission
adopted Florida Administrative Code Rules 25-6.030, “Storm
Protection Plan” (the SPP Rule), and 25-6.031, “Storm Protection
Plan Cost Recovery Clause” (the SPPCRC Rule). The SPP Rule
explains what an SPP must contain. The SPPCRC Rule sets out the
costs that utilities may recover from customers and describes the
procedures for recovery.
Following the requirements of the SPP Statute, the SPP Rule,
and the SPPCRC Rule, Florida investor-owned utilities filed their
first SPP proposals in April 2020. The OPC intervened on behalf of
Florida consumers in the administrative proceedings regarding
these proposals. The utilities, the OPC, and other intervenors
entered into settlements approving the plans. As part of that
process, the Commission heard oral argument from the parties in
support of each settlement agreement and considered evidence
-5- presented by the parties. Ultimately, the Commission approved the
settlements and determined that the utilities’ SPPs were in the
public interest, pending review and approval in 2022. The 2020
settlements preserved the parties’ rights to challenge the prudence
of any projects in subsequent SPPCRC Rule proceedings.
The proceedings before us now started when, in 2022, the
utilities timely submitted renewed proposals for the 2023-2032
period. The four utilities that filed were Florida Power & Light
Company (FPL), Duke Energy Florida, LLC (DEF), Tampa Electric
Company (TECO), and Florida Public Utilities Company (FPUC).2
The OPC again intervened in each case.
The Commission ultimately issued final orders approving—to
varying extents3—each SPP Plan, and the associated SPPCRC Rule
docket. The OPC appeals the Commission’s five final orders to us.
2. FPUC filed its SPP in 2022 for the first time. It did not make an initial filing in 2020 due to delays caused by Hurricane Michael.
3. Where it determined that a utility’s plan did not meet the public interest test, the Commission ordered modifications. For example, in FPUC’s final order, the Commission determined:
FPUC’s SPP, with the following modifications, is in the public interest and is approved: (1) removal of the
-6- II
The OPC argues that the Commission erroneously interpreted
the SPP Statute and SPP Rule; it should have considered what the
statute calls the “prudence” of the SPPs, in addition to whether
those plans were in the public interest. What’s missing, the OPC
says, is a quantitative, dollar-to-dollar assessment of the estimated
costs and benefits of the proposed SPP programs and projects. For
example, the OPC argues that the Commission erred by not
requiring FPL and FPUC to “provide the estimated reduction in
outage times and restoration costs or a meaningful comparison of
the estimated costs to those benefits.”
Not so, respond the utilities: the SPP Statute establishes two
distinct proceedings, one for plan review and another for cost
recovery. While the SPP Statute requires the Commission to
consider “the estimated costs and benefits to the utility and its
customers of making the improvements proposed in the plan,” that
Future T&D Enhancement Program, and (2) removal of the Transmission & Substation Resiliency Program. FPUC shall file an amended SPP within 30 days of the issuance of the final order for administrative approval by Commission staff.
-7- does not mean what the OPC thinks it does: it is not a command to
perform a “prudence review” of the SPPs when determining if they
are in the public interest, but rather, to review the prudence of the
costs undertaken in the separate cost recovery proceeding
envisioned by the SPP Statute.
This case, then, requires us to decide if the Commission acted
lawfully in approving the SPPs—that is, whether it correctly
interpreted the SPP Statute and acted within its legal authority
when it approved the plans. “Whether the [Commission] has the
authority to act is a question of law, which is subject to de novo
review.” Citizens of State v. Graham, 191 So. 3d 897, 900 (Fla.
2016). First, we analyze the SPP Statute and conclude from its
words and structure that the Commission’s interpretation of it is
correct; second, we explain why the Commission’s determination
did indeed adhere to what the statute requires.
A
The SPP Statute directs the Commission to “determine
whether it is in the public interest to approve, approve with
modification, or deny” the SPPs at issue. § 366.96(5), Fla. Stat. In
the relevant (but, as we shall see, not identical) context of rate
-8- making cases, we have said the public interest determination “is not
a pure finding of fact that we are able to review by searching for
competent, substantial evidence in the record. Instead, as
suggested by the qualitative words with which it is described, the
Commission’s decision . . . rests on both facts in the record and
policy judgments guided by its ‘specialized knowledge and expertise
in this area.’ ” Floridians Against Increased Rates, Inc. v. Clark
(FAIR), 371 So. 3d 905, 910 (Fla. 2023) (quoting Gulf Coast Elec.
Coop., Inc. v. Johnson, 727 So. 2d 259, 262 (Fla. 1999)). Once the
Commission has done that work, ours is to decide whether its
public interest determination “is within the range of discretion given
to the Commission by the Legislature.” Id. at 911 (citing
§ 120.68(7)(e)1., Fla. Stat. (2021)). And when they come to us, the
Commission’s decisions about what is in the public interest benefit
from “the presumption that they are reasonable and just.” Id.
(quoting W. Fla. Elec. Coop. Ass’n, Inc. v. Jacobs, 887 So. 2d 1200,
1204 (Fla. 2004)).
The Commission is correct that chapter 366 is about more
than rate making, for it says this Court will do more than review
rates set by the Commission. See § 366.10, Fla. Stat. (“[T]he
-9- Supreme Court shall review, upon petition, any action of the
commission relating to rates or service of utilities providing electric
or gas service.” (emphasis added)). What is more, from its
separation from sections 366.06 and 366.07, Florida Statutes
(2021), it is evident that the SPP Statute stands apart from the rate
making process, and in its unique language provides a separate
procedure for the Commission’s review of storm hardening
measures. See Conage v. United States, 346 So. 3d 594, 598 (Fla.
2022) (“[T]he plainness or ambiguity of statutory language is
determined by reference to the language itself, the specific context
in which that language is used, and the broader context of the
statute as a whole.” (quoting Robinson v. Shell Oil Co., 519 U.S. 337,
341 (1997))).
Sections 366.96(2) and (3) lay the groundwork for a process
specific to the storm hardening context—as distinguished from rate
making—by defining relevant terms and setting a timeline for the
SPP proceedings.
The statute continues with subsections (4)(a)-(d), which lay out
the required content of each plan. The statute directs the
Commission to consider each plan’s ability to “reduce restoration
- 10 - costs and outage times . . . and enhance reliability”; whether the
plan is “feasible, reasonable, or practical”; the “estimated costs and
benefits”; and the “estimated annual rate impact” of the SPP in the
first three years. § 366.96(4)(a)-(d), Fla. Stat. Here the Commission
is not directed to consider actual incurred costs. That comes later.
Instead, subsection (4) lists those factors that the Commission is to
consider “[i]n its review of each transmission and distribution storm
protection plan filed pursuant to this section.” Id.
Subsection (4) does not require the Commission to determine
that the benefits of the proposed plan outweigh its costs. Certainly
it lists what the Commission must consider about each plan. And
certainly those considerations include “[t]he extent to which the
plan is expected to reduce restoration costs and outage times,”
“estimated costs and benefits to the utility and its customers of
making the improvements proposed in the plan,” and any
“estimated annual rate impact resulting from implementation of the
plan.” § 366.96(4)(a), (c)-(d), Fla. Stat. (emphasis added). But the
statute expressly recognizes the tentativeness of these datapoints,
and thus the infeasibility of a definitive computation of net cost or
benefit at the plan approval phase.
- 11 - Subsection (5) provides the purpose of the Commission’s
review: to evaluate proposed SPPs in 180 days to “determine
whether it is in the public interest to approve, approve with
modification, or deny the plan.” We read the requirements of
subsection (4) in their physical and logical relationship to
subsection (5) and conclude that the former sets out the content of
the public interest determination required by the latter. See
Antonin Scalia & Bryan A. Garner, Reading Law: The Interpretation
of Legal Texts 167 (2012) (explaining that we must consider “the
physical and logical relation of [a text’s] many parts”); see also Lab’y
Corp. of Am. v. Davis, 339 So. 3d 318, 324 (Fla. 2022) (“Under the
whole-text canon, proper interpretation requires consideration of
‘the entire text, in view of its structure and of the physical and
logical relation of its many parts.’ ” (citing Scalia & Garner, supra,
at 167)); Allstate Ins. Co. v. Revival Chiropractic, LLC, 385 So. 3d
107, 113 (Fla. 2024) (“Provisions in the texts of statutes and
contracts cannot be viewed in isolation from the full textual context
of which they are a part.”).
From its language and location in the statute, we discern that
subsection (7) does something different. The most sensible reading
- 12 - of this provision—which says that proceeding with actions to
implement an approved plan will not later be deemed evidence of
imprudence for a utility’s cost recovery purposes—is that if, in fact,
any costs ultimately incurred exceed the relevant component of
forecasted benefit, that deficiency will not constitute evidence of
imprudence by the utility, as long as the plan has duly considered
the expected or estimated data, and the Commission has found the
plans made in light of that consideration to have been in the public
interest.
It helps to read subsection (7) in the context of the subsection
it follows:
(6) At least every 3 years after approval of a utility’s transmission and distribution storm protection plan, the utility must file for commission review an updated transmission and distribution storm protection plan that addresses each element specified by commission rule. The commission shall approve, modify, or deny each updated plan pursuant to the criteria used to review the initial plan. (7) After a utility’s transmission and distribution storm protection plan has been approved, proceeding with actions to implement the plan shall not constitute or be evidence of imprudence. The commission shall conduct an annual proceeding to determine the utility’s prudently incurred transmission and distribution storm protection plan costs and allow the utility to recover such costs through a charge separate and apart from its base rates, to be referred to as the storm protection plan cost
- 13 - recovery clause. If the commission determines that costs were prudently incurred, those costs will not be subject to disallowance or further prudence review except for fraud, perjury, or intentional withholding of key information by the public utility.
§ 366.96(6)-(7), Fla. Stat.
Subsection (6) separates the preceding public interest
determination process from a subsequent “cost recovery” process.
Helpfully, the first word of subsection (7) is “[a]fter”—here a
subordinating conjunction—and the clause it introduces tells us
that “proceeding with actions to implement the plan shall not
constitute or be evidence of imprudence.” It is only after the time
described in this clause that we come to the statute’s four
references to “prudence” and its cognates. They appear in the
context of the “annual review proceeding” the Commission must
undertake “to determine the utility’s prudently incurred
transmission and distribution storm protection plan costs” which
decide the utility’s right “to recover such costs through a charge
separate and apart from its base rates.” § 366.96(7), Fla. Stat.
As the Commission did, we read this text to identify a separate
phase of cost recovery proceedings, the purpose of which is to
determine the recoverability by the utilities of certain costs, and not
- 14 - whether an SPP is in the public interest. Actions taken to
implement an approved plan shall not be deemed evidence of
imprudence for subsection (7)—that is, cost recovery—purposes. It
is still the Commission’s duty at that point to determine which
costs were prudently incurred, for it is only “those costs [that] will
not be subject to disallowance or further prudence review except for
fraud, perjury, or intentional withholding of key information by the
public utility.” § 366.96(7) Fla. Stat.
The fact that rate payers will bear some SPP-related costs, as
set forth in the SPPCRC Rule, does not convert the statute to a rate
making proceeding. We see in the inclusion of the words “separate
and apart from its base rates” a legislative choice to demarcate the
lines between the SPPCRC Rule and rate making proceedings
described elsewhere in chapter 366. Id.; see Sierra Club v. Brown,
243 So. 3d 903, 908 (Fla. 2018) (expressly differentiating between
the Commission’s rate making proceedings where utilities “recover
costs for capital investments” and its general review of settlements
for the public interest).
To determine what is in the public interest, the Commission
starts with what the relevant statute commands: here, at section
- 15 - 366.96(1) and (4). See FAIR, 371 So. 3d at 912-13. Subsection (1)
says, among other things, “[i]t is in the state’s interest to strengthen
[Florida’s] electric utility infrastructure to withstand extreme
weather conditions,” to promote “overhead hardening” of electrical
facilities and the “undergrounding” of electrical distribution lines,
and to “mitigate restoration costs and outage times.” See
§ 366.96(1)(c)-(e), Fla. Stat. Subsection (4) gives specificity to the
factors the Commission must consider in deciding whether a
particular plan is in the public interest, as that interest is described
in subsection (1).
By contrast, when the Commission determines whether a
utility’s costs have been prudently incurred, it considers “what a
reasonable utility manager would have done, in light of the
conditions and circumstances that were known, or should [have]
been known, at the time the decision was made.” Duke Energy Fla.,
LLC v. Clark, 344 So. 3d 394, 395 (Fla. 2022) (alteration in original)
(quoting S. All. for Clean Energy v. Graham, 113 So. 3d 742, 750
(Fla. 2013)). Each utility bears the burden of proving that its
investment choices are prudent. See § 366.06(1), Fla. Stat.
(requiring that costs must be “prudently invested by the public
- 16 - utility company”). Instead of performing the analysis outlined
above, when it considers the prudence of costs undertaken by a
utility, the Commission “shall investigate and determine the actual
legitimate costs . . . actually used and useful in the public service.”
Id. In this retrospective evaluation, the Commission reviews
incurred costs to ensure investments are made “honestly” and
“prudently” and are “useful in serving the public.” Id. What is at
stake for the utility is whether it will be paid for something it
planned to do, and in fact did.
In summary, the Commission’s work when it decides what is
in the public interest is different from the work it does when it
decides whether a utility acted prudently. It makes those decisions
at different times, considering different statutorily described factors.
As a matter of colloquial speech, an imprudent investment or cost
may not be in the public interest. But while it speaks plainly, the
statute does not speak colloquially. The two determinations can be
distinguished. The Commission is correct that the SPP Statute
calls for a review of the utilities’ SPPs to determine if they are in the
public interest, and not whether the investments they propose are,
- 17 - in the sense in which the term has been used in this carefully
drafted statute, prudent.
B
The Commission correctly determined that the SPPs at issue
are in the public interest. That is because it did as the SPP Statute
required and considered the factors provided in section 366.96(4),
as further detailed in the SPP Rule. See Fla. Admin. Code R.
25-6.030. 4 Paragraph (3) of that rule requires that utilities’ SPPs
provide:5
(d) A description of each proposed storm protection program that includes: 1. A description of how each proposed storm protection program is designed to enhance the utility’s existing transmission and distribution facilities including an estimate of the resulting reduction in outage times and restoration costs due to extreme weather conditions; 2. If applicable, the actual or estimated start and completion dates of the program;
4. “Each utility as defined in Section 366.96(2)(a), F.S., must file a petition with the Commission for approval of a[n SPP] . . . .” Fla. Admin. Code R. 25-6.030(1). “For each Storm Protection Plan, the following information must be provided . . . .” Id. R. 25-6.030(3).
5. While there are other content requirements, the OPC mostly takes issue with FPL and FPUC’s fulfillment of subparagraph (3)(d)1.-4.
- 18 - 3. A cost estimate including capital and operating expenses; 4. A comparison of the costs identified in subparagraph (3)(d)3. and the benefits identified in subparagraph (3)(d)1.; and 5. A description of the criteria used to select and prioritize proposed storm protection programs.
Id. R. 25-6.030(3)(d)1.-5.
FPL met the criteria set by the SPP Rule. 6 FPL addressed each
section of its SPP to correlate with the criteria required by the SPP
Rule. Each section of the SPP provides a description of the storm
hardening program, explains potential benefits, and lists estimated
costs. See id. R. 25-6.030(3)(d)1.-3. For each proposed program in
the SPP, FPL provided “a cost estimate” and “a comparison of the
costs and benefits for each program.” Id. R. 25-6.030(3)(d)4.-5.
FPL provided charts with quantitative estimates for 2023-2025, and
for the 2023-2031 term. See id. R. 25-6.030(3)(d)3.
FPUC also fulfilled the criteria set by the SPP Rule. FPUC
detailed the estimated overall costs and provided express
“cost/benefit comparison” sections for each program throughout
6. We address only FPL’s and FPUC’s proposed SPPs because the OPC alleges that they are the two utilities that did not fulfill the requirements posed by the SPP Rule.
- 19 - the SPP. See id. R. 25-6.030(3)(d)4.-5. In each “cost/benefit
comparison” section, FPUC claims that the “[p]rojected benefits
associated with the [program] include a reduction in storm
restoration costs and increase in service reliability; associated with
a reduction in outage events during both extreme and non-extreme
weather conditions.” See id. R. 25-6.030(3)(d)1. FPUC uses
previous data from prior hurricanes to illustrate how estimated
outage times are significantly reduced through its storm hardening
programs. Id. Like FPL, FPUC provides a qualitative description
estimating reductions through its prior hurricane experience.
The Commission, on the basis of these presentations,
“explain[ed] why it reached its conclusions and how those
conclusions factored into its public interest determination.” FAIR,
371 So. 3d at 913. We have said that, in making a public interest
finding, the Commission should (1) consider all parties’ arguments,
(2) apply the public interest factors of the SPP Statute, and
(3) provide an explanation of how it reached its decision based on
the evidence. Id. at 912. Here, the Commission provided “reasoned
and articulated” final orders explaining why FPUC and FPL’s SPPs
were in the public interest. Id. at 911.
- 20 - The FPL final order, while it is no model of detailed reasoning,
adequately supports the Commission’s public interest
determination as required by section 366.96(4). In explaining how
FPL estimated its reduction in restoration costs and outage times, it
says:
Using the historical data analysis, the Utility estimated the reduction in outage times and restoration costs that would result from the implementation of its proposed SPP programs. The historical data demonstrates that FPL’s prior storm hardening projects reduced restoration costs and outage times associated with extreme weather events. Based on the historical data, FPL demonstrated that its SPP is expected to reduce restoration costs and outage times associated with extreme weather and enhance reliability.
This statement at least identifies as a basis for the Commission’s
approval FPL’s prior storm hardening projects and their positive
effect on restoration costs and outage times. 7 Additionally,
7. Nothing in the statute precludes the Commission from providing a more substantive account of how projects are in the public interest, including by discussing their expected or realized benefits to considerations of health, safety, and economic security, and by providing an account of how their costs or burdens fall on different customers. See Jodi L. Short, In Search of the Public Interest, 40 Yale J. on Regul. 759, 772-78, 824-25 (2023). In layman’s terms, the question to be answered is, “Are these projects worth it?” A spreadsheet netting out expenditures and savings may
- 21 - section V of the Commission’s final order addresses the “estimated
costs and benefits of FPL’s SPP.” See § 366.96(4)(c), Fla. Stat. It
identifies evidence that the Commission used to inform its decision.
Ultimately, the Commission gave the green light to eight previously
approved SPP programs, which had been submitted as part of FPL’s
prior SPP. The Commission rejected other proposed programs that
did not meet the definition of storm hardening and therefore would
not be in the public interest. See § 366.96(2)(b), Fla. Stat. (defining
acceptable SPPs as overhead hardening or undergrounding
initiatives).
The FPUC final order also passes muster. Following the same
format and methodology of FPL’s final order, the Commission
restated the parties’ arguments, analyzed how FPUC fulfills each
statutory requirement, and described how the evidence adduced by
FPUC supported the Commission’s public interest determination.
See FAIR, 371 So. 3d at 912. The Commission explained how FPUC
used its experience from Hurricane Michael to illustrate how its
be part of its answer, but nothing prevents the Commission from saying more.
- 22 - proposed SPP programs would harden its systems, and
consequently reduce restoration costs and outage times. See
§ 366.96(4)(a), Fla. Stat. The Commission also accepted FPUC’s
data representing the SPP programs’ estimated rate impact. See
§ 366.96(4)(d), Fla. Stat. The Commission rejected two proposed
programs, finding they did not qualify as storm protection activities
within the public interest.
The Commission’s final orders as to TECO and DEF also
provide adequate support for a public interest determination. The
orders are shorter in length but contain similar critical information:
restatement of the parties’ arguments, evidence and testimony of
key experts, and a conclusion that the proposed plans meet the
requirements of the SPP Statute. DEF’s SPP is estimated to reduce
restoration costs by approximately $50 million per year and reduce
customer interruption to around 400 million minutes on average
per year. See § 366.96(4)(a), Fla. Stat. And for each proposed
program, TECO provided an estimate of the decrease in restoration
costs and in the delay customers would experience before having
power restored. See id. In both final orders, the Commission
disapproves programs that it explains either lacked sufficient
- 23 - evidence to satisfy the public interest (“TECO did not provide
sufficient data supporting its position”) or were not programs in the
public interest as intended by the SPP Statute (DEF collaboration
with Walmart not in the public interest as it “does not meet the
definition as laid out in the statute”). See § 366.96(2)(b), Fla. Stat.
III
The Commission did not abuse its discretion or impair the
fairness of the proceedings by excluding expert witness Kollen’s
testimony. The Commission was within its authority to conclude
that Kollen’s testimony included improper legal opinion and was in
any event admitted into the SPPCRC Rule record, where its
relevance was not at issue.
Kollen’s testimony contained impermissible legal opinion in
that he contended that the SPP Statute and Rule incorporate a
prudence review—precisely the legal question at issue. Florida law
generally precludes expert testimony where it constitutes an
opinion on such a question of law. See § 90.702, Fla. Stat. (2021)
(permitting expert testimony in the form of an opinion if based on
facts or data and produced by reliable principles or methods, and
the principles are applied reliably to the facts); Town of Palm Beach
- 24 - v. Palm Beach Cnty., 460 So. 2d 879, 882 (Fla. 1984) (deciding that
expert testimony cannot opine on how a case should be
determined); see also T.J.R. Holding Co., Inc. v. Alachua Cnty., 617
So. 2d 798, 800 (Fla. 1st DCA 1993) (“[T]he interpretation of a
statute is a question of law to be determined solely by the court, not
by expert witnesses.”); Bunin v. Matrixx Initiatives, Inc., 197 So. 3d
1109, 1110 (Fla. 4th DCA 2016). That’s what this was. The OPC
admits Kollen’s complete “testimony contains a variety of [his]
expert interpretations of the requirements of the SPP Statute, and
the SPP and SPPCRC Rules.” Because an expert’s interpretation of
questions of law and legal statutes is impermissible, his testimony
was properly excluded.
Also, granting the motion to strike Kollen’s testimony did not
impair the fairness of the proceedings. Under section 120.68(7)(c),
Florida Statutes (2021), “[t]he fairness of the proceedings or the
correctness of the action” may be impaired by “a material error in
procedure or a failure to follow prescribed procedure.”
§ 120.68(7)(c), Fla. Stat.; see also Citizens of Fla. v. Mayo, 333 So.
2d 1, 8-9 (Fla. 1976) (remanding where inadequate Commission
findings caused a “material error in procedure” that “affected both
- 25 - the fairness and the correctness” of the proceedings). It was no
procedural error to exclude Kollen’s legal opinion testimony.
Indeed, where Kollen’s testimony did not constitute improper legal
opinion, or was relevant to his expertise as an economist, it was
admitted. The record contains Kollen’s testimony regarding the
SPPs’ effects on customer rates, their costs compared to the benefits
of certain programs, and his opinion on utilities’ decision criteria.
And in the SPPCRC Rule proceedings, where the parties agree that
a prudence review is appropriate, Kollen’s testimony was admitted.
The OPC was offered a fair and equal opportunity to present its
arguments despite the stricken testimony.
IV
We affirm the Commission’s final orders.
It is so ordered.
MUÑIZ, C.J., and CANADY, LABARGA, GROSSHANS, FRANCIS, and SASSO, JJ., concur.
NOT FINAL UNTIL TIME EXPIRES TO FILE REHEARING MOTION AND, IF FILED, DETERMINED.
An Appeal from the Florida Public Service Commission
Charles J. Rehwinkel, Deputy Public Counsel, Mary A. Wessling, Patricia A. Christensen, Danijela Janjic, and Octavio Simoes-Ponce,
- 26 - Associate Public Counsels, Office of Public Counsel on behalf of The Florida Legislature, Tallahassee, Florida,
for Appellant Citizens of the State of Florida
Keith C. Hetrick, General Counsel, Samantha M. Cibula, Attorney Supervisor, and Susan Sapoznikoff, Senior Attorney, Jonathan H. Rubottom, Senior Attorney, Florida Public Service Commission, Tallahassee, Florida,
for Appellee Florida Public Service Commission
Dianne M. Triplett and Matthew R. Bernier of Duke Energy Florida, LLC, Tallahassee, Florida; Michael P. Silver and Alyssa L. Cory of Shutts & Bowen LLP, Tampa, Florida, and Daniel E. Nordby of Shutts & Bowen LLP, Tallahassee, Florida,
for Appellee Duke Energy Florida
C. Alan Lawson, Paul C. Huck, Jr., Jason Gonzalez, and Amber Stoner Nunnally of Lawson Huck Gonzalez, PLLC, Tallahassee, Florida,
for Appellee Florida Power & Light Company
Lauren V. Purdy, Beth Keating, and Jounice L. Nealy Brown of Gunster, Yoakley & Stewart, P.A., Jacksonville, Florida,
for Appellee Florida Public Utilities Co.
J. Jeffry Wahlen, Malcolm N. Means, and Virginia Ponder of Ausley McMullen, Tallahassee, Florida,
for Appellee Tampa Electric Company
- 27 -