Citizens of the State of Florida, etc. v. Andrew Giles Fay, etc.

Supreme Court of Florida·Decided November 14, 2024·No. SC2022-1733, SC2022-1735, SC2022-1745, SC2022-1748 & SC2022-1777·Published

Opinion

Supreme Court of Florida

Nos. SC2022-1733, SC2022-1735, SC2022-1745, SC2022-1748, & SC2022-1777

CITIZENS OF THE STATE OF FLORIDA, etc., Appellant,

vs.

ANDREW GILES FAY, etc., et al., Appellees.

November 14, 2024

COURIEL, J.

We have for review final orders of the Public Service Commission approving proposals from four electric utility companies to improve the power grid’s ability to withstand extreme weather. These initiatives are the first of their kind, submitted by the utility companies pursuant to section 366.96, Florida Statutes, which became law in 2019. 1 The Office of Public Counsel (OPC) challenged the orders below and appeals the Commission’s approval

1. We have jurisdiction. See art. V, § 3(b)(2), Fla. Const.;

§ 366.10, Fla. Stat. (2021).

of them here, arguing that the Commission erred in its interpretation of the statute and impaired the fairness of the proceedings below by granting the utilities’ motions to strike portions of an expert’s testimony.

We decide that the Commission correctly reviewed and approved the utilities’ proposals after concluding that they are in the public interest. Also, the Commission did not abuse its discretion in striking the expert testimony at issue.

I

Finding it in the state’s interest to strengthen electric utility infrastructure to withstand extreme weather conditions, the Legislature enacted—in section 366.96, Florida Statutes (the SPP Statute)—a comprehensive program requiring public utilities to make adequate preparations for storms, allowing the utilities to recover some of the costs of those preparations from rate-paying customers. See ch. 19-158, Laws of Fla. Each public utility company must submit a Storm Protection Plan (SPP) “for the overhead hardening and increased resilience of electric transmission and distribution facilities, undergrounding of electric distribution facilities, and vegetation management.” § 366.96(2)(b),

Fla. Stat. (2021). These improvements—intended to increase the resiliency of the electric grid, reduce outages, and improve their response times during extreme weather—are collectively called “storm hardening.” See generally § 366.96, Fla. Stat.

The SPP Statute requires each public utility to file an SPP with the Commission, laying out its proposals in this regard for the next decade. “Each plan must explain the systematic approach the utility will follow to achieve the objectives of reducing restoration costs and outage times associated with extreme weather events and enhancing reliability.” § 366.96(3), Fla. Stat.

SPPs are subject to approval by the Public Service Commission. The Commission reviews each SPP every three years during the plan’s ten-year coverage period. At each three-year mark, the Commission must determine if it is in the public interest to approve the SPP measures proposed for the upcoming period. See § 366.96(5)-(6), Fla. Stat. In its review of each SPP, the Commission considers:

(a) The extent to which the plan is expected to reduce restoration costs and outage times associated with extreme weather events and enhance reliability, including whether the plan prioritizes areas of lower reliability performance.

(b) The extent to which storm protection of transmission and distribution infrastructure is feasible, reasonable, or practical in certain areas of the utility’s service territory, including, but not limited to, flood zones and rural areas.

(c) The estimated costs and benefits to the utility and its customers of making the improvements proposed in the plan.

(d) The estimated annual rate impact resulting from implementation of the plan during the first 3 years addressed in the plan.

§ 366.96(4), Fla. Stat.

The Commission’s approval or denial of each SPP must occur within 180 days of its submission. Once the Commission has approved a plan, “proceeding with actions to implement the plan shall not constitute or be evidence of imprudence” by the utility. § 366.96(7), Fla. Stat.

The SPP Statute does not define “prudence” or “imprudence.”

However, chapter 366 of our statutes—the one relating to public utilities—refers to prudence or its cognates 24 times, often in describing costs. See, e.g., § 366.95(1), Fla. Stat. (2021) (“The commission shall issue a financing order authorizing the financing of reasonable and prudent nuclear asset-recovery costs . . . .”); § 366.93(2), Fla. Stat. (2021) (“Such mechanisms must be designed to promote utility investment in nuclear or integrated gasification

combined cycle power plants and allow for the recovery in rates of all prudently incurred costs . . . .”); § 366.91(3), Fla. Stat. (2021) (“Prudent and reasonable costs associated with a renewable energy contract shall be recovered from the ratepayers . . . .”).

The SPP Statute directs the Commission to adopt rules to guide how it is administered. So in January 2020, the Commission adopted Florida Administrative Code Rules 25-6.030, “Storm Protection Plan” (the SPP Rule), and 25-6.031, “Storm Protection Plan Cost Recovery Clause” (the SPPCRC Rule). The SPP Rule explains what an SPP must contain. The SPPCRC Rule sets out the costs that utilities may recover from customers and describes the procedures for recovery.

Following the requirements of the SPP Statute, the SPP Rule, and the SPPCRC Rule, Florida investor-owned utilities filed their first SPP proposals in April 2020. The OPC intervened on behalf of Florida consumers in the administrative proceedings regarding these proposals. The utilities, the OPC, and other intervenors entered into settlements approving the plans. As part of that process, the Commission heard oral argument from the parties in support of each settlement agreement and considered evidence

presented by the parties. Ultimately, the Commission approved the settlements and determined that the utilities’ SPPs were in the public interest, pending review and approval in 2022. The 2020 settlements preserved the parties’ rights to challenge the prudence of any projects in subsequent SPPCRC Rule proceedings.

The proceedings before us now started when, in 2022, the utilities timely submitted renewed proposals for the 2023-2032 period. The four utilities that filed were Florida Power & Light Company (FPL), Duke Energy Florida, LLC (DEF), Tampa Electric Company (TECO), and Florida Public Utilities Company (FPUC).2 The OPC again intervened in each case.

The Commission ultimately issued final orders approving—to varying extents3—each SPP Plan, and the associated SPPCRC Rule docket. The OPC appeals the Commission’s five final orders to us.

2. FPUC filed its SPP in 2022 for the first time. It did not make an initial filing in 2020 due to delays caused by Hurricane Michael.

3. Where it determined that a utility’s plan did not meet the public interest test, the Commission ordered modifications. For example, in FPUC’s final order, the Commission determined:

FPUC’s SPP, with the following modifications, is in the public interest and is approved: (1) removal of the

II

The OPC argues that the Commission erroneously interpreted the SPP Statute and SPP Rule; it should have considered what the statute calls the “prudence” of the SPPs, in addition to whether those plans were in the public interest. What’s missing, the OPC says, is a quantitative, dollar-to-dollar assessment of the estimated costs and benefits of the proposed SPP programs and projects. For example, the OPC argues that the Commission erred by not requiring FPL and FPUC to “provide the estimated reduction in outage times and restoration costs or a meaningful comparison of the estimated costs to those benefits.”

Not so, respond the utilities: the SPP Statute establishes two distinct proceedings, one for plan review and another for cost recovery. While the SPP Statute requires the Commission to consider “the estimated costs and benefits to the utility and its customers of making the improvements proposed in the plan,” that

Future T&D Enhancement Program, and (2) removal of the Transmission & Substation Resiliency Program.

Free access — add to your briefcase to read the full text and ask questions with AI

Citizens of the State of Florida, etc. v. Andrew Giles Fay, etc., (Fla. 2024).

Citizens of the State of Florida, etc. v. Andrew Giles Fay, etc. (Citizens of the State of Florida, etc. v. Andrew Giles Fay, etc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Robinson v. Shell Oil Co.
519 U.S. 337 (Supreme Court, 1997)
TJR Holding Co. v. Alachua County
617 So. 2d 798 (District Court of Appeal of Florida, 1993)
WEST FLORIDA ELEC. CO-OPERATIVE ASSOCIATION v. Jacobs
887 So. 2d 1200 (Supreme Court of Florida, 2004)
Citizens of Florida v. Mayo
333 So. 2d 1 (Supreme Court of Florida, 1976)
GULF COAST ELEC. CO-OP., INC. v. Johnson
727 So. 2d 259 (Supreme Court of Florida, 1999)
Town of Palm Beach v. Palm Beach County
460 So. 2d 879 (Supreme Court of Florida, 1984)
Citizens of the State of Florida v. Art Graham, etc.
191 So. 3d 897 (Supreme Court of Florida, 2016)
Simona Bunin v. Matrixx Initiatives, Inc., etc.
197 So. 3d 1109 (District Court of Appeal of Florida, 2016)
Sierra Club v. Julie Imanuel Brown, etc.
243 So. 3d 903 (Supreme Court of Florida, 2018)
Southern Alliance for Clean Energy v. Graham
113 So. 3d 742 (Supreme Court of Florida, 2013)