Citizens for Preservation of Floyd County, Inc. v. Appalachian Power Co.

248 S.E.2d 797, 219 Va. 540, 1978 Va. LEXIS 211
CourtSupreme Court of Virginia
DecidedNovember 22, 1978
DocketRecord No. 780600
StatusPublished
Cited by1 cases

This text of 248 S.E.2d 797 (Citizens for Preservation of Floyd County, Inc. v. Appalachian Power Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Citizens for Preservation of Floyd County, Inc. v. Appalachian Power Co., 248 S.E.2d 797, 219 Va. 540, 1978 Va. LEXIS 211 (Va. 1978).

Opinion

CARRICO, J.,

delivered the opinion of the Court.

In Campbell County v. Appalachian Pow. Co., 216 Va. 93, 215 S.E.2d 918 (1975), we affirmed the State Corporation Commission’s approval of one segment of a proposed 765 kilovolt (kv) circuit, or “loop,” connecting the generating facilities of Appalachian Power Company with the population centers of western Virginia needing electrical power. The Campbell County case involved a segment of the “loop” running from Cloverdale, near Roanoke, to Joshua Falls, near Lynchburg. As a continuation of the same proceeding, the Commission in the present case considered Appalachian’s application for approval of a segment running from Jackson’s Ferry, near Wytheville, to Axton, in the Martinsville-Danville area.

The Commission reviewed Appalachian’s present application in two stages. First, on June 10,1974, the Commission held a hearing [543]*543on the need for the Jackson’s Ferry-Axton line; on July 5,1974, the Commission entered an order holding that the need for the line had been established. Then, commencing on September 23, 1974, the Commission held a series of hearings concerning the location of the line. On January 4,1978, it approved construction of the line within a corridor running, in part, through Floyd County. An intervenor, Citizens for the Preservation of Floyd County, Inc. (CPFC), is here on an appeal of right seeking reversal of the order approving construction of the line through Floyd County.

CPFC’s contentions on appeal are as follows:

1. Inadequate notice was given of the public hearing on the need for the line.
2. The Commission did not establish criteria for evaluating scenic and environmental assets or provide a rational framework for decision making.
3. The Commission failed to consider alternatives to several constraints imposed by Appalachian on the location of the line.
4. The Commission failed to investigate alternatives to use of a 765 kv line.
5. The Commission failed to require Appalachian to discharge its statutory duty of providing evidence that existing rights-of-way could not adequately serve the needs of the company.
6. The Commission failed to inquire into the harm the proposed line may cause to human, animal, and plant life and therefore did not fulfill its statutory duty to minimize adverse effects on the environment.
7. The Commission failed to receive and give consideration to information from state agencies concerned with the environment, as required by statute.

NOTICE

CPFC did not intervene in the proceedings below until after the Commission had entered its July 5,1974 order finding that the need for the proposed line had been established. CPFC says that it did not intervene earlier and did not participate in the need hearing because notice of the hearing was inadequate.

[544]*544In language prescribed by the Commission, Appalachian published in the Floyd Press, a weekly newspaper of general circulation in Floyd County, and served on the governmental authorities of Floyd County the notice set out in the margin.1

CPFC argues that the notice was “not adequate because it failed to inform the residents of Floyd County that [Appalachian’s] proposal called for location of the line through the County” and did not state that “the opportunity to contest the need for the line would be foreclosed by a failure to participate in the need hearing.”

[545]*545We disagree with CPFC. Code § 56-265.2,2 under which the need hearing was conducted, requires “due notice to interested parties” before the Commission may grant a certificate of public convenience and necessity authorizing construction of certain public utility facilities. In our opinion, this requirement is satisfied with respect to interested parties in a particular county when a notice is published in a newspaper having general circulation in the county and is served on the county’s officials, which notice states that a hearing is to be held on the need to construct a utility line between two identified points whose locations readily indicate that the line might traverse the county. We believe further that the notice employed in this case was sufficient to alert interested parties to the fact that their failure to participate in the hearing would foreclose the opportunity to contest the need for the line.

ENVIRONMENTAL CRITERIA

CPFC contends that, under Code § 56-46.1,3 the Commission, in evaluating proposed routes for a utility line, is required to determine that the route the line is to follow “will reasonably minimize adverse impact on the scenic and environmental assets of the area concerned.” Yet, CPFC asserts, the Commission has failed, by rule, prior decision, or action in the present case, to establish criteria for evaluating scenic and environmental assets [546]*546or to “provide a rational framework for decision-making.” This failure, CPFC asserts, resulted in confusion concerning the several routes proposed in the present case, with advocates of particular routes applying different and often conflicting criteria.

In the Campbell County case, we noted the duty imposed upon the Commission by Code § 56-46.1 to establish conditions to minimize the environmental impact of construction of utility lines. We noted further that the Commission had discharged this obligation by adopting guidelines promulgated by the Federal Power Commission. 216 Va. at 102, 215 S.E. 2d at 925.

These guidelines have as their purpose to provide the most acceptable answers from an environmental standpoint for the design and location of rights-of-way and transmission facilities. No claim is made in the present case that the guidelines are insufficient to serve their stated purpose. We reiterate, therefore, that the Commission has discharged the obligation imposed upon it by Code § 56-46.1. And, in the present case, while the witnesses for the opposing sides may have differed in their views with respect to the question of environmental impact, we cannot say that the Commission departed from the guidelines in approving the location of Appalachian’s proposed facility.

[547]*547 ALTERNATIVES TO CONSTRAINTS

CPFC contends that the Commission did not properly evaluate alternatives to several constraints imposed by Appalachian upon the location of the line and thus abdicated its responsibility to determine a route that would minimize adverse environmental impact.

A.

First, CPFC argues that the Commission sought no alternatives to the constraint imposed by Appalachian by its insistence that the line start at Jackson’s Ferry. The Commission, CPFC says, not only failed to require Appalachian to submit alternative starting points but also disregarded entirely an alternative route proposed by CPFC’s expert that would have commenced at Lynchburg and bypassed Floyd County.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

VA. ELEC. & POWER v. Citizens for Safe Power
284 S.E.2d 613 (Supreme Court of Virginia, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
248 S.E.2d 797, 219 Va. 540, 1978 Va. LEXIS 211, Counsel Stack Legal Research, https://law.counselstack.com/opinion/citizens-for-preservation-of-floyd-county-inc-v-appalachian-power-co-va-1978.