Citizens Alliance to Protect Our Wetlands v. Wynn

908 F. Supp. 825, 1995 U.S. Dist. LEXIS 19450, 1995 WL 758772
CourtDistrict Court, W.D. Washington
DecidedMay 11, 1995
DocketNo. C95-591Z
StatusPublished

This text of 908 F. Supp. 825 (Citizens Alliance to Protect Our Wetlands v. Wynn) is published on Counsel Stack Legal Research, covering District Court, W.D. Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Citizens Alliance to Protect Our Wetlands v. Wynn, 908 F. Supp. 825, 1995 U.S. Dist. LEXIS 19450, 1995 WL 758772 (W.D. Wash. 1995).

Opinion

ORDER

ZILLY, District Judge.

THIS MATTER comes before the Court on separate motions for a temporary restraining order, docket no. 2, and a preliminary injunction, docket no. 14, brought by Plaintiff Citizens Alliance to Protect Our Wetlands (CAPOW). CAPOW is a non-profit corporation representing property owners and residents within the Auburn area of King [828]*828County. CAPOW alleges that the Federal Defendants,1 in issuing a permit to Defendant Northwest Racing Associates (NRA) to fill 17.4 acres of wetlands in Auburn, violated both the Clean Water Act (CWA), 33 U.S.C. § 1344, and the National Environmental Policy Act (NEPA), 42 U.S.C. § 4332.

CAPOW filed its motion for a temporary restraining order (TRO) to halt the filling of the wetlands at issue on April 18, 1995. The parties agreed to postpone the Court’s consideration of the motion for a TRO until May 8, 1995, at which time the Court would hear oral argument on CAPOWs motions for a TRO and a preliminary injunction. The parties submitted a stipulation, and the Court signed the proposed order, allowing NRA to fill up to 2.5 additional acres of wetlands on or before May 8, 1995; prior to the stipulation, NRA had already filled 2.8 of the 17.4 acres permitted.

On May 8, 1995, the Court heard oral argument from the parties on the motions for a TRO and a preliminary injunction.2 Having considered the oral arguments of the parties, and having reviewed ¿11 papers filed in support of, and in opposition to, the motions for a TRO and a preliminary injunction, the Court hereby DENIES both motions.

Background

In December 1992, NRA applied to the Corps for a permit under § 404 of the Clean Water Act to fill 53 acres of wetlands to construct a thoroughbred horse racing facility on a 196-acre site in Auburn. In August 1993, NRA' submitted a revised permit application seeking to fill 17.1 acres of “palustrine emergent wetlands” and 0.3 acres of “scrub-shrub wetlands” for a sealed-down 165-acre project. AR 2423, 2500.

In December 1993, the Corps determined that an Environmental ■ Impact Statement (EIS) would be required. The Corps then proceeded to perform a “practicable alternatives” analysis, examining 16 possible sites, including Auburn and Lacey. NRA had originally stated as the project purpose: “to construct and operate a thoroughbred horse racing track in Auburn, Washington, to replace the former Longacres Park in Renton, Washington.” AR 2504. The Corps redefined the project purpose more broadly as follows:

To develop and operate an economically viable thoroughbred horse racing facility in western Washington to meet the long-term needs of Washington’s thoroughbred horse racing industry.

Id. In evaluating the alternatives, the Corps used seven criteria, one of which was whether

[t]he project can generate adequate handle to support the industry. This would require a mutuel handle of approximately $153 million per year or a $10 million purse.

AR 2505. The Corps calculated “mutuel handle” as including the amount wagered on-site at the proposed racetrack facility and the amount wagered at “satellite” facilities on races held at the proposed live racetrack. Final EIS (January 1995), Appendix B5 (Technical Evaluation of Alternative Sites) at 7 (docket no. 28). The potential “handle” is one indicator of whether the racing facility is economically viable. By tentative agreement of the Horseman’s Benevolent Protection Association, the “purse” (or the amount of money awarded to owners of winning horses) represents 6.5% of the mutuel handle. Final EIS, Appendix B5 at 7 (docket no. 28).

The Corps determined that none of the sites except the proposed Auburn site satisfied all seven criteria. In this suit, CAPOW [829]*829claims that the Lacey site constituted a “practicable alternative” having a “less adverse impact on the aquatic ecosystem” than the Auburn site. See 40 C.F.R. § 230.10(a). CAPOW charges the Corps with violating the Clean Water Act by issuing a permit to fill the wetlands at issue when a practicable alternative existed. The Corps concluded, however, using four different scenarios, that the Lacey site could not generate adequate handle.3 Thus, the Corps determined that Lacey was not a practicable alternative. In January 1995, the Corps published the Final EIS. NRA received a § 404 permit for the Auburn site on April 7, 1995. CAPOW filed this action on April 18, 1995.

Analysis

A. Standard for Preliminary Injunction,

To obtain a preliminary injunction, the moving party must show either “(1) a combination of probable success on the merits and the possibility of irreparable injury, or (2) that serious questions are raised and the balance of hardships tips sharply in its favor.” Big Country Foods, Inc. v. Board of Education, 868 F.2d 1085, 1088 (9th Cir.1989). Under this formula, the degree of irreparable injury required increases as the probability of success on the merits decreases. Id. The same standard applies to the issuance of a temporary restraining order. See Graham v. Teledyne-Continental Motors, Div. of Teledyne Indus., Inc., 805 F.2d 1386, 1388 (9th Cir.1986), cert. denied, 484 U.S. 815, 108 S.Ct. 67, 98 L.Ed.2d 31 (1987).

B. Success on the Merits/Serious Questions

1. The Clean Water Act4

The regulation at issue, 40 C.F.R. § 230.10, provides in part:

(a) Except as provided under section 404(b)(2), no discharge of dredged or fill material shall be permitted if there is a practicable alternative to the proposed discharge which would have less adverse impact on the aquatic ecosystem, so long as the alternative does not have other significant adverse environmental consequences.
(2) An alternative is practicable if it is available and capable of being done after taking into consideration cost, existing technology, and logistics in light of overall project purposes.
(3) Where the activity associated with a discharge which is proposed for a special aquatic site ... is not “water depen,dent”[], practicable alternatives that do not involve special aquatic sites are presumed to be available, unless clearly demonstrated otherwise.
(d) Except as provided under section 404(b)(2), no discharge of dredged or fill material shall be permitted unless appropriate and practicable steps have been taken which will minimize potential adverse impacts of the discharge on the aquatic ecosystem.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Louisiana Wildlife Federation, Inc. v. York
603 F. Supp. 518 (W.D. Louisiana, 1984)
Morgan v. Walter
728 F. Supp. 1483 (D. Idaho, 1989)
Friends of the Earth v. Hintz
800 F.2d 822 (Ninth Circuit, 1986)
Big Country Foods, Inc. v. Board of Education
868 F.2d 1085 (Ninth Circuit, 1989)
Buljubasic v. United States
484 U.S. 815 (Supreme Court, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
908 F. Supp. 825, 1995 U.S. Dist. LEXIS 19450, 1995 WL 758772, Counsel Stack Legal Research, https://law.counselstack.com/opinion/citizens-alliance-to-protect-our-wetlands-v-wynn-wawd-1995.