Cities Of Riverside And Colton, California v. Federal Energy Regulatory Commission

765 F.2d 1434, 1985 U.S. App. LEXIS 20805
CourtCourt of Appeals for the Ninth Circuit
DecidedJuly 18, 1985
Docket84-7184
StatusPublished
Cited by1 cases

This text of 765 F.2d 1434 (Cities Of Riverside And Colton, California v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cities Of Riverside And Colton, California v. Federal Energy Regulatory Commission, 765 F.2d 1434, 1985 U.S. App. LEXIS 20805 (9th Cir. 1985).

Opinion

765 F.2d 1434

CITIES OF RIVERSIDE AND COLTON, CALIFORNIA, Petitioners,
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent,
and
Cities of Vernon and Anaheim, and Southern California Edison
Company, Intervenors.

Nos. 84-7184, 84-7220 and 84-7576.

United States Court of Appeals,
Ninth Circuit.

Argued and Submitted May 10, 1985.
Decided July 18, 1985.

Duncan, Allen & Mitchell, Donald R. Allen, David P. Yaffe, Richard M. Gittleman, Washington, D.C., for Riverside and Colton, Cal.

Joseph S. Davis, William H. Satterfield, Gen. Counsel, Barbara J. Weller, Deputy Sol., Joel M. Cockrell, Washington, D.C., for F.E.R.C.

David B. Brearley, El Monte, Cal., Arnold Fieldman, Goldberg, Fieldman, & Letham, P.C., Washington, D.C., for intervenor City of Vernon.

Wallace L. Duncan, James D. Pembroke, John W. Griggs, Charles F. Holum, Duncan, Weinberg & Miller, P.C., Washington, D.C., for Anaheim, Cal.

Petition for Review of the Decision of the Federal Energy Regulatory Commission.

Before KENNEDY, HUG and FERGUSON, Circuit Judges.

HUG, Circuit Judge:

The cities of Riverside and Colton, California (the "Cities") appeal from a Federal Energy Regulatory Commission (the "Commission") order approving Southern California Edison Company's ("Edison") multi-class rate design.

The Cities, which are wholesale customers of Edison and intervenors in Edison's rate increase proceedings before the Commission, do not challenge the rate of return on common equity or the overall return on rate base approved by the Commission as a part of Edison's cost of providing service to its wholesale customers. Rather, the Cities argue that the multi-class rate design approved by the Commission is arbitrary and capricious because the Commission purportedly departed from previously established standards applied in determining whether a single-class rate design is appropriate and failed to explain adequately its rationale for approving a multi-class rate design. The Cities also contend that the Commission's order is not justified by substantial evidence. We affirm.

FACTS

On January 15, 1979, Edison filed with the Commission a proposed rate increase pursuant to Section 205 of the Federal Power Act, 16 U.S.C. Sec. 824d (1982) (the "Act"), seeking to increase the rates charged to nine of its wholesale customers. Under its proposed rate increase, Edison's wholesale customers were given the option of being served under Rate Schedule R ("Resale") or Rate Schedule TOU-R ("Time of Use-Resale").-- Customers would be automatically served under Rate Schedule R unless they elected to be served under Rate Schedule TOU-R. Rate Schedule R is based upon a customer's highest demand during the month, while Rate Schedule TOU-R is based upon a customer's highest demand during a specified "peak" period.1 The Cities, along with the cities of Anaheim, Banning, and Azusa, filed a joint protest and petition to intervene in Edison's rate case. Another wholesale customer, the city of Vernon, also intervened in protest to Edison's application.

On March 15, 1979, the Commission accepted Edison's rates for filing and suspended the proposed rate increase for five months pending an evidentiary hearing on the lawfulness of the proposed rates. Hearings on Edison's application were held between May 13 and November 6, 1980.

During the proceedings before the administrative law judge ("ALJ"), opposing positions on rate design were presented. The city of Vernon sought the creation of two separate wholesale classes based on load diversity, while the Cities argued that no such diversity existed and that Edison should design rates for only one class. In his November 6, 1981 Initial Decision, the ALJ adopted a rate design, which had not been urged by any party, and ordered Edison to design a Schedule TOU-R demand rate and a Schedule R demand rate for each individual customer; the customer would then select the rate that best suited its load characteristics.

On September 10, 1982, the Commission issued Opinion No. 145, reversing the ALJ's decision on rate design and adopted the rate design proposed by Edison. The Commission noted that there was no evidence in the record to support the ALJ's decision to establish a rate for each wholesale customer, and rejected Vernon's proposed design, finding it "interesting," but not "sufficiently fleshed out to merit its adoption." The Commission concluded as follows:

Any proposal that would establish more than one customer class should reflect the customer's relative status concerning diversity, the voltage level each customer is served under and the customer's load factors. These are factors we found important in El Paso Electric Co., supra, in adopting separate rate classes for wholesale customers.

We reverse the judge. In Opinion No. 62, supra, the Commission ordered Edison to use rates containing one customer class. No party proposing a change from a unitary customer class has provided us with a persuasive alternative. We adopt Edison's filed one-class rate design. Finally, we direct Edison to demonstrate in its compliance filing that its rate design produces the same approximate earned rate of return for each customer.

Opinion No. 145. 20 FERC p 61,301, 61,594 (CCH) (1982); (emphasis added).

Rehearing of Opinion No. 145 was sought by the Cities, Edison, and Vernon. The Commission denied rehearing, and attempted to clarify its holding regarding rate design.

Both Edison and Cities request that we clarify the Rate Design portion of our Opinion. Our holding on that issue was that we generally adopted the rate design proposed by Edison in its filing, including R and TOU-R rate schedules. As to the language requiring a compliance filing that produced the same approximate earned rate of return for each customer, our intention was that this statement was a general directive, not necessarily requiring any drastic changes in the filed rate design. However, if any specific problems arise concerning the rate design that is eventually filed, they will be addressed in the compliance process.

Opinion No. 145-A. 21 FERC p 61,211, 61,475 (CCH) (1982) (emphasis added).

On March 18, 1983, Edison submitted its compliance filing, which contained revised rates intended to comply with the Commission's directives contained in Opinion Nos. 145 and 145-A (the "First Compliance Filing"). Two alternatives were submitted: Alternative A placed all wholesale customers--Rate Schedule R customers--in a single wholesale class. Alternative B divided the wholesale customers into two groups--Rate Schedule R and Rate Schedule TOU-R customers. Although both Alternative A and Alternative B produced the overall test year rate of return of 10.09%, there were variations in the rates of return Edison would earn from individual customers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
765 F.2d 1434, 1985 U.S. App. LEXIS 20805, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cities-of-riverside-and-colton-california-v-federal-energy-regulatory-ca9-1985.