Cities of Allen v. Railroad Commission of Texas

309 S.W.3d 563, 2010 WL 392158
CourtCourt of Appeals of Texas
DecidedApril 13, 2010
Docket03-06-00691-CV
StatusPublished
Cited by18 cases

This text of 309 S.W.3d 563 (Cities of Allen v. Railroad Commission of Texas) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cities of Allen v. Railroad Commission of Texas, 309 S.W.3d 563, 2010 WL 392158 (Tex. Ct. App. 2010).

Opinion

OPINION

DIANE M. HENSON, Justice.

Fifty-one Texas cities 1 (collectively, “the Cities”) brought a declaratory-judgment action against the Railroad Commission (“the Commission”), challenging the validity of Commission Rule 7.7101. See 16 *566 Tex. Admin. Code § 7.7101 (2009) (Tex. R.R. Comm’n, Interim Rate Adjustments); see also Tex. Gov’t Code Ann. § 2001.038 (West 2008) (allowing parties to challenge validity of agency rule by declaratory-judgment action). CenterPoint Energy Resources Corporation (“CenterPoint”), Atmos Energy Corporation (“Atmos”), and Texas Gas Services Company (“Texas Gas”) intervened in support of the validity of the Commission’s rule. The trial court issued a final judgment denying the Cities’ request for declaratory relief, but issued findings of fact and conclusions of law stating that certain subsections of the Commission’s rule were void. We affirm the judgment of the trial court.

BACKGROUND

In 2008, the Texas Legislature amended the Gas Utility Regulatory Act, Tex. Util. Code Ann. §§ 101.001-105.051 (West 2007 & Supp.2009), to allow gas utilities an opportunity to recover a return on capital expenditures made during the interim period between rate cases filed pursuant to subchapter C of chapter 104 of the utilities code. See Act of May 16, 2003, 78th Leg., R.S., ch. 938, § 1, 2003 Tex. Gen. Laws 2801 (codified at Tex. Util.Code Ann. § 104.301); see also Tex. Util.Code Ann. §§ 104.101-.112 (West 2007) (setting forth procedures allowing regulated utilities to seek approval to change rates, referred to by parties as subchapter C rate cases). Under section 104.301, a gas utility may file a tariff or rate schedule providing for an interim rate adjustment with the applicable regulatory authority within two years of the utility’s last subchapter C rate case. See Tex. Util.Code Ann. § 104.301(a) (West 2007). 2 The parties refer to section 104.301 as the “GRIP statute,” with GRIP being an acronym for “Gas Reliability Infrastructure Program.” 3

The GRIP statute provides, in relevant part:

A gas utility that has filed a rate case under Subchapter C within the preceding two years may file with the regulatory authority a tariff or rate schedule that provides for an interim adjustment in the utility’s monthly customer charge or initial block rate to recover the cost of changes in the investment in service for gas utility services.

Id. This tariff or rate schedule must be filed at least 60 days before the proposed implementation date of the new rates. Id. During this 60-day period, the municipality may suspend implementation of the new rates for up to 45 days. Id. The amount of the interim rate adjustment allowed under the GRIP statute is based on values associated with the utility’s return on investment, depreciation expenses, ad valorem taxes, revenue-related taxes, and incremental federal income taxes. Id. § 104.301(d).

The GRIP statute indicates that the reasonableness and prudence of the investments in service recovered by an interim rate adjustment will be subject to review in the utility’s next subchapter C rate *567 ease. See id. § 104.301(a). Specifically, the statute provides that once a final order has been issued in a subchapter C rate case filed after the implementation of an interim rate adjustment, any change in investment that was included in the interim adjustment is “no longer subject to subsequent review for reasonableness or prudence.” Id. Importantly, the statute also provides that until the issuance of a final order in the utility’s next rate case, “all amounts collected under the tariff or rate schedule before the filing of the rate case are subject to refund.” Id. Any utility that implements an interim rate adjustment is required to file a subchapter C rate case no later than 180 days after the fifth anniversary of the date its interim rate became effective. Id. § 104.301(h). Alternatively, the regulatory authority itself may instigate a rate case at any time to review the reasonableness of the utility’s rates. Id. § 104.301(i); see also id. § 104.151 (West 2007).

In response to the GRIP statute, the Commission adopted Rule 7.7101, referred to by the parties as the “GRIP rule.” See 16 Tex. Admin. Code § 7.7101. The GRIP rule, which sets forth the substantive and procedural requirements for obtaining an interim rate adjustment, provides that the director of the Commission may reject any GRIP application that “does not substantially comply with the requirements of this section.” See id. § 7.7101(a). 4 The rule goes on to describe the required contents of a GRIP application, including an annual project report and an annual earnings monitoring report, and provides the methodology to be used in calculating the interim rate adjustment. Id. § 7.7101(c), (f). Consistent with the GRIP statute, the rule provides that during the utility’s next rate case, the factors used to calculate the interim rate adjustment “shall be fully subject to review for reasonableness and prudence,” id. § 7.7101(j), and until the rate case has been concluded, all amounts collected under the adjusted rate schedule are subject to refund. Id. § 7.7101(f).

The GRIP rule also describes the procedure for reviewing a utility’s GRIP filing, stating that the director of the Commission is required to ensure that such filings are reviewed for compliance with the GRIP statute and rule. Id. § 7.7101(g). Upon completion of the review, the director’s recommendation regarding approval or rejection of the filing is submitted to the Commission for decision. Id. The GRIP rule does not provide for an adjudicatory hearing before the Commission on contested matters related to the GRIP filing, nor does it specifically provide for any involvement from the municipality having jurisdiction over the utility’s rates.

After the GRIP statute and rule were adopted, certain utilities filed applications for interim rate adjustments with the Cities. The Cities denied the applications, and the utilities appealed to the Commission. The Cities then requested adjudicative hearings at the Commission on issues related to the applications, but the Commission refused, taking the position that the GRIP statute and rule did not provide for any such hearing. The Commission ultimately granted the utilities’ applications for interim rate adjustments.

The Cities filed a declaratory-judgment action, seeking a declaration that the GRIP rule is void to the extent it prohibits them from intervening and obtaining an evidentiary hearing on appeals to the Com

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New York Party Shuttle, LLC v. John Bilello
414 S.W.3d 206 (Court of Appeals of Texas, 2013)
Jeffrey C. Green v. State
Court of Appeals of Texas, 2012
Atmos Energy Corp. v. Cities of Allen
353 S.W.3d 156 (Texas Supreme Court, 2011)
Monroe v. Monroe
358 S.W.3d 711 (Court of Appeals of Texas, 2011)
Dalal Hibri Monroe v. David Allen Monroe
Court of Appeals of Texas, 2011
the Inland Sea, Inc. v. Christopher Castro
Court of Appeals of Texas, 2011

Cite This Page — Counsel Stack

Bluebook (online)
309 S.W.3d 563, 2010 WL 392158, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cities-of-allen-v-railroad-commission-of-texas-texapp-2010.