Cipriani Construction Corp. v. GRN Electric and Solar Inc.

CourtDistrict Court, N.D. New York
DecidedFebruary 20, 2024
Docket1:23-cv-00771
StatusUnknown

This text of Cipriani Construction Corp. v. GRN Electric and Solar Inc. (Cipriani Construction Corp. v. GRN Electric and Solar Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cipriani Construction Corp. v. GRN Electric and Solar Inc., (N.D.N.Y. 2024).

Opinion

UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF NEW YORK - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

CIPRIANI CONSTRUCTION CORP.,

Plaintiff,

-v- 1:23-CV-771

GRN ELECTRIC AND SOLAR INC., and KIRK FERRIER,

Defendants.

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

APPEARANCES: OF COUNSEL:

HODGSON RUSS LLP JAMES ZAWODZINSKI, JR., ESQ. Attorneys for Plaintiff RYAN K. CUMMINGS, ESQ. The Guaranty Building 140 Pearl Street, Suite 100 Buffalo, NY 14202

SCHILLINGER & ERIC K. SCHILLINGER, ESQ. ASSOCIATES, PLLC Attorneys for Defendant Kirk Ferrier 11 North Pearl Street, Suite 1700 Albany, NY 12207

DAVID N. HURD United States District Judge

DECISION and ORDER

I. INTRODUCTION Plaintiff Cipriani Construction Corp. (“Cipriani”) was hired to build a solar project. Cipriani subcontracted the electrical work to defendant GRN Electric and Solar Inc. (“GRN Electric”). GRN Electric began the work and Cipriani made payments that totaled $920,000. But GRN Electric’s crew eventually

walked off the job site and defendant Kirk Ferrier (“Ferrier”), GRN Electric’s principal and owner, demanded $375,000 more to finish the work. Cipriani refused to pay. Cipriani hired a different outfit, which completed the work for another million dollars or so. Cipriani later won an arbitration

award against GRN Electric. And Cipriani confirmed that award in Supreme Court, Albany County, which has entered a money judgment in its favor. But neither GRN Electric nor Ferrier have paid back a dime of the $920,000. On June 20, 2023, Cipriani filed this civil action in the U.S. District Court

for the Southern District of New York alleging, inter alia, that GRN Electric and Ferrier violated certain state-law requirements by failing to maintain in trust and/or properly account for the $920,000 that Cipriani had paid them under the parties’ written agreement. Dkt. No. 1. But because Cipriani had

mislaid venue in the Southern District, the action was sua sponte transferred to this judicial district on June 26, 2023. Dkt. Nos. 5, 9–11. On July 5, 2023, Cipriani filed a six-count amended complaint that asserts claims under Article 3-A of New York Lien Law seeking an accounting (Count

One) and for the alleged diversion of project funds that should have been held in trust (Count Two); a claim under New York General Business Law § 349 for deceptive practices (Count Five); and state common law claims for fraud (Count Three), negligent misrepresentation (Count Four), and conversion (Count Six). Dkt. No. 14. After the time period in which to file an answer

expired, Cipriani requested the entry of default against GRN Electric and Ferrier, Dkt. No. 22, which was certified on October 16, 2023, Dkt. No. 23. On December 29, 2023, Cipriani moved for the entry of a default judgment in the amount of $920,000 plus costs and fees. Dkt. No. 25. However, on the

date on which any opposition was due, counsel for defendant Ferrier entered a notice of appearance, Dkt. No. 27, and sought an extension of time in which to respond to Cipriani’s motion for default judgment, Dkt. No. 28, which was granted over Cipriani’s opposition, Dkt. Nos. 29, 30. Thereafter, defendant

Ferrier cross-moved to vacate or set aside his default (but not the entry of default against his co-defendant GRN Electric). Dkt. No. 31. Cipriani has opposed vacatur. Dkt. No. 32. Both motions have been fully briefed and will be considered on the basis of

the submissions without oral argument. II. BACKGROUND Cipriani is a general contractor organized as a New York corporation with headquarters in Colonie, New York. Am. Compl. ¶¶ 2, 7. GRN Electric is an

electrical subcontractor organized as a Delaware corporation based out of Long Branch, New Jersey. Id. ¶¶ 4, 8. Ferrier, the CEO and owner/operator of GRN Electric, also resides (or resided) in New Jersey.1 Id. ¶¶ 3, 9.

On August 24, 2021, Cipriani was hired to construct a solar project in Johnstown, New York (the “Project”). Am. Compl. ¶ 10. Cipriani met with Ferrier and then hired GRN Electric to handle certain electrical work on the Project. Id. ¶¶ 11–12. Cipriani and GRN Electric entered into a “Standard

Form of Agreement Between Contractor and Subcontractor for the Project” (the “Contract”). Id. ¶¶ 11–13 & Ex. A. The Contract set out a seven-week timeline for “substantial completion.” Id. Cipriani made payments totaling $920,000 in accordance with the Contract. Am. Compl. ¶ 15.

On December 30, 2021, just one day before “substantial completion” was required under the Contract, Ferrier directed GRN Electric’s work crew to walk off the job. Am. Compl. ¶ 16. Later that day, Ferrier, on behalf of GRN Electric, e-mailed to Cipriani a “change order” for $375,000 to be paid in a

series of three payments. Id. ¶ 17. Ferrier’s e-mail stated that GRN Electric would not resume work at the site until the first of these three payments had been made. Id. Cipriani requested a detailed explanation for the additional costs, but defendants failed to provide one.2 Id. ¶¶ 19–20.

1 Other filings suggest that Ferrier might now reside in Texas. Neither fact would necessarily establish his domicile.

2 In his declaration, Ferrier avers that Cipriani concealed the true nature of the site conditions, which led to a series of increased costs. Dkt. No. 31-4. On January 6, 2022, in accordance with § 3.5 of the Contract, Cipriani sent to GRN Electric, through Ferrier, a formal written notice directing them

to resume work “within five working days” or risk being replaced by another subcontractor and charged for the difference in cost. Am. Compl. ¶ 21 & Ex. B. But GRN Electric’s crew did not resume work. Am. Compl. ¶ 22. On January 21, 2022, Cipriani terminated the Contract for cause based on

GRN Electric’s failure to timely remedy its breach; i.e., its failure to resume work on the Project. Am. Compl. ¶ 23 & Ex. C. The January 21 letter also identified certain deficiencies with GRN Electric’s work on the Project. Am. Compl. ¶ 24–27. Cipriani later hired a substitute electrical contractor, which

completed the work at a substantial additional cost. See id. ¶ 40. On February 7, 2022, in accordance with § 76 of New York’s Lien Law, Cipriani sent to GRN Electric, through Ferrier, a letter demanding that GRN Electric provide a verified statement setting forth detailed information about

the identities of its materialmen and sub-subcontractors as well as the fate of the $920,000 in scheduled payments that Cipriani had already made under the Contract. Am. Compl. ¶ 28 & Ex. D. Cipriani’s February 7 Letter “specifically instructed” GRN Electric “not to

utilize any trust funds to pay for anything except those expenses authorized by New York Lien Law § 71(1) or (2)” and cautioned that “[f]ailure to abide by this provision can result in personal liability of the officer or director who makes such payment.” Am. Compl. ¶ 29 & Ex. D. To date, neither GRN Electric nor Ferrier have provided an accounting. Am. Compl. ¶ 30.

On March 4, 2022, in accordance with § 6.1 of the Contract, Cipriani filed a Demand for Arbitration with the American Arbitration Association (“AAA”) and served it on both GRN Electric and Ferrier. Am. Compl. ¶¶ 41–44 & Ex. E. In response, Ferrier petitioned in Supreme Court, Albany County to stay

the arbitration as to him because he was not a party to the Contract between Cipriani and GRN Electric. Am. Compl. ¶ 45 & Ex. F. Thereafter, Cipriani filed an amended arbitration claim that removed Ferrier, Am. Compl. ¶ 46 & Ex. G, and Ferrier’s petition was denied as moot, Am. Compl. ¶¶ 47–48.

Between July 8, 2022, and August 26, 2022, the AAA conducted a series of arbitration proceedings against GRN Electric. Am. Compl. ¶¶ 49–57.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Guggenheim Capital, LLC v. Birnbaum
722 F.3d 444 (Second Circuit, 2013)
Interworks Systems Inc. v. Merchant Financial Corp.
604 F.3d 692 (Second Circuit, 2010)
Aspro Mechanical Contracting, Inc. v. Fleet Bank, N.A.
805 N.E.2d 1037 (New York Court of Appeals, 2004)
Labarbera v. ASTC LABORATORIES INC.
752 F. Supp. 2d 263 (E.D. New York, 2010)
West-Fair Electric Contractors v. Aetna Casualty & Surety Co.
661 N.E.2d 967 (New York Court of Appeals, 1995)
Atlas Building System Inc. v. Rende
236 A.D.2d 494 (Appellate Division of the Supreme Court of New York, 1997)
Sibley v. Choice Hotels International, Inc.
304 F.R.D. 125 (E.D. New York, 2015)
United States v. Starling
76 F.4th 92 (Second Circuit, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
Cipriani Construction Corp. v. GRN Electric and Solar Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/cipriani-construction-corp-v-grn-electric-and-solar-inc-nynd-2024.