Cinemark Holdings, Inc v. Factory Mutual Insurance Company

District Court, E.D. Texas·Decided July 28, 2021·No. 4:21-cv-00011·Unknown

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF TEXAS SHERMAN DIVISION

CINEMARK HOLDINGS, INC., et al., § § Plaintiffs, § § v. § § Civil Action No. 4:21-CV-00011 FACTORY MUTUAL INSURANCE § Judge Mazzant COMPANY, § § Defendant. §

MEMORANDUM OPINION AND ORDER Pending before the Court is Plaintiffs’ Opposed Motion for Leave to File an Amended Complaint (Dkt. #58). Having considered the Motion, the Court finds it should be GRANTED. BACKGROUND Cinemark Holdings, Inc. (“Cinemark”) is the third largest movie theater circuit in the United States. To protect its property, Cinemark purchased an “All Risks” insurance policy (“the Policy”) from Factory Mutual Insurance Company (“Factory Mutual”). The Policy expressly includes coverage for physical loss or damage by a communicable disease. Cinemark paid over $3.7 million in premiums to Factory Mutual. In early 2020, the COVID-19 pandemic upended normal life in the United States. COVID- 19 is a deadly communicable disease that spreads in several ways, including changing the content of air and the character of surfaces. Over 1,700 Cinemark employees tested positive for, were exposed to, or displayed symptoms of COVID-19. Most of these employees were on Cinemark property just before testing positive. As a direct result of the damage caused by COVID-19 to its property, Cinemark was forced to close its theaters, incurring business income loss. Cinemark relied on its insurance coverage and submitted a claim to Factory Mutual on April 20, 2020. The Policy insures “against ALL RISKS OF PHYSICAL LOSS OR DAMAGE, except as hereinafter excluded, while located as described in this Policy.” (Dkt. #21, Exhibit 1 at p. 9). The Policy also “insures TIME ELEMENT loss . . . directly resulting from physical loss or

damage of the type insured.” (Dkt. #21, Exhibit 1 at p. 49). The Policy also lists “Additional Coverages.” These include the “Communicable Disease Response”1 and the “Interruption by Communicable Disease”2 coverages. The Policy contemplates that communicable diseases can cause loss or damage by excluding “loss or damage caused by or resulting from terrorism” from the Communicable Disease Coverages (Dkt. #21, Exhibit 1 at pp. 34, 69). Months passed with no response from Factory Mutual. By the time Cinemark sued in November 2021, Factory Mutual had not issued a coverage position. On June 3, 2021, Cinemark moved for leave to file its Third Amended Complaint (Dkt. #58). The deadline for Cinemark to file amended pleadings was June 16, 2021 (Dkt. #26 at p. 1). On June 17, 2021, Factory Mutual responded (Dkt. #63). On June 24, 2021, Cinemark replied

(Dkt. #71). LEGAL STANDARD “When a trial court imposes a scheduling order, Federal Rules of Civil Procedure 15 and 16 operate together to govern the amendment of pleadings.” Tex. Indigenous Council v. Simpkins, 544 F. App’x. 418, 420 (5th Cir. 2013). Rule 15(a) governs a party’s request to amend its pleading

1 The Communicable Disease Response section “covers the reasonable and necessary costs incurred by the Insured . . . for the . . . cleanup, removal and disposal of the actual not suspected presence of communicable diseases from the insured property.” (Dkt #21, Exhibit 1 at pp. 34-35 (bold in original)). 2 The Interruption by Communicable Disease section covers “the Actual Loss Sustained and EXTRA EXPENSE incurred by the Insured during the PERIOD OF LIABILITY at such location with the actual not suspected presence of communicable disease.” (Dkt. #21, Exhibit 1 at p. 69 (bold in original)). before a scheduling order’s deadline to amend passes. See id. Rule 16(b)(4) governs a party’s request to amend its pleading after the deadline to amend passes. Sapp v. Mem’l Hermann Healthcare Sys., 406 F. App’x. 866, 868 (5th Cir. 2010) (citing S&W Enters., L.L.C. v. SouthTrust Bank of Ala., NA, 315 F.3d 533, 536 (5th Cir. 2003)).

Rule 15(a) provides that a party may amend its pleading once without seeking leave of court or the consent of the adverse party at any time before a responsive pleading is served. After a responsive pleading is served, “a party may amend only with the opposing party’s written consent or the court’s leave.” Id. Rule 15(a) instructs the court to “freely give leave when justice so requires.” Id. The rule “‘evinces a bias in favor of granting leave to amend.’” Jones v. Robinson Prop. Grp., L.P., 427 F.3d 987, 994 (5th Cir. 2005) (quoting Lyn–Lea Travel Corp. v. Am. Airlines, Inc., 283 F.3d 282, 286 (5th Cir. 2002)). But leave to amend “is not automatic.” Matagorda Ventures, Inc. v. Travelers Lloyds Ins. Co., 203 F. Supp. 2d 704, 718 (S.D. Tex. 2000) (citing Dussouy v. Gulf Coast Inv. Corp., 660 F.2d 594, 598 (5th Cir. 1981)). Whether to grant leave to amend “lies within the sound discretion of the district court.” Little v. Liquid Air Corp., 952 F.2d

841, 845–46 (5th Cir. 1992). A district court reviewing a motion to amend pleadings under Rule 15(a) considers five factors: (1) undue delay; (2) bad faith or dilatory motive; (3) repeated failure to cure deficiencies by previous amendments; (4) undue prejudice to the opposing party; and (5) futility of amendment. Smith v. EMC, 393 F.3d 590, 595 (5th Cir. 2004) (citing Foman v. Davis, 371 U.S. 178, 182 (1962)). Rule 16(b)(4) provides that the Court’s scheduling order “may be modified only for good cause and with the judge’s consent.” See Agredano v. State Farm Lloyds, No. 5:15-CV-1067-DAE, 2017 WL 5203046, at *1 (W.D. Tex. July 26, 2017) (citing E.E.O.C. v. Serv. Temps Inc., 679 F.3d 323, 333–34 (5th Cir. 2012)) (stating, “a party seeking leave to amend its pleadings after a deadline has passed must demonstrate good cause for needing an extension.”). “The good cause standard requires the ‘party seeking relief to show that the deadlines cannot reasonably be met despite the diligence of the party needing the extension.’” S&W Enters., L.L.C., 315 F.3d at 535 (quoting 6A Charles Alan Wright & Arthur R. Miller, Federal Practice and Procedure § 1522.1 (2d ed. 1990)).

In determining whether good cause exists, courts consider a four-part test: “(1) the explanation for the failure to [timely move for leave to amend]; (2) the importance of the [amendment]; (3) potential prejudice in allowing the [amendment]; and (4) the availability of a continuance to cure such prejudice.” Id. (quoting Reliance Ins. Co. v. La. Land & Expl. Co., 110 F.3d 253, 257 (5th Cir. 1997)). Only after the movant demonstrates cause under Rule 16(b)(4) does “the more liberal standard of Rule 15(a)” apply to a party’s request for leave to amend. Id. ANALYSIS Cinemark asks for leave to amend its complaint to add an additional, substantively identical second policy to its claim for damages (See Dkt. #58). Specifically, Cinemark asks to extend the damages to include the time period between April 30, 2020 to April 30, 2021. Factory Mutual

opposes, arguing the amendment is futile and unduly prejudicial (See Dkt. #63).

Free access — add to your briefcase to read the full text and ask questions with AI

Cinemark Holdings, Inc v. Factory Mutual Insurance Company, (E.D. Tex. 2021).

Cinemark Holdings, Inc v. Factory Mutual Insurance Company (Cinemark Holdings, Inc v. Factory Mutual Insurance Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Lyn-Lea Travel Corp. v. American Airlines, Inc.
283 F.3d 282 (Fifth Circuit, 2002)
Smith v. EMC Corporation
393 F.3d 590 (Fifth Circuit, 2004)
Jones v. Robinson Property Group, L.P.
427 F.3d 987 (Fifth Circuit, 2005)
Foman v. Davis
371 U.S. 178 (Supreme Court, 1962)
Matagorda Ventures, Inc. v. Travelers Lloyds Insurance
203 F. Supp. 2d 704 (S.D. Texas, 2001)
Little v. Liquid Air Corp.
952 F.2d 841 (Fifth Circuit, 1992)