Cincinnati, Wilmington and Zanesville Railroad v. Iliff

13 Ohio St. 235, 13 Ohio St. (N.S.) 235
CourtOhio Supreme Court
DecidedDecember 15, 1862
StatusPublished
Cited by19 cases

This text of 13 Ohio St. 235 (Cincinnati, Wilmington and Zanesville Railroad v. Iliff) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cincinnati, Wilmington and Zanesville Railroad v. Iliff, 13 Ohio St. 235, 13 Ohio St. (N.S.) 235 (Ohio 1862).

Opinion

BriNKErhorr, J.

To give a construction to and to declare-the legal effect of contracts introduced in evidence to a jury, is undoubtedly the proper function of the court;-and it is the duty of the court, before whom the case is tried, so to do, if requested. But under the circumstances disclosed in the bill of exceptions, the failure of the court below to do so in this case involves no error. It would seem that by the voluntary acts, and actual or tacit consent of counsel on both sides,, the contract between the railroad company and Chamberlain for the construction of the road, was formally offered and received as a part of the evidence in the case ; but, as is quite common in practice, when neither party desires to have the written evidence adduced construed by the court, and when both parties are willing to trust its reading and interpretation to the jury, it was not read to either court or jury the attention of the court was not specially called to its provisions ; no request was made for its construction by the-court; and it was probably permitted to lie upon the table of counsel until the jury retired to deliberate on the verdict to-be rendered, and then, with other evidence, it was handed te them. To claim that the failure of the court to construe the contract under these circumstances is error, would be unfair, alike to the court and to the opposite party ; a.nd if the claim-were sustained, it would sanction what would often be a surprise upon both. If a party desires the construction of the court in regard to the contents of a written instrument in-evidence, he must in some way manifest such desire.

On the supposititious state of fact, to be found by the jury-on an examination of said contract, the court laid down the-[247]*247rule correctly, and in strict accordance with the ruling of this court in Cincinnati v. Stone, 5 Ohio St. Rep. 88. It charged, “that if they found from the contract, that the company did reserve the right to control the mode and manner of constructing the road, then, as to the damage sustained by the plaintiff outside of the one hundred feet not covered by the release, and also as to the damage done inside of said one hundred feet, in case they found, on the evidence and the law as before given, the release to be inoperative, the company was liable to the plaintiff for all damages he had proved he had sustained.” And to guard against the possible inference, from this general proposition, that the company might be held responsible for injuries by the contractor or his employees, growing out of acts not within the company’s reserved power to control, or for injuries not by a reasonable necessity involved in the very act of constructing the road, the court adds : “ in all respects falling within the limits of the right of the company so reserved to direct and controland “ that, beyond those limits, the company would be responsible only so far as the construction of the road, by a reasonable necessity, involved the doing of the damage complained of.”

I have considered the last exceptions first; for the reason that in respect to them, the majority of the court is very clear in the opinion that there was no error in the court below.

The first exception presents a question of more doubt and difficulty, but in respect to that also, the majority of the court is of opinion that there was no error.

The action was brought to recover damages for an alleged trespass upon, and appropriation of the plaintiff’s land, for the construction and use of a railroad. The railroad company answered, setting up, in bar of the action, an alleged release of the right of way to it by the plaintiff. The signing and sealing of the instrument of release was not contested by the plaintiff. But the point of contest was, whether the release had ever become operative by what, in law, amounted to an effective delivery. The record shows, and it was admitted1 [248]*248on all hands, that the paper, after being, signed and sealed, was put into the hands of one Carrol, who was an agent of the company to procure the right of way for its road, and who subsequently delivered the paper into the possession of the company without any other authority from the plaintiff than what was given by him when he parted with its immediate custody.

From the tenor of the charge of the court below .to the jury, it would seem to have been claimed there in behalf of the company, as it is claimed here, that the act of the plaintiff, in handing over the instrument of release to a known agent of the company to procure the right of way for its road, was, of itself, and necessarily, in law, an effective delivery to the company.

On the part of the plaintiff, it seems to have been contended, as it is contended here, that he did not deliver the paper as a completed iustrument of release to Carrol, as the agent of the company, to accept such delivery; but that, at the time he handed the paper over to Carrol, he distinctly constituted him his own agent, or depositáry, to hold the instrument as an escrow, until the performance of the condition mentioned in the statement of the case ; and, in case of its nonperformance, to return it to him; and that such act of handing the paper over to Carrol, was not, in law, a delivery to the company.

Such being the claims of the parties respectively, and evidence having been given by both parties in support of their respective claims, as to matters of fact, the court below charged the jury — “ that if they found the release of the .plaintiff was executed, and delivered by him to Carrol, upon the condition hereinbefore stated, and that the condition had not been performed at the time Carrol delivered the release to the company, the same was obligatory upon the plaintiff, if he knew, or had good reason to believe, at the time he so delivered the release to Carrol, that Carrol was the agent of the company for the purpose of procuring for it the right of way for its railroad through the county; unless Carrol was distinctly constituted the plaintiff’s agent, as well as the [249]*249agent of tbe company, for the purpose of holding and returning to him the paper, in case of the nonperformance of the condition; and that this could be done, although the plaintiff ¿new that Carrol was acting as the agent of the company in obtaining such right of way; that it was competent for the plaintiff, by plain and distinct terms, to constitute Carrol his own agent, for the purpose of holding the release, and returning it in case of the nonperformance of the condition; and that it made no difference that the company did not know of, or give its consent to, such agency in behalf of the plaintiff.”

The correctness of the first part of this charge is not controverted. It is certainly a distinct and unequivocal recognition and application of the general and undisputed doctrine, that a delivery of an instrument of grant, or release, to a known agent of the grantee or releasee, is, in law, a delivery to the principal; and that the instrument will be effective according to its terms, no matter what verbal stipulations may have been made at the time of its delivery, in respect to its operation after delivery. There can be no doubt, according to the uniform current of authority, that if, in this case; the instrument of release had been, as a completed instrument, delivered to Carrol simply as the agent of the company to procure the right of way, although the delivery may have been accompanied by verbal stipulations that the instrument should not operate

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell v. Turner
874 N.E.2d 820 (Ohio Court of Appeals, 2007)
Investment Research Institute, Inc. v. Sherbank Marketing, Inc.
731 N.E.2d 690 (Ohio Court of Appeals, 1998)
Bradley v. Farmers New World Life Insurance
679 N.E.2d 1178 (Ohio Court of Appeals, 1996)
Squire v. Branciforti
2 N.E.2d 878 (Ohio Supreme Court, 1936)
Whitaker & Fowle v. Lane
104 S.E. 252 (Supreme Court of Virginia, 1920)
Gross v. List
23 Ohio C.C. Dec. 579 (Tuscarawas Circuit Court, 1912)
Alabama Coal & Coke Co. v. Gulf C. & C. Co.
51 So. 570 (Supreme Court of Alabama, 1910)
Fitzgerald v. Allen
88 N.E. 240 (Illinois Supreme Court, 1909)
Goodhue v. Goodhue
3 Ohio N.P. (n.s.) 225 (Ohio Superior Court, Cincinnati, 1905)
McCormick Harvesting Machine Co. v. Morlan
96 N.W. 976 (Supreme Court of Iowa, 1903)
Dixon v. Bristol Savings Bank
31 S.E. 96 (Supreme Court of Georgia, 1897)
Schurtz v. Colvin
55 Ohio St. (N.S.) 274 (Ohio Supreme Court, 1896)
Ashford v. Prewitt
102 Ala. 264 (Supreme Court of Alabama, 1893)
Price v. Home Insurance
54 Mo. App. 119 (Missouri Court of Appeals, 1893)
Humphreys v. R. & M. R. R.
13 S.E. 985 (Supreme Court of Virginia, 1891)
Martin v. Taylor
52 Ark. 389 (Supreme Court of Arkansas, 1889)
Holt v. Colton
22 N.W. 495 (Supreme Court of Dakota, 1885)
Lyttle v. Cozad
21 W. Va. 183 (West Virginia Supreme Court, 1882)
Parker v. Parker
8 N.W. 806 (Supreme Court of Iowa, 1881)

Cite This Page — Counsel Stack

Bluebook (online)
13 Ohio St. 235, 13 Ohio St. (N.S.) 235, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cincinnati-wilmington-and-zanesville-railroad-v-iliff-ohio-1862.