Cianbro Corporation v. Curran-Lavoie, Inc., D/B/A Kenneth E. Curran, Inc.

814 F.2d 7, 3 U.C.C. Rep. Serv. 2d (West) 469, 1987 U.S. App. LEXIS 3470
CourtCourt of Appeals for the First Circuit
DecidedMarch 18, 1987
Docket86-1680
StatusPublished
Cited by132 cases

This text of 814 F.2d 7 (Cianbro Corporation v. Curran-Lavoie, Inc., D/B/A Kenneth E. Curran, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cianbro Corporation v. Curran-Lavoie, Inc., D/B/A Kenneth E. Curran, Inc., 814 F.2d 7, 3 U.C.C. Rep. Serv. 2d (West) 469, 1987 U.S. App. LEXIS 3470 (1st Cir. 1987).

Opinion

ROSENN, Senior Circuit Judge.

This highly fact intensive case arises out of a dispute over the sale of certain assets and road construction contracts by Curran-Lavoie, Inc. (Curran), a construction company, to Cianbro Corp. (Cianbro), in exchange for a $600,000 promissory note. The district court found that a settlement agreement between the parties resolved all prior disputes, so that Curran could no longer recover a sum of $18,855 it claimed Cianbro owed to it. The district court also found that Cianbro was entitled to “set-off” the disputed amount by withholding two payments due under the note now held by Kenneth E. Curran, Inc. 1 and that accordingly Cianbro was not in default on the note. We affirm. 2

I.

In 1978 Curran was actively engaged as a road construction contractor. It was experiencing certain difficulties, however, due primarily to its president’s illness and the State of New Hampshire’s decision to suspend contracted-for work on two major bridge projects in Keene, New Hampshire. As a result, representatives of Curran communicated with Cianbro for the purpose of selling inventory and equipment, and also *9 for the purpose of inducing Cianbro to complete several uncompleted contracts.

After a period of negotiation, the parties entered into a handwritten “Agreement for Sale” (the sales agreement) to take effect on September 1, 1978. The agreement provided, inter alia, that Curran would sell equipment and inventory, and assign four of its construction contracts, including the two Keene, New Hampshire projects, to Cianbro. In return, Cianbro agreed to pay Curran $600,000, to be evidenced by a promissory note. The note provided that Cianbro would pay Curran $600,000 plus 10% interest, payable monthly at a rate of $10,000 per month.

Because part of the sales agreement called for the assignment of the uncompleted construction contracts with the State of New Hampshire, State approval was required to substitute Cianbro as the contractor. New Hampshire refused to consent to the substitution of Cianbro for Curran on the contracts, however, and Cianbro therefore arranged to become a subcontractor. Accordingly, Curran remained as an intermediary to whom the State payments were made and Curran in turn transmitted the payments to Cianbro.

As a further complication, the State owed money to Curran for work Curran had performed prior to September 1, 1978 (the date the sales agreement became effective). At the August 1978 meeting at which the agreement of sale was prepared and signed, Curran and Cianbro were unable to determine the exact amount still owed to Curran by the State, and so they agreed to figure it out at a later meeting between their representatives. This meeting never took place. Further, Cianbro also recognized that Curran was entitled to damages from the State for extra work caused by the unwarranted shut-down of the Keene projects. 3 Cianbro agreed to compensate Curran for sums awarded by the State for these claims out of the checks forwarded by the State to Curran and transmitted by Curran to Cianbro.

In a letter dated November 8, 1978, Cur-ran informed Cianbro that Cianbro owed it a total of $137,441.03, subject to later correction, both for work in progress on September 1 and for extra costs. Cianbro disagreed with the amount and in an effort to resolve the dispute the parties exchanged letters for eight months.

In April 1979, Curran received and endorsed over to Cianbro a check for $174,-729.57 from the State for extra costs, including those incurred by Curran. On April 19, 1979, Cianbro’s engineer wrote to Curran indicating that Curran was entitled to $9,300 for the rental of steel sheet piling and $1,555 for overhead during the shutdown. On June 7, 1979, Cianbro’s chairman wrote Curran a letter agreeing that Curran was entitled to $8,000 for “Mobilization” on the Keene projects. The total of the three sums is $18,855, the amount at issue in Cianbro’s action against Curran.

Representatives of Curran and Cianbro ultimately met on August 29, 1979. Cur-ran claims that the meeting was conducted for the sole purpose of determining how much Cianbro owed to it for work in progress as of September 1, 1978, and that extra costs incurred by Curran prior to that time were neither discussed nor a part of their settlement agreement. 4 Cianbro, on the other hand, contends that the meeting was intended to resolve all disputed claims, and points to a letter sent by Curran the day before the meeting, which noted that the parties were “to meet tomorrow at Littleton to resolve all claims relative to the Sale of Curran-Lavoie, Inc. equipment and inventory, September 1, 1978.” The settlement agreement reached on August 29 was *10 drawn up by Curran, labeled “Final Estimate,” and read:

“Final Estimates for Projects in Progress, Curran-Lavoie, Inc. Sale September 1,1978 as invoiced November 8,1978 $137,441.03
At request of Tom Currier, Construction Engineer, extra costs experienced by Curran-Lavoie, Inc. because of the temporary work suspension order at Keene project, May 22,1978, were separated from original billing to Cianbro Corporation February 15,1979. Less 66,684.99*
Adjustment in accordance with information furnished by Cianbro Corporation letter dated June 7, 1979. Less 945.00
Adjustment per agreement reached at David Driscoll's office, Littleton, August 29,1979 Less 24,241.56
NET AMOUNT DUE CURRAN-LAVOIE, INC. $ 45,569.48
* indicates the total monies owed Cur-ran-Lavoie, Inc. by State of New Hampshire for extra expenses incurred because of temporary work suspension at Keene May 22, 1978, adjusted to correct for costs in excess of estimates as at November 8, 1978 are $66,684.99 plus $1,684.66, or $68,369.65.
Note: The above invoice is complete and final, per agreement reached this date, subject to a final adjustment relative to the performance and payment bond premiums upon receipt of audited invoices from The Rowley Agency, Inc. It is anticipated that a substantial additional bond premium must be paid for Keene P-2962-F because of extra work items approved by the Department. Also, it is understood that a credit will be generated by audit of Wentworth-Rumney project because of direct payment of all structural steel by NCS. This subject will be reviewed and reported to Cianbro as soon as available after acceptance and approval by the State of New Hampshire.

(Emphasis added).

Curran states that the starting figure of $137,441.03 represents what Curran claimed was owed to it for both the work in progress and the extra costs, including the $18,855 Cianbro had acknowledged was due Curran and which Cianbro had received. Subtracted from that was $66,684.99, which Curran states is the amount it had previously claimed represented the extra costs, including the $18,855.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hadley v. Capone
D. Massachusetts, 2024
Art Technology Group, Inc. v. Puritan's Pride, Inc.
716 F. Supp. 2d 93 (D. Massachusetts, 2010)
World Energy Alternatives, LLC v. Settlemyre Industries, Inc.
671 F. Supp. 2d 215 (D. Massachusetts, 2009)
D’Jamoos v. Atlas Aircraft, et al.
2009 DNH 170 (D. New Hampshire, 2009)
Mercado-Salinas v. Bart Enterprises International, Ltd.
669 F. Supp. 2d 176 (D. Puerto Rico, 2009)
Wiley v. GERBER PRODUCTS COMPANY
667 F. Supp. 2d 171 (D. Massachusetts, 2009)
Rivera-Carmona v. American Airlines
639 F. Supp. 2d 194 (D. Puerto Rico, 2009)
Jackson v. Economou et al
2008 DNH 094 (D. New Hampshire, 2008)
Jackson National Life Insurance v. Economou
557 F. Supp. 2d 216 (D. New Hampshire, 2008)
Massachusetts Institute of Technology v. Micron Technology, Inc.
508 F. Supp. 2d 112 (D. Massachusetts, 2007)
Weiss Ex Rel. Fibercore, Inc. v. OFS FITEL, LLC
361 B.R. 315 (D. Massachusetts, 2007)
Bracero v. New Tree Personnel Services, Inc.
441 F. Supp. 2d 358 (D. Puerto Rico, 2006)
Commodity Futures Trading v. Cromwell
2006 DNH 019 (D. New Hampshire, 2006)
TransCanada Power Marketing, Ltd. v. Narragansett Electric Co.
402 F. Supp. 2d 343 (D. Massachusetts, 2005)
Cruickshank v. Clean Seas Co.
402 F. Supp. 2d 328 (D. Massachusetts, 2005)
Wolverine Proctor & Schwartz, Inc. v. Aeroglide Corp.
394 F. Supp. 2d 299 (D. Massachusetts, 2005)
Intercall Telecommunications, Inc. v. Instant Impact, Inc.
376 F. Supp. 2d 155 (D. Puerto Rico, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
814 F.2d 7, 3 U.C.C. Rep. Serv. 2d (West) 469, 1987 U.S. App. LEXIS 3470, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cianbro-corporation-v-curran-lavoie-inc-dba-kenneth-e-curran-inc-ca1-1987.