Ciacci v. Woolley

33 Haw. 247, 1934 Haw. LEXIS 10
CourtHawaii Supreme Court
DecidedDecember 8, 1934
DocketNo. 2162.
StatusPublished
Cited by37 cases

This text of 33 Haw. 247 (Ciacci v. Woolley) is published on Counsel Stack Legal Research, covering Hawaii Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ciacci v. Woolley, 33 Haw. 247, 1934 Haw. LEXIS 10 (haw 1934).

Opinion

*249 OPINION OF THE COURT BY

PARSONS, J.

This is an action for damages for injury to the plaintiff alleged to have been proximately caused by the negligence of defendant, a building contractor, in the faulty construction of a scaffolding upon which the plaintiff, a plasterer, was working at the time he received said injury. Verdict and judgment in the trial court were for the plaintiff and the case is before us upon the defendant’s bill of exceptions. The bill contains fifteen exceptions, one of which, the eighth, has been waived.

Exception one is to the overruling of defendant’s demurrer to plaintiff’s first and second amended complaints.. The record before us shows a demurrer to plaintiff’s *250 amended complaint filed February 1, 1934, a minute order overruling the same, an exception thereto noted by the defendant and an order allowing the defendant ten days within which to answer. Defendant’s answer, a general denial, was filed February 8, 1934. By permission of the court a second amended complaint was filed April 5, 1934, subject to defendant’s demurrer and answer to the first amended complaint.

. The plaintiff’s second amended complaint alleges in effect and among other things that on or about January 1, 1932, the defendant, a general contractor, entered into a contract with S. H. Kress & Company, a foreign corporation, for the construction of an addition or enlargement of its store premises at No. 1117 Fort Street, Honolulu; that in order to complete said contract in accordance with the plans and specifications therefor, certain plastering work was required to be done on said structure by defendant; that defendant entered into a subcontract with one George F. Larsen to furnish the material and labor necessary to do said plastering, and plaintiff, a plasterer by trade, was employed by the said George F. Larsen, together' with other workmen of like craft, to do said plastering; that in the construction of said building it was necessary for defendant to construct and he did construct certain scaffolding for the use of the workmen working on said structure, including the plaintiff, which said scaffolding plaintiff was required to use in his work as a plasterer; that said scaffolding was unsafe and insecure and was constructed in a negligent way and without regard to the safety of plaintiff and other workmen using said scaffolding ; that the plaintiff believing said scaffolding had been constructed in a safe and workmanlike manner and relying on the safety of the same and being obliged to use said scaffolding and having no choice but to use the same was, on the 22d day of July, 1932, working on said scaf *251 folding plastering the ceiling of said structure, Avhen without Avarning and Avithout negligence on plaintiff’s part the flooring of said scaffolding upon AAdiich plaintiff was standing at said time suddenly gave Avay and in the ensuing fall and efforts to save himself from striking the floor beloAV plaintiff grasped a cornice of said building and in doing so suffered severe and painful injuries to his shoulder, dislocating the same, Avrenching the muscles and tendons thereof and causing him great pain and anguish; that the injuries received by the plaintiff as aforesaid Avere proximately caused by the negligence and carelessness of the defendant as aforesaid in the construction of said scaffolding and his disregard of the safety of plaintiff while engaged as a workman upon said scaffolding as aforesaid. Then folloAvs a more detailed description of plaintiff’s injuries, an allegation that they are not compensable under the Workmen’s Compensation Act by reason of the fact that plaintiff Avas in receipt of Avages in excess of thirty-six dollars a week, allegations of general and special ad damnum in the aggregate sum of $9300 and prayer for judgment.

The grounds of demurrer relied upon by defendant as set forth in his opening brief are as follows: “(a) That it does not appear from said complaint that defendant was under any duty under his subcontract with George F. Larsen to construct the scaffolding referred to in said complaint or any scaffolding for the use of employees of said Larsen; (b) That it does not appear from said complaint that defendant intended the said scaffolding erected by him for the use of plaintiff; (c) That it does not appear from said complaint that defendant knew or should have known that said scaffolding would be used by plaintiff ; (d) That there are no facts alleged in said complaint sufficient to show Avherein defendant owed any duty of care to plaintiff.” These grounds do not require lengthy *252 consideration. They were addressed to the first amended complaint and are not wholly applicable to the second amended complaint which amplifies the averments of the first. The record does not show any ruling upon them as applied to the second amended complaint and consequently no exception with reference to them subsequent to the exception to the order overruling the demurrer to the first amended complaint. Assuming, but not deciding, that the former ruling overruling the demurrer and exception thereto now applies to the second amended complaint — the said grounds are disposed of as follows: As to ground (a), the allegation of the complaint (in its context) of necessity of construction and fact of construction of scaffolding by defendant is a sufficient allegation of defendant’s duty in the premises without setting forth specifically that said necessity arose out of contract with George F. Larsen. Under it proof that the duty arose under such contract was properly offered and admitted without objection; and allegation and proof are sufficient in this respect to sustain the verdict and judgment.

Ground (b) is negatived by the recitals herein of the allegations of the second amended complaint. Ground (c) is not sufficient in law to sustain defendant’s demurrér. In the circumstances herein recited no averment that defendant knew or should have known that said scaffolding would be used by plaintiff was required. The averment above recited as to the necessity and fact of the erection by the defendant of the scaffolding for the use of the subcontractor’s workmen, including the plaintiff, in its above recited context was sufficient in the premises.

The exact points relied upon by the defendant in ground (d) “that no facts are alleged to show defendant owed a duty toward plaintiff, Avith reference to the safety of the scaffolding” are not set forth in the argument of exception one in the brief. The allegations as to the con *253 tractor’s undertaking and construction for the purposes aboA'e named and in the above recited circumstances sufficiently shoAV a duty on his part to exercise ordinary care to provide for the workmen of his subcontractor, including the plaintiff, a reasonably safe place in Avhich to Avork. Metzger v. Cramp Co., 235 Pa. 17, 83 Atl. 590; Steele v. Grahl-Peterson, 135 Ia. 418, 109 N. W. 882; Pettingill v. Porter & Son, 219 Mass. 347; Bright v. Barnett & Record Co., 88 Wis. 299.

Defendant’s exception ttvo is to the order

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Winfrey v. GGP Ala Moana LLC.
308 P.3d 891 (Hawaii Supreme Court, 2013)
Rodriguez v. GEN. DYNAMICS ARMAMENT & TECH. PRODS.
696 F. Supp. 2d 1163 (D. Hawaii, 2010)
Ditto v. McCurdy
947 P.2d 961 (Hawaii Intermediate Court of Appeals, 1997)
Carlos v. MTL, INC.
883 P.2d 691 (Hawaii Intermediate Court of Appeals, 1994)
State v. Pinero
859 P.2d 1369 (Hawaii Supreme Court, 1993)
Akiona v. United States
938 F.2d 158 (Ninth Circuit, 1991)
GWC Restaurants, Inc. v. Hawaiian Flour Mills, Inc.
691 F. Supp. 247 (D. Hawaii, 1988)
Stewart v. Brennan
748 P.2d 816 (Hawaii Intermediate Court of Appeals, 1988)
Armstrong v. Cione
736 P.2d 440 (Hawaii Intermediate Court of Appeals, 1987)
Jenkins v. Whittaker Corp.
785 F.2d 720 (Ninth Circuit, 1986)
Jenkins v. Whittaker Corporation
785 F.2d 720 (Ninth Circuit, 1986)
Agee v. Kahului Trucking & Storage, Inc.
688 P.2d 256 (Hawaii Supreme Court, 1984)
Medina v. Figuered
647 P.2d 292 (Hawaii Intermediate Court of Appeals, 1982)
Wakuya v. Oahu Plumbing & Sheet Metal, Ltd.
636 P.2d 1352 (Hawaii Intermediate Court of Appeals, 1981)
Turner v. Willis
582 P.2d 710 (Hawaii Supreme Court, 1978)
Winter v. Scherman
554 P.2d 1137 (Hawaii Supreme Court, 1976)
Low v. Honolulu Rapid Transit Co.
445 P.2d 372 (Hawaii Supreme Court, 1968)
Kometani v. Heath
431 P.2d 931 (Hawaii Supreme Court, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
33 Haw. 247, 1934 Haw. LEXIS 10, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ciacci-v-woolley-haw-1934.