Church of St. Patrick v. Dakin

1 Rob. 202
CourtSupreme Court of Louisiana
DecidedDecember 15, 1841
StatusPublished
Cited by1 cases

This text of 1 Rob. 202 (Church of St. Patrick v. Dakin) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Church of St. Patrick v. Dakin, 1 Rob. 202 (La. 1841).

Opinion

Garland, J.

In the month of June, 1838, the plaintiffs entered into a contract with the defendants, by which the latter undertook, for the sum of $115,000, to construct and complete the building known as St. Patrick’s Church, in this city, upon certain terms and conditions. The contract, among various other stipulations, says :

‘ It is furthermore agreed, that if any difficulty shall occur between the aforesaid parties, growing out of the works herein specified, which they, the said parties, cannot settle amicably between themselves, then and in that case, the subject or matter in dispute [203]*203shall be referred to three or five disinterested persons, to be chosen by the said parties in the usual manner, who shall be fully competent and qualified to judge and decide upon all questions and matters arising out of the eredion of said building and works; the decision of which said persons, chosen as aforesaid, shall to all intents and purposes, be final and binding in the premises, without any appeal therefrom whatsoever.’

* It is also agreed and understood, that any and all contentions or matters of difference whatsoever, arising in the premises, shall be settled and adjusted in the manner above mentioned, and that in no case shall the aforesaid parties be permitted to have recourse or appeal to any court of justice for the settlement of any such contentions or differences.’

In'the execution of the contract various disagreements arose be^ tween the trustees and contractors, although the superintendence of the work was confided to a building committee named by th.e plaintiffs at the time of making the contract, which differences, jt was agreed should be submitted, in conformity to the contract, to arbitrators. On the 23d of August, 1839, a bond was signed by the parties, in which, after reciting the terms of the contract, it is said: ‘ now as differences have arisen between the said board of trustees and the said firm, of Dakin & Dakin, they hereby agree to. submit all such difficulties, and contentions, and matters of difference whatsoever, arising in the premises,’’ to five persons, * the decision of which five persons, shall to all intents and purposes, bte final and binding in the premises, without any appeal therefrom.’

Under' this submission, the parties appeared before the arbitra: tors, and on the part of the plaintiffs, it was alleged:

- 1. That the defendants had violated the contract, by failing to comply with its specifications. 2. That they had failed to place bond limbers in the walls, under all the openings, to prevent cracks and equalize the settling of the building. '3. That they had failed to bind the buttresses to the walls with suitable timbers, as agreed on, to-preventthemfrom cracking off, fro'm-the main walls. 4. That they had not put in the window frames, and completed the wood work as the walls were put up, whereby they were weakened. 5. That the walls had cracked, and the work was executed in an inferior manner. 6.. The plaintiffs ask that the whole contract be [204]*204annulled and damages awarded them, it being impossible, from the hostility of the undertakers, to finish the church under their superintendence.

What the precise propositions submitted by the defendants to the arbitrators were, does not distinctly appear, but it seems that they objected to the submission of the question, of annulling the contract on the ground of the alleged hostility of the parties.

The arbitrators, after an examination of some testimony, of the contract, and the building, decided :

1. That the defendants had violated their contract by omitting to place bond timbers in the walls, as required, in consequence of which they were weakened and otherwise injured.

2. That as the contract required the inside of the walls to be framed and battened out for lath-work, the said arbitrators were of opinion that wall' strips should have been put in the wall as it went up, as attempts to nail on or attach pieces for the purpose would weaken the'walls.

The arbitrators then proceed to specify various remedies for the defects in the work, and conclude :

3. ‘ That as it appears from some misunderstanding between the parties, feelings of a hostile nature have arisen between them, which must inevitably prevent them from proceeding together in the further progress of the building, with that degree of harmony which should exist between parties so connected, it is, in our opinion, much better for both parties, that the contract between them be now annulled ; but in doing this a sufficient recompense should be made to Messrs. Dakin & Dakin for their plans, and for the trouble they have had in conducting the progress of the building thus far, making due allowance, however, for the damages to which they have subjected themselves, by the aforesaid omissions,

They therefore decree that the contract be annulled, that Dakin & Dakin have $5000 for their plans of the building, and that thpy pay $5000 damages to the plaintiffs. They further decree that the trustees, as a compensation to defendants for their labor and trouble, shall allow them eight percent upon the amount of money already expended upon the building, over and above the actual cost expended thereon, such cost to be ascertained by proper vouchers, or bills and receipts furnished therefor.’ All contracts made by Da? [205]*205kin & Dakin, previous to the submission, for labor or materials, to be assumed by the trustees, who are also to pay for all materials upon the premises. They conclude by saying that if, upon the settlement of the said accounts, Dakin & Dakin shall be indebted to the trustees, the amount shall be deducted from the price of the drawings before mentioned.

In this situation the award leaves the parties. The trustees file it with the»notary, in whose custody the original contract is, and upon a certified copy, and an account, stated by themselves, showing a balance of $1807 60 against the defendants, they commence this suit, praying that the said defendants be compelled to comply with said award, that it be approved and confirmed, and its execution decreed and enforced. To this the defendants object, on a variety of grounds, among others:

1. That the award is null, because the arbitrators exceeded their powers, and passed on matters not submitted to them, and particularly in annulling the contract.

2. The award is void for uncertainty, inasmuch as it does not enable the court to give any judgment or decree for the payment of any specific sum to either party.

3. That it is not a final settlement and adjustment of all the accounts and matters in controversy between the parties, which were referred to the arbitrators.

The other objections taken by the defendants, it is not now necessary to notice; nor is it material, in the view we have taken of the case, to decide upon the bills of exceptions taken by both parties.

The judge of the Commercial Court heard the testimony offered by both parties, and after a learned opinion gave a judgment ho-mologating and confirming the award, and decreeing ‘ that either party be at liberty to apply to the court to take steps to fix :

‘ 1. The value of the materials on the premises at the time of the award.

‘ 2, The amount on which defendants are to be allowed their compensation of eight per cent on monies expended.

3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The General Parkhill
1 E.D. Pa. 479 (E.D. Pennsylvania, 1861)

Cite This Page — Counsel Stack

Bluebook (online)
1 Rob. 202, Counsel Stack Legal Research, https://law.counselstack.com/opinion/church-of-st-patrick-v-dakin-la-1841.