Christie v. United States

48 Ct. Cl. 293, 1913 U.S. Ct. Cl. LEXIS 113, 1912 WL 1194
CourtUnited States Court of Claims
DecidedApril 7, 1913
DocketNo. 24693
StatusPublished

This text of 48 Ct. Cl. 293 (Christie v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Christie v. United States, 48 Ct. Cl. 293, 1913 U.S. Ct. Cl. LEXIS 113, 1912 WL 1194 (cc 1913).

Opinions

Howry, J.,

delivered the opinion of the court:

Plaintiffs are contractors residing and doing business in Chicago, but carrying on extensive contracting work throughout the country.

For the consideration of $440,000 they, on March 10, 1900, entered into a contract in writing with the United States for continuing the improvement of the Warrior Eiver, in the State of Alabama, for the purpose of securing a navigable, depth of 6 feet of water from Mobile to Birmingham. The improvements called for by this contract were in addition to $220,000 theretofore appropriated and expended for the same purpose.

Advertisements for sealed proposals 'for building Locks and Dams Nos. 4, 5, and 6 on this river were published stating the requirements of the Government in the specifications. Plaintiffs made a proposal in writing on the specifications which described that the dam should be built of timber cribwork, tightly sheathed, and filled with gravel or stone, and to rest on pile foundations. The work was to conform generally to drawings exhibited and to such others in explanation of details or showing modifications of plans as might be furnished from time to time during construction. (Par. 40, Spec.)

The specifications provided that maps of the localities might be seen at the office of the United States engineer at Tuscaloosa, Ala., until January 20, 1900. Bidders were notified that they were expected to visit the premises and to make their own estimates of the facilities and difficulties attending the execution of the work, including the uncertainty of weather and other contingencies. (Par. 3, Spec.)

By paragraph 38 it was provided that the quantities of material called for and necessary for the work were approximate only, and that no claim should be made against the United States on account of any excess or deficiency, absolute or relative. Bidders were told that they were expected to examine the drawings and invited to make the estimates [322]*322of quantities for themselves, though they were informed .that it was not expected that the actual quantities would vary more than 10 per cent from the estimates.

The work was to begin 30 days from date of notification of 'approval of the contract and completed not later than December 31, 1901.

Two members of the contracting firm visited Tuscaloosa to secure information upon which to prepare their bid. They drove to the site of one of the locks and dams and, being satisfied, declined to visit the site of the other two locks and returned to Tuscaloosa, which was on the river. and not greatly distant from the site of the. locks.

The contract provided that—

“The engineer officer shall have the power to prescribe the order and manner of executing the work in all its parts; of inspecting and rejecting materials, work, and workmanship which in his judgment do not conform to the drawings that may be furnished from time to time, or to these specifications. Any material, work, or workmanship so rejected by him shall be kept out of or removed from the finished work, and no estimate or payment shall be made until such material, work, or workmanship be so removed. * * * In all cases of dispute the decision of the engineer officer in charge will be accepted as final and without appeal.” (Par. 18.)

The right was reserved to make minor changes in the specifications and letting plans, but no modifications were to- be made the basis of claims for extras unless so provided by written supplementary agreement.

The specifications were stated to be intended to be “ full, clear, and complete ”; any doubt as to their meaning or obscurity in the wording was to be explained by the engineer officer, who reserved the right to correct any errors or omissions as such became apparent.

. Plaintiff encountered difficulties. Warrior River is an alluvial stream, and its fluctuations between low water in summer and high water in winter and early spring ranges from less than 1 foot to more than 70 feet. In flood stages the river overflows its banks and spreads out over the adjacent. country from 2 to 5 miles. On account of freshets, floods, and epidemics of fever and malaria during the work[323]*323ing season of the year that the contract was let, and the scarcity and difficulty of procuring labor during the second, third, and fourth years of the contract, the time for the completion of the work was extended on application of the contractors on March 18, 1901, to December 31, 1902, without the deductions provided for by the specifications.

Again, on March 12,1902, there was a further extension of time upon written application from the contractors to December 31, 1903. The causes were embodied in a supplemental contract dated April 29, 1902, and the prescribed deductions for expected failure to complete were remitted.

Locks and Dams Nos. 5 and 6 were completed by plaintiffs and accepted by the United States in December, 1902, and Lock and Dam No. 4 was completed and accepted in like manner in November, 1903. Embraced in the settlement for all work done by the contractors were sums amounting to $469,144.37, which included extras, in addition to the contract price originally named.

But plaintiffs allege that there were other causes which made an extension of the time for the completion of the contract necessary, such as delay in notifying the contractors that stone would be required in place of sand and gravel; changes in the quantities of stone required; increased quantity of excavation at one of the locks under the supplemental contract; and delay in securing title to the land where an abutment was to be erected at one of the locks. The breaches alleged to have arisen may be summarized, viz: (1) From delays and causes just stated; (2) from untrue and misleading statements of fact contained in the specifications charged to have been known by certain subordinate officers; (3) from unauthorized changes in the plans and specifications; and (4) from the appointment of incompetent inspectors whose supervision of the work was alleged to have been unintelligent and unreasonable.

The record is voluminous with pleading, testimony and exhibit, statement and argument. Supplemental to three large volumes of printed matter there are photographs and maps, account books and tables relating to excavations and embankments, and much matter in manuscript. The court [324]*324discovers important testimony not in the printed record and does not understand why, under the order to print, any testimony of importance should have been omitted from the printed volumes. But after careful investigation the court has made the findings which must determine whether they support the conclusions.

The second finding disposes of the contentions respecting delays in permitting commencement of the work. By the finding it is shown that between the conditions caused by floods in the river and the delays caused by the Government the delay did not rest wholly upon one side to the controversy. Thus, when one of the contractors arrived to begin the work the river was in such a state of flood that the gauge registered 37 feet above low water at Tuscaloosa; on April 10 the water had fallen 10 feet, but rose again in 9 days to a height of 66 feet, gradually receding until 21 feet was registered the 1st of May.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. Richards
38 U.S. 26 (Supreme Court, 1839)
Schuchardt v. Allens
68 U.S. 359 (Supreme Court, 1864)
Martinsburg & Potomac Railroad v. March
114 U.S. 549 (Supreme Court, 1885)
Sun Insurance v. Kountz Line
122 U.S. 583 (Supreme Court, 1887)
Southern Development Co. v. Silva
125 U.S. 247 (Supreme Court, 1888)
Lyng v. Michigan
135 U.S. 161 (Supreme Court, 1890)
Gleeson v. Virginia Midland Railroad
140 U.S. 435 (Supreme Court, 1891)
Lehigh Zinc and Iron Company v. Bamford
150 U.S. 665 (Supreme Court, 1893)
Simpson v. United States
172 U.S. 372 (Supreme Court, 1899)
Los Angeles v. Los Angeles City Water Co.
177 U.S. 558 (Supreme Court, 1900)
Ripley v. United States
223 U.S. 695 (Supreme Court, 1912)
Webster v. Bailey
31 Mich. 36 (Michigan Supreme Court, 1875)
Wilder v. DeCou
18 Minn. 470 (Supreme Court of Minnesota, 1872)
Wannell v. Kem
57 Mo. 478 (Supreme Court of Missouri, 1874)
Barndt v. Frederick
11 L.R.A. 199 (Wisconsin Supreme Court, 1890)

Cite This Page — Counsel Stack

Bluebook (online)
48 Ct. Cl. 293, 1913 U.S. Ct. Cl. LEXIS 113, 1912 WL 1194, Counsel Stack Legal Research, https://law.counselstack.com/opinion/christie-v-united-states-cc-1913.