Chris Hill Construction Company v. State of Tennessee

Court of Appeals of Tennessee·Decided February 4, 1999·No. 02A01-9803-BC·Published

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON JANUARY 1999 SESSION

CHRIS-HILL CONSTRUCTION ) Tennessee Claims Commission COMPANY, ) Western Division, Claim 204648 )

v.

Claimant/Appellant, )

)

)

FILED

Appeal No. 02A01-9803-BC-

00057 February 4, 1999 )

STATE OF TENNESSEE, ) Cecil Crowson, Jr.

Appellate C ourt Clerk

)

Defendant/Appellee. )

APPEAL FROM THE TENNESSEE CLAIMS COMMISSION WESTERN DIVISION AT MEMPHIS HONORABLE MARTHA BRASFIELD, COMMISSIONER

For the Appellant: James W. McDonnell, Jr. O. John Norris WYATT, TARRANT & COMBS 6075 Poplar Avenue, Suite 650 Memphis, TN 38119-4721

For the Appellee: John Knox Walkup Attorney General and Reporter

Mary G. Moody Senior Counsel

Laura T. Kidwell Assistant Attorney General 425 Fifth Avenue North Second Floor, Cordell Hull Bldg. Nashville, TN 37243-0488

AFFIRMED WILLIAM H. INMAN, SENIOR JUDGE CONCUR: W. FRANK CRAWFORD, JUDGE

DAVID R. FARMER, JUDGE OPINION

The Facts

This claim arises from Chris-Hill Construction Company’s (“claimant”)

participation in bidding on a Tennessee Department of Transportation (“TDOT”) project for widening and improving the bridges and approaches over the Illinois Central Railroad, Tarent Branch and Cane Creek on U.S. 51 in Shelby County (“the project”). The plans and specifications for this project were prepared by TDOT which furnished them to interested bidders, including Chris-Hill and Dement Construction Company (“Dement”).

Bobby Garland of the TDOT was available to prospective bidders to answer questions about contract requirements. Danny Stoppenhagen and J. B. Hill, representatives of Chris-Hill, contacted Garland to enquire if TDOT would enforce a note on the plans prohibiting the placement of a crane on the existing bridge in order to drive pilings. After checking with the TDOT Structures Division, Garland informed them that the note would be enforced. Chris-Hill thereupon added the costs of constructing a berm upon which to locate a platform for the crane to its bid.

On February 13, 1991, two days before the bids were to be opened, Dement Vice-President Ty Capps contacted Garland and advised him that there were conflicting provisions in the plans and specifications regarding the requirement of seismic connections in the bearing pilings for the bridges. He requested that TDOT issue an addendum to the contract clarifying the matter. Garland reviewed the plans and specifications and talked with Danny Stoppenhagen about his interpretation of them, and thereupon determined that there was a conflict in the documents. On February 14, Garland told Capps that an addendum clarifying the

requirements for seismic connections on the pilings would not be issued because it was too late to issue a clarification to all interested bidders. He told Capps to bid the job based upon his own (Capps’) interpretation of the plans. On the same day, Stoppenhagen called Garland asking if “anything else had developed regarding the seismic piling.” Garland advised Stoppenhagen, as he had advised Capps, that he should bid the job based upon his own (Stoppenhagen’s) interpretation of the documents.

On February 15, 1991, the bids were submitted and opened. The two lowest bidders were Dement at $1,463,378 and Chris-Hill at $1,525,529. The contract was awarded to Dement. During the bid review process, Garland determined that Dement would still be the lowest bidder after adding $10,200 (Dement’s estimated price for the seismic connections in controversy) to its bid as submitted.

After the contract was awarded, Dement and the TDOT agreed that the contract was ambiguous about whether the use of seismic connections in the bearing pilings for the bridges was required. As provided for in the Standard Specifications for Road and Bridge Construction, Dement and TDOT executed a supplemental agreement paying Dement $150 per connection for the seismic connections, for a total of $10,200. This amount would have been paid to Chris- Hill had it been the successful bidder.

After construction began, Dement obtained permission from TDOT to place a crane on the existing bridge in order to drive some of the pilings for the project, which eliminated the need to construct a berm or base for that purpose.

The contract required the installation of a double row of sheet piling parallel to the Illinois Central tracks in order to maintain the stability of the tracks during the excavation for and driving of the concrete bridge pilings. Claimant complained

that Dement was not only using a crane on the existing bridge, but had installed only one row of sheet piling, in violation of the contract.1 Dement was thereupon instructed by TDOT to install the second row.

Chris-Hill filed this claim alleging that it sustained damages as a result of the negligence of the TDOT, in allowing Dement to use the existing bridge as the platform from which to drive the required pilings in violation of the contract. Claimant alleged that if the “secret variation” had been disclosed, the expense incurred for the construction of a berm would not have been required and consequently it would have been the low bidder. This action by TDOT is alleged to have been in violation of T.C.A. § 9-8-307(a)(1)(I) and (N) as hereafter stated. Claimant alleged further variations previously discovered.

Because TDOT always prepared its own cost estimates on projects, claimant requested production of TDOT’s estimate of the costs involved in driving the pilings. This request was refused.

At the close of the claimant’s case the Commissioner granted the motion of TDOT to dismiss, holding that there was no evidence that TDOT granted DEMENT the variance prior to the bidding and thus no negligence.

Issues Presented for Review

1. Did the claimant present a prima facie case of negligence, or as enlarged by TDOT, what rights do the provisions of T.C.A. § § 54-5-

114 --118 convey upon those bidding on a state highway project in accordance with those statutes?

2. Does T.C.A. § 9-8-307(a)(1)(I) provide jurisdiction in the Tennessee Claims Commission for claims by unsuccessful bidders on Tennessee Department of Transportation construction projects, alleging that the State was negligent in allowing the successful bidder to deviate from the original plans and specifications?

1 Dement had discussed the matter with the railroad, who advised Dement that one row was adequate. But the TDOT thought otherwise and insisted on a double row as the contract specified.

3. Was the Commissioner correct in refusing to compel the State to Produce its construction estimate for this project?

Standard of Review

The case was involuntarily dismissed pursuant to Rule 41.02(2), T.R.C.P., which requires a consideration of the standard prescribed in City of Columbia v. C. F. W. Const. Co., 557 S.W.2d 734 (Tenn. 1977):

But in the non-jury case, when a motion to dismiss is made at the close of plaintiff’s case under Rule 41.02(2), the trial judge must impartially weigh and evaluate the evidence in the same manner as though he were making findings of fact at the conclusion of all of the evidence for both parties, determine the facts of the case, apply the law to those facts, and, if the plaintiff’s case has not been made out by a preponderance of the evidence, a judgment may be rendered against the plaintiff on the merits, or, the trial judge, in his discretion, may decline to render judgment until the close of all the evidence.

The action should be dismissed if on the facts found and the applicable law the plaintiff has shown no right to relief.

This court’s scope of review of the Commissioner’s decision is pursuant to Rule 13(d), T. R. A. P. The findings of the trial court in granting a Rule 41.02(2) motion are accompanied by a presumption of correctness and, unless the preponderance of the evidence is otherwise, those findings must be affirmed. Atkins v. Kirkpatrick, 823 S.W.2d 547, 552 (Tenn. App. 1991).

Discussion

Free access — add to your briefcase to read the full text and ask questions with AI

Chris Hill Construction Company v. State of Tennessee, (Tenn. Ct. App. 1999).

Chris Hill Construction Company v. State of Tennessee (Chris Hill Construction Company v. State of Tennessee) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Haynes v. Hamilton County
883 S.W.2d 606 (Tennessee Supreme Court, 1994)
City of Columbia v. C.F.W. Construction Co.
557 S.W.2d 734 (Tennessee Supreme Court, 1977)
Atkins v. Kirkpatrick
823 S.W.2d 547 (Court of Appeals of Tennessee, 1991)
Computer Shoppe, Inc. v. State
780 S.W.2d 729 (Court of Appeals of Tennessee, 1989)
State ex rel. Leech v. Wright
622 S.W.2d 807 (Tennessee Supreme Court, 1981)