IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON JANUARY 1999 SESSION
CHRIS-HILL CONSTRUCTION ) Tennessee Claims Commission COMPANY, ) Western Division, Claim 204648 )
v. Claimant/Appellant, ) ) ) FILED Appeal No. 02A01-9803-BC- 00057 February 4, 1999 ) STATE OF TENNESSEE, ) Cecil Crowson, Jr. Appellate C ourt Clerk ) Defendant/Appellee. )
APPEAL FROM THE TENNESSEE CLAIMS COMMISSION WESTERN DIVISION AT MEMPHIS HONORABLE MARTHA BRASFIELD, COMMISSIONER
For the Appellant: James W. McDonnell, Jr. O. John Norris WYATT, TARRANT & COMBS 6075 Poplar Avenue, Suite 650 Memphis, TN 38119-4721
For the Appellee: John Knox Walkup Attorney General and Reporter
Mary G. Moody Senior Counsel
Laura T. Kidwell Assistant Attorney General 425 Fifth Avenue North Second Floor, Cordell Hull Bldg. Nashville, TN 37243-0488
AFFIRMED
WILLIAM H. INMAN, SENIOR JUDGE
CONCUR:
W. FRANK CRAWFORD, JUDGE DAVID R. FARMER, JUDGE OPINION
The Facts
This claim arises from Chris-Hill Construction Company’s (“claimant”)
participation in bidding on a Tennessee Department of Transportation (“TDOT”)
project for widening and improving the bridges and approaches over the Illinois
Central Railroad, Tarent Branch and Cane Creek on U.S. 51 in Shelby County
(“the project”). The plans and specifications for this project were prepared by
TDOT which furnished them to interested bidders, including Chris-Hill and
Dement Construction Company (“Dement”).
Bobby Garland of the TDOT was available to prospective bidders to answer
questions about contract requirements. Danny Stoppenhagen and J. B. Hill,
representatives of Chris-Hill, contacted Garland to enquire if TDOT would enforce
a note on the plans prohibiting the placement of a crane on the existing bridge in
order to drive pilings. After checking with the TDOT Structures Division, Garland
informed them that the note would be enforced. Chris-Hill thereupon added the
costs of constructing a berm upon which to locate a platform for the crane to its
bid.
On February 13, 1991, two days before the bids were to be opened, Dement
Vice-President Ty Capps contacted Garland and advised him that there were
conflicting provisions in the plans and specifications regarding the requirement of
seismic connections in the bearing pilings for the bridges. He requested that
TDOT issue an addendum to the contract clarifying the matter. Garland reviewed
the plans and specifications and talked with Danny Stoppenhagen about his
interpretation of them, and thereupon determined that there was a conflict in the
documents. On February 14, Garland told Capps that an addendum clarifying the
2 requirements for seismic connections on the pilings would not be issued because
it was too late to issue a clarification to all interested bidders. He told Capps to bid
the job based upon his own (Capps’) interpretation of the plans. On the same day,
Stoppenhagen called Garland asking if “anything else had developed regarding the
seismic piling.” Garland advised Stoppenhagen, as he had advised Capps, that he
should bid the job based upon his own (Stoppenhagen’s) interpretation of the
documents.
On February 15, 1991, the bids were submitted and opened. The two lowest
bidders were Dement at $1,463,378 and Chris-Hill at $1,525,529. The contract
was awarded to Dement. During the bid review process, Garland determined that
Dement would still be the lowest bidder after adding $10,200 (Dement’s estimated
price for the seismic connections in controversy) to its bid as submitted.
After the contract was awarded, Dement and the TDOT agreed that the
contract was ambiguous about whether the use of seismic connections in the
bearing pilings for the bridges was required. As provided for in the Standard
Specifications for Road and Bridge Construction, Dement and TDOT executed a
supplemental agreement paying Dement $150 per connection for the seismic
connections, for a total of $10,200. This amount would have been paid to Chris-
Hill had it been the successful bidder.
After construction began, Dement obtained permission from TDOT to place
a crane on the existing bridge in order to drive some of the pilings for the project,
which eliminated the need to construct a berm or base for that purpose.
The contract required the installation of a double row of sheet piling parallel
to the Illinois Central tracks in order to maintain the stability of the tracks during
the excavation for and driving of the concrete bridge pilings. Claimant complained
3 that Dement was not only using a crane on the existing bridge, but had installed
only one row of sheet piling, in violation of the contract.1 Dement was thereupon
instructed by TDOT to install the second row.
Chris-Hill filed this claim alleging that it sustained damages as a result of
the negligence of the TDOT, in allowing Dement to use the existing bridge as the
platform from which to drive the required pilings in violation of the contract.
Claimant alleged that if the “secret variation” had been disclosed, the expense
incurred for the construction of a berm would not have been required and
consequently it would have been the low bidder. This action by TDOT is alleged
to have been in violation of T.C.A. § 9-8-307(a)(1)(I) and (N) as hereafter stated.
Claimant alleged further variations previously discovered.
Because TDOT always prepared its own cost estimates on projects, claimant
requested production of TDOT’s estimate of the costs involved in driving the
pilings. This request was refused.
At the close of the claimant’s case the Commissioner granted the motion of
TDOT to dismiss, holding that there was no evidence that TDOT granted
DEMENT the variance prior to the bidding and thus no negligence.
Issues Presented for Review
1. Did the claimant present a prima facie case of negligence, or as enlarged by TDOT, what rights do the provisions of T.C.A. § § 54-5- 114 --118 convey upon those bidding on a state highway project in accordance with those statutes?
2. Does T.C.A. § 9-8-307(a)(1)(I) provide jurisdiction in the Tennessee Claims Commission for claims by unsuccessful bidders on Tennessee Department of Transportation construction projects, alleging that the State was negligent in allowing the successful bidder to deviate from the original plans and specifications?
1 Dement had discussed the matter with the railroad, who advised Dement that one row was adequate. But the TDOT thought otherwise and insisted on a double row as the contract specified.
4 3. Was the Commissioner correct in refusing to compel the State to Produce its construction estimate for this project? Standard of Review
The case was involuntarily dismissed pursuant to Rule 41.02(2), T.R.C.P.,
which requires a consideration of the standard prescribed in City of Columbia v.
C. F. W. Const. Co., 557 S.W.2d 734 (Tenn. 1977):
Free access — add to your briefcase to read the full text and ask questions with AI
IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON JANUARY 1999 SESSION
CHRIS-HILL CONSTRUCTION ) Tennessee Claims Commission COMPANY, ) Western Division, Claim 204648 )
v. Claimant/Appellant, ) ) ) FILED Appeal No. 02A01-9803-BC- 00057 February 4, 1999 ) STATE OF TENNESSEE, ) Cecil Crowson, Jr. Appellate C ourt Clerk ) Defendant/Appellee. )
APPEAL FROM THE TENNESSEE CLAIMS COMMISSION WESTERN DIVISION AT MEMPHIS HONORABLE MARTHA BRASFIELD, COMMISSIONER
For the Appellant: James W. McDonnell, Jr. O. John Norris WYATT, TARRANT & COMBS 6075 Poplar Avenue, Suite 650 Memphis, TN 38119-4721
For the Appellee: John Knox Walkup Attorney General and Reporter
Mary G. Moody Senior Counsel
Laura T. Kidwell Assistant Attorney General 425 Fifth Avenue North Second Floor, Cordell Hull Bldg. Nashville, TN 37243-0488
AFFIRMED
WILLIAM H. INMAN, SENIOR JUDGE
CONCUR:
W. FRANK CRAWFORD, JUDGE DAVID R. FARMER, JUDGE OPINION
The Facts
This claim arises from Chris-Hill Construction Company’s (“claimant”)
participation in bidding on a Tennessee Department of Transportation (“TDOT”)
project for widening and improving the bridges and approaches over the Illinois
Central Railroad, Tarent Branch and Cane Creek on U.S. 51 in Shelby County
(“the project”). The plans and specifications for this project were prepared by
TDOT which furnished them to interested bidders, including Chris-Hill and
Dement Construction Company (“Dement”).
Bobby Garland of the TDOT was available to prospective bidders to answer
questions about contract requirements. Danny Stoppenhagen and J. B. Hill,
representatives of Chris-Hill, contacted Garland to enquire if TDOT would enforce
a note on the plans prohibiting the placement of a crane on the existing bridge in
order to drive pilings. After checking with the TDOT Structures Division, Garland
informed them that the note would be enforced. Chris-Hill thereupon added the
costs of constructing a berm upon which to locate a platform for the crane to its
bid.
On February 13, 1991, two days before the bids were to be opened, Dement
Vice-President Ty Capps contacted Garland and advised him that there were
conflicting provisions in the plans and specifications regarding the requirement of
seismic connections in the bearing pilings for the bridges. He requested that
TDOT issue an addendum to the contract clarifying the matter. Garland reviewed
the plans and specifications and talked with Danny Stoppenhagen about his
interpretation of them, and thereupon determined that there was a conflict in the
documents. On February 14, Garland told Capps that an addendum clarifying the
2 requirements for seismic connections on the pilings would not be issued because
it was too late to issue a clarification to all interested bidders. He told Capps to bid
the job based upon his own (Capps’) interpretation of the plans. On the same day,
Stoppenhagen called Garland asking if “anything else had developed regarding the
seismic piling.” Garland advised Stoppenhagen, as he had advised Capps, that he
should bid the job based upon his own (Stoppenhagen’s) interpretation of the
documents.
On February 15, 1991, the bids were submitted and opened. The two lowest
bidders were Dement at $1,463,378 and Chris-Hill at $1,525,529. The contract
was awarded to Dement. During the bid review process, Garland determined that
Dement would still be the lowest bidder after adding $10,200 (Dement’s estimated
price for the seismic connections in controversy) to its bid as submitted.
After the contract was awarded, Dement and the TDOT agreed that the
contract was ambiguous about whether the use of seismic connections in the
bearing pilings for the bridges was required. As provided for in the Standard
Specifications for Road and Bridge Construction, Dement and TDOT executed a
supplemental agreement paying Dement $150 per connection for the seismic
connections, for a total of $10,200. This amount would have been paid to Chris-
Hill had it been the successful bidder.
After construction began, Dement obtained permission from TDOT to place
a crane on the existing bridge in order to drive some of the pilings for the project,
which eliminated the need to construct a berm or base for that purpose.
The contract required the installation of a double row of sheet piling parallel
to the Illinois Central tracks in order to maintain the stability of the tracks during
the excavation for and driving of the concrete bridge pilings. Claimant complained
3 that Dement was not only using a crane on the existing bridge, but had installed
only one row of sheet piling, in violation of the contract.1 Dement was thereupon
instructed by TDOT to install the second row.
Chris-Hill filed this claim alleging that it sustained damages as a result of
the negligence of the TDOT, in allowing Dement to use the existing bridge as the
platform from which to drive the required pilings in violation of the contract.
Claimant alleged that if the “secret variation” had been disclosed, the expense
incurred for the construction of a berm would not have been required and
consequently it would have been the low bidder. This action by TDOT is alleged
to have been in violation of T.C.A. § 9-8-307(a)(1)(I) and (N) as hereafter stated.
Claimant alleged further variations previously discovered.
Because TDOT always prepared its own cost estimates on projects, claimant
requested production of TDOT’s estimate of the costs involved in driving the
pilings. This request was refused.
At the close of the claimant’s case the Commissioner granted the motion of
TDOT to dismiss, holding that there was no evidence that TDOT granted
DEMENT the variance prior to the bidding and thus no negligence.
Issues Presented for Review
1. Did the claimant present a prima facie case of negligence, or as enlarged by TDOT, what rights do the provisions of T.C.A. § § 54-5- 114 --118 convey upon those bidding on a state highway project in accordance with those statutes?
2. Does T.C.A. § 9-8-307(a)(1)(I) provide jurisdiction in the Tennessee Claims Commission for claims by unsuccessful bidders on Tennessee Department of Transportation construction projects, alleging that the State was negligent in allowing the successful bidder to deviate from the original plans and specifications?
1 Dement had discussed the matter with the railroad, who advised Dement that one row was adequate. But the TDOT thought otherwise and insisted on a double row as the contract specified.
4 3. Was the Commissioner correct in refusing to compel the State to Produce its construction estimate for this project? Standard of Review
The case was involuntarily dismissed pursuant to Rule 41.02(2), T.R.C.P.,
which requires a consideration of the standard prescribed in City of Columbia v.
C. F. W. Const. Co., 557 S.W.2d 734 (Tenn. 1977):
But in the non-jury case, when a motion to dismiss is made at the close of plaintiff’s case under Rule 41.02(2), the trial judge must impartially weigh and evaluate the evidence in the same manner as though he were making findings of fact at the conclusion of all of the evidence for both parties, determine the facts of the case, apply the law to those facts, and, if the plaintiff’s case has not been made out by a preponderance of the evidence, a judgment may be rendered against the plaintiff on the merits, or, the trial judge, in his discretion, may decline to render judgment until the close of all the evidence. The action should be dismissed if on the facts found and the applicable law the plaintiff has shown no right to relief.
This court’s scope of review of the Commissioner’s decision is pursuant to
Rule 13(d), T. R. A. P. The findings of the trial court in granting a Rule 41.02(2)
motion are accompanied by a presumption of correctness and, unless the
preponderance of the evidence is otherwise, those findings must be affirmed.
Atkins v. Kirkpatrick, 823 S.W.2d 547, 552 (Tenn. App. 1991).
Discussion
Chris-Hill asserted its claim for damages under T.C.A. § 9-8-307, sections
(a)(1)(I) and (N), the latter of which provides jurisdiction in the Claims
Commission for claims arising from “negligent deprivation of statutory rights.”
The statutory rights Chris-Hill seeks to enforce are those arising under T.C.A. § §
54-5-113 -- 118, which provide that the Tennessee Department of Transportation,
when making contracts in its own behalf or when acting as agent, must advertise
for bids, require that a bond accompany the bids, open the bids in the presence of
5 the bidders and public, and award the contract to the best and most advantageous
bidder, reserving the right to reject all bids, a process referred to as “competitive
bidding,” State ex rel. Leech v. Wright, 622 S.W.2d 807, 814-815 (Tenn. 1981).
A consideration of the first issue requires this Court to determine what rights these
statutes confer upon participating bidders.
It is well settled that competitive bidding statutes are enacted for the
purposes of providing bidders with a fair opportunity to compete for public
contracts and promoting the public interest by guarding against favoritism and
fraud. Marta v. Metropolitan Government of Nashville, 842 S.W.2d 611, 616-617
(Tenn. App. 1992). A participating bidder has the right to have its bid considered
honestly and fairly, competing on the same footing as all other bidders. Computer
Shoppe, Inc. v. State, 780 S.W.2d 729, 737 (Tenn. App. 1989). This requires that
all bidders be placed upon the same plane of equality and that they each bid upon
the same terms and conditions involved in all the items and parts of the contract
and that the proposal specify as to all bids the same, or substantially similar
specifications. State ex rel. Leech v. Wright, 662 S.W.2d at 815.
The claimant had the right to prepare and submit its bid upon the same
terms, conditions, plans and specifications relied upon by all other bidders on this
project, and prior to bidding, Chris-Hill was entitled to have the same information
regarding the requirements of the contract that was given to Dement.
In the Section (N) averments, Chris-Hill alleges that it was denied its rights
under the competitive bidding statute because, after the contract was awarded,
TDOT allowed the successful bidder, Dement, to deviate from the plans and
specifications in the actual construction of the project. Three deviations were
specifically alleged by the claimant:
6 1. TDOT allowed Dement to place a crane on the existing bridge in order to drive sheet metal and concrete pilings.
2. TDOT entered a supplemental agreement with Dement providing for payment of $150 for each of sixty-eight seismic piling connections.
3. TDOT allowed Dement to use only one row of sheet metal pilings in a location where the plans called for two rows.
It was admitted by the TDOT that after the contract was let, Dement was
given a supplemental contract for sixty-eight seismic connections at $150 each, and
that during the construction Dement was allowed to place a crane on the existing
bridge. Dement complied with TDOT’s order to use a double row of sheet piling
after it was brought to the attention of TDOT that a single row was being used.
Chris-Hill, in its complaint, referred to these “secret deviations,” alleging
that TDOT told Dement, before bidding, that the deviations would ultimately be
allowed, and that if it had known before bidding that TDOT would ultimately
allow these deviations from the plans and specifications, its bid would have been
the lowest.
The State argues that a claim for deprivation of rights under the competitive
bidding statutes requires Chris-Hill to prove that TDOT assured Dement that it
would be allowed to make these deviations before it submitted its bid.2
The State argues that claimant presented no direct proof that TDOT provided
Dement with information prior to bidding that gave it any unfair advantage in the
bidding. Bobby Garland, the TDOT employee responsible for communicating with
prospective bidders about the plans and specifications, testified that he did not
2 The State is not liable for “. . . willful, malicious or criminal acts by State employees, or for acts of State employees done for personal gain.” T.C.A. § 9-8-307(a)(3)(d). The statutory scheme is clear that the liability of the State is bottomed on negligence, the failure to use ordinary care or to adhere to an appropriate standard of care. See, Haynes v. Hamilton County, 883 S.W.2d 606 (Tenn. 1994).
7 discuss the issues of placing a crane on the existing bridge or the number of rows
of sheet piling required with Dement prior to the submission of bids. He also
testified that, although he did discuss with Dement the issue of whether seismic
connections were required, he did not tell Dement before the bidding that it would
be allowed a supplemental agreement to pay for seismic connections.
The claimant relies on the fact that after the contract was awarded, Dement
was allowed to deviate from the original plans and specifications, and argues that
it is reasonable from that fact that Dement had been told prior to bidding that the
deviations would be allowed.
It is not controverted that in most TDOT highway construction projects the
contractor is allowed to deviate from the original plans and specifications in some
way, a practice known to Chris-Hill because it has been allowed such deviations
on its TDOT projects. We agree with the argument of the appellee that if the
inference proposed by the claimant established a prima facie case, the unsuccessful
bidder on most TDOT projects could make a claim that they had been deprived of
rights under the competitive bidding statutes. Such an inference is equatable to a
finding of corrupt state action, and cannot be properly considered as negligence in
order to make a 307(N) case.
Without the inference, it is not seriously controverted that there is no proof
in the record which would support a finding that Dement Construction Company
was given an unfair advantage in the bidding on this project or that, for any reason,
Chris-Hill’s bid was not “fairly considered.” The Commissioner’s dismissal of
Chris-Hill’s claims under T.C.A. § 9-8-307(a)(1)(N) is not contrary to the
preponderance of the evidence.
8 T.C.A. § 9-8-307(a)(1)(I) provides that the Claims Commission has
jurisdiction to hear claims arising from
Negligence in planning and programming for, inspection of, design of, preparation of plans for, approval of plans for, and construction of, public roads, streets, highways, or bridges and similar structures, designated by the Department of Transportation as being on the State system of highways or the State system of interstate highways.
The Claims Commissioner found that jurisdiction only existed under this
section for Chris-Hill’s claim so far as it pertained to negligence in the preparation
of the plans for the project to be bid. Chris-Hill claimed that TDOT had been
negligent in the preparation of the plans because there was an ambiguity in the
plans regarding the use of seismic connections on the concrete pilings. The
Commissioner dismissed that claim on the basis that, under this court’s holding in
Computer Shoppe, Inc. v. State, supra, the State has no duty to prospective bidders
to prepare error-free plans.
Chris-Hill also argues that Section 307(a)(1)(I) authorizes claims by
unsuccessful bidders against the State which allege negligence on the part of the
TDOT in allowing successful bidders to deviate from the original plans and
specifications. We cannot agree. The post-contract deviations were not the result
of negligence and Section 307(a)(1)(I) is not implicated.
Finally, claimant argues that the Commission erred in not requiring the
TDOT to produce its in-house estimate of the costs of the project. The General
Assembly prohibited the publication of information which revealed the amount of
available funding for any project by Chapter 1085 of the 1990 Public Acts.
The judgment is affirmed at the costs of the appellant.
_______________________________
9 William H. Inman, Senior Judge
_______________________________ W. Frank Crawford, Judge
_______________________________ David R. Farmer, Judge
10 IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON JANUARY 1999 SESSION
CHRIS-HILL CONSTRUCTION ) Tennessee Claims Commission COMPANY, ) Western Division, Claim 204648 ) Claimant/Appellant, ) ) v. ) Appeal No. 02A01-9803-BC-00057 ) STATE OF TENNESSEE, ) ) Defendant/Appellee. )
______________________________________________________________
JUDGMENT ______________________________________________________________
This cause came on to be regularly heard and considered by this Court, and
for the reasons stated in the Opinion of this Court filed this date, it is ORDERED
that:
1. The judgment of the trial court is affirmed.
2. Costs of this appeal are taxed against the appellant, Chris-Hill
Construction Company, for which execution may issue if necessary.
____________________________ INMAN, S.J. __________________________ CRAWFORD, J.
____________________________ FARMER, J.