Choate Construction Co. v. Auto-Owners Insurance

736 S.E.2d 443, 318 Ga. App. 682, 2012 Fulton County D. Rep. 3849, 2012 WL 5856526, 2012 Ga. App. LEXIS 977
CourtCourt of Appeals of Georgia
DecidedNovember 20, 2012
DocketA12A1045
StatusPublished
Cited by4 cases

This text of 736 S.E.2d 443 (Choate Construction Co. v. Auto-Owners Insurance) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Choate Construction Co. v. Auto-Owners Insurance, 736 S.E.2d 443, 318 Ga. App. 682, 2012 Fulton County D. Rep. 3849, 2012 WL 5856526, 2012 Ga. App. LEXIS 977 (Ga. Ct. App. 2012).

Opinion

Ellington, Chief Judge.

In this suit on payment and performance bonds, general contractor Choate Construction Company (“Choate”) appeals from the grant of summary judgment in favor of surety Auto-Owners Insurance Company (“AOIC”). Choate contends that the trial court erred in [683]*683finding that, because the bonds named a principal that was a different company than the subcontractor it had hired, it could not collect on the bonds. For the following reasons, we reverse.

“Summary judgment is proper when there is no genuine issue of material fact and the movant is entitled to judgment as a matter of law. We review the grant of summary judgment de novo, construing the evidence in favor of the nonmovant.” (Citations and punctuation omitted.) White v. Ga. Power Co., 265 Ga. App. 664, 664-665 (595 SE2d 353) (2004). So viewed, the record shows the following facts.

In November 2008, Choate entered into a contract with the Board of Regents of the University System of Georgia for the construction of fraternity and sorority housing at the University of Georgia. It hired Dedmon Electrical Services (“Dedmon”) as an electrical subcontractor on the project, which the subcontract referred to as “Greek Park.” Under the subcontract, Choate required Dedmon to furnish payment and performance bonds. Choate gave bond forms to Dedmon’s owner, Thad Dedmon, to be completed and returned to Choate before Dedmon began its work on the project. After contracting with Choate, Dedmon opened an account with, and purchased materials for the project from, Atlanta Electrical Distributors, Inc. (“AED”); Thad Dedmon personally guaranteed payment on the account.

In January 2009, Dedmon began work on the project, even though it had not yet provided the requisite payment and performance bonds to Choate. The next month, Choate received payment and performance bonds that had been issued by AOIC, as the surety, and that identified the principal as “D. E. S. Electrical Contractors” (“DES”); Jacqueline Payne had signed the bonds as the owner of DES. The bonds also identified Choate as the “Obligee,” stated that the obligee had a contract with the “Bd. of Regents [,] Univ. System of Georgia for the construction of Greek Park,” described the services to be provided under the principal’s subcontract with the obligee as “Electrical Installations,” gave the date and the value of the subcontract, and referenced and incorporated the subcontract. Although neither Dedmon nor Thad Dedmon was named on the bonds, a Choate office employee wrote “Dedmon Electric” at the top of the performance bond. Choate did not confirm that DES and Dedmon were, in fact, the same company, nor did it contact Dedmon, Thad Dedmon, DES, Payne, or AOIC to inquire about the discrepancy between the name of the principal on the bonds, DES, and the name of the company with which Choate had the subcontract, Dedmon. Instead, based upon the assumption that the bonds covered Dedmon’s services under the subcontract, Choate allowed Dedmon to continue working on the project. Dedmon eventually defaulted on the subcontract with Choate and failed to pay its account with AED.

[684]*684Choate filed a claim with AOIC on the bonds, but AOIC refused to pay, asserting that neither DES, the named principal on the bonds, nor Payne, who signed the bonds as the owner of DES, were parties to the electrical subcontract between Dedmon and Choate, nor had they otherwise contracted with either Choate or AED. According to AOIC, Payne applied for the bonds as the “Owner” of DES under the surety’s “Quick Bond Program.” Under that program, AOIC offers bonds for qualified individuals or contractors with projects that take less than a year to complete and that have a total value of work of less than $250,000. Because of the limitations on the time and value of the prospective project, AOIC does not require a bond applicant to provide the underlying contract as part of his or her application, because the contract is “not relevant to the applicant’s bondability[.]” The record shows, however, that on Payne’s application for the bonds, she stated that the underlying contract was with “Choate Construction Company,” that the contract was dated “01/17/2009,” and that the contract price was “$231,960.64.” Further, under “Job Description,” the application stated “UN of GA/Greek Park/Athens, GA[J Installation of electrical components per drawings.” This information essentially matches the information on the subcontract between Choate and Dedmon.

In November 2009, AED filed suit against Choate, Dedmon, Thad Dedmon, DES, Payne, AOIC, and others, claiming damages for failure to pay on an open account, breach of contract, liability on the surety bonds, quantum meruit and unjust enrichment, and attorney fees. Choate asserted a cross-claim against AOIC and “D. E. S. Electrical Contractors, Inc. a/k/a D. E. S. Electrical Contractors a/k/a Dedmon Electric Services a/k/a Dedmon Electrical Services,” asserting breach of contract and claims for contractual indemnity and under the payment and performance bonds.

In March 2010, the trial court entered a default judgment against Thad Dedmon on AED’s claims. AED then dismissed its claims against Payne, settled its claims against Choate, and assigned to Choate its remaining claims against Dedmon, DES, and AOIC. Choate filed a motion to realign the parties by substituting it as the named plaintiff and AOIC, Thad Dedmon, and “Dedmon Electrical Services a/k/a D. E. S. Electrical Contractors” as the defendants. AOIC objected to the motion, asserting that Dedmon and DES were separate companies with no legal relationship. Choate and AOIC also filed cross-motions for summary judgment.

Following a motion hearing, the trial court granted summary judgment to AOIC, finding, inter alia, that the bonds were unambiguous in their identification of the principal as DES, the surety as AOIC, and the obligee as Choate. Further, it found that Choate had [685]*685failed to present any evidence that Dedmon and DES were the same entity or that Thad Dedmon and Payne were ever involved in the same company. The court concluded that AOIC was not liable on bonds that identified DES as the principal and that, as a result, AOIC was entitled to summary judgment.

1. On appeal, Choate contends that the trial court erred in finding that AOIC was not liable on the bonds as a matter of law, arguing that the evidence, when viewed in its favor, was sufficient to create a jury issue as to whether Dedmon and DES were the same business entity for the purpose of the bonds on the subcontract. Further, Choate argues that any ambiguities in the identity of the bond principal should be construed most strongly against the surety, AOIC.

“[A] contract involving a compensable surety is construed most strongly against the surety and in favor of the indemnity which the obligee has reasonable grounds to expect.” (Citation, punctuation and emphasis omitted.) Growth Properties of Florida v. Wallace, 168 Ga.App. 893, 896 (1) (310 SE2d 715) (1983).

[W]hen the fact of suretyship does not exist on the face of the contract, the parties involved are permitted to either prove or disprove the existence of a suretyship relationship. The question is an evidentiary one and its proper resolution requires that facts be submitted to the fact finder to determine what was the intent of the parties. The cardinal rule of contract construction is to ascertain the intention of the parties. The question of the intention of the parties in this case is properly for the jury.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Choate Construction Company v. Auto-Owners Insurance Company
779 S.E.2d 465 (Court of Appeals of Georgia, 2015)
Haire v. Smith, Currie & Hancock LLP
925 F. Supp. 2d 126 (District of Columbia, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
736 S.E.2d 443, 318 Ga. App. 682, 2012 Fulton County D. Rep. 3849, 2012 WL 5856526, 2012 Ga. App. LEXIS 977, Counsel Stack Legal Research, https://law.counselstack.com/opinion/choate-construction-co-v-auto-owners-insurance-gactapp-2012.