Childers Redimix and Construction Supply Inc. v. Concrete Plants, Inc.

CourtDistrict Court, N.D. Ohio
DecidedMarch 14, 2023
Docket5:21-cv-02150
StatusUnknown

This text of Childers Redimix and Construction Supply Inc. v. Concrete Plants, Inc. (Childers Redimix and Construction Supply Inc. v. Concrete Plants, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Childers Redimix and Construction Supply Inc. v. Concrete Plants, Inc., (N.D. Ohio 2023).

Opinion

UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF OHIO EASTERN DIVISION

CHILDERS REDIMIX AND ) CASE NO. 5:21-cv-2150 CONSTRUCTION SUPPLY INC., ) ) ) PLAINTIFF, ) JUDGE SARA LIOI ) vs. ) ) MEMORANDUM OPINION CONCRETE PLANTS, INC., ) AND ORDER ) ) DEFENDANT. )

Before the Court is the motion filed by plaintiff Childers Redimix and Construction Supply Inc. (“Childers Redimix” or “plaintiff”) seeking summary judgment on defendant’s counterclaim. (Doc. No. 37.) Defendant Concrete Plants, Inc. (“CPI” or “defendant”) filed a brief in opposition (Doc. No. 38) and Childers Redimix filed a reply (Doc. No. 41).1 For the reasons discussed herein, the motion is denied. I. PROCEDURAL BACKGROUND On October 15, 2021, Childers Redimix initiated this lawsuit in the Stark County Court of Common Pleas. The complaint asserts three causes of action: (1) unjust enrichment; (2) breach of contract; and (3) declaratory judgment. (Doc. No. 1-1, Complaint.) Although not expressly stated in the complaint, the first and second causes of action are construed by the Court as pleaded in the

1 Both parties filed depositions in support of their respective briefs. For convenience, the Court’s references herein to any deposition testimony are to the transcripts filed by CPI. (See Doc. No. 39-1, Deposition of Jesse P. Childers, Jr.; Doc. No. 40-1, Deposition of Charles Denton (Denny) Holmes, III.) Neither party included the exhibits to the depositions, but most of the relevant exhibits are attached to either the pleadings and/or the briefs on the instant motion. For purposes of this ruling, the Court relies on any such exhibits only to the extent they are undisputed by the parties. alternative since, under Ohio law,2 “one cannot recover under a theory of unjust enrichment when there is a contract governing the dispute.” Mktg. Assoc., Inc. v. Fellowes, Inc., No. 1:05-cv-1518, 2006 WL 721619, at *1 (N.D. Ohio Mar. 21, 2006) (citations omitted).3 On November 12, 2021, CPI properly removed the action to this Court on the basis of diversity jurisdiction. (Doc. No. 1, Notice of Removal.) Shortly thereafter, on November 19, 2021, CPI filed its answer to the complaint, along with a counterclaim for declaratory judgment. (Doc. No. 5, Answer and Counterclaim.) On November 30, 2021, Childers Redimix filed its reply to CPI’s counterclaim. (Doc. No. 7, Reply to Counterclaim.) Childers Redimix timely filed the instant motion for summary judgment on CPI’s

counterclaim; it did not also move for summary judgment on any of its own claims. CPI did not seek summary judgment on any of the claims in the lawsuit or on its counterclaim. II. FACTUAL BACKGROUND4 The following are undisputed material facts. In 2017, Childers Redimix’s principal and sole shareholder Jesse Childers (“Childers”) reached out to Charles Denton (Denny) Holmes, III (“Holmes”) at CPI seeking to purchase a portable concrete plant from CPI so as to expand Childers Redimix’s business into “supplying cement and supplying building materials.” (Doc. No. 39-1, at

2 Since this case is brought under the Court’s diversity jurisdiction, the substantive law of the forum state is applied. Perry v. Allstate Indem. Co., 953 F.3d 417, 421 (6th Cir. 2020) (citation omitted). 3 That said, a determination that there was no contract between the parties (which would eliminate plaintiff’s breach of contract claim) would not automatically resolve the other claims. 4 All page number references herein are to the consecutive page numbers applied to each individual document by the electronic filing system, a citation practice recently adopted by this Court despite a different directive in the Initial Standing Order for this case. 2 9; 12; 23.)5 In particular, Childers explained to Holmes that Childers Redimix had an opportunity to be the exclusive supplier of cement with respect to the Pro Football Hall of Fame Village being constructed in Canton, Ohio—a $2 billion project. In fact, Childers claimed to have a letter of intent from the lead developer of that project promising to “buy concrete exclusively from [Childers Redimix] for the duration of the [Village] project.” (Id. at 22–23; 26.) According to Childers, Holmes understood that Childers Redimix was “a strong candidate for the concrete supplier on the [Village] project.” (Id. at 29.) Holmes, in fact, believed that Childers Redimix would need “two plants instead of one . . . [in order] to meet [the] contract requirements[.]” (Id. at 29–30.6) After the initial discussions, several modified proposals were sent to Childers in July and

August of 2017. (See Doc. No. 1-1 ¶¶ 7, 9; Doc. No. 5 ¶¶ 7, 9.) There is no disagreement that, on August 22, 2017, CPI emailed Childers a final proposal dated July 28, 2017.7 (Doc. No. 1-1, Ex. 3 at 25; Doc. No. 5-1, Ex. 1.) There were two lines at the bottom of the proposal’s final page— one captioned “Accepted” and the other captioned “Approved.” No specific person is identified to sign the “Accepted” line, but Holmes is listed as the signatory for the “Approved” line. Immediately above these two signature lines, the proposal states:

5 Childers was familiar with Holmes because, in 2015, Childers and his father had considered buying a concrete plant from CPI (to be located in Akron, Ohio) and dealt with Holmes at that time; that project never materialized. (Doc. No. 39-1, at 20–22.) 6 Holmes testified that CPI’s proposal only encompassed one plant by request of Childers Redimix. (Doc. No. 40-1, at 118–19 (“We only quoted one plant; because at the time, [Childers] stated, ‘Let’s go with one plant, see how we do. And then we’ll add the second plant.’”).) 7 The fact that there were several modified proposals is undisputed, although there is a dispute as to the authenticity and/or accuracy of the exhibits attached to the complaint purportedly exemplifying several of the proposals. From the context of the various documents in the record, along with relevant deposition testimony of Holmes and Childers, the Court can ascertain that Doc. No. 1-1, Ex. 3 at 25 is an undisputed copy of the cover email and Doc. No. 5-1, Ex. 1 is an undisputed copy (signed by Childers) of the July 28, 2017 proposal. These are the documents cited herein. 3 Total Price F.O.B. Canton, Ohio $ 895,000.00 Less Deposit ($ 125,000.00) Total $ 770,000.00

Terms: 25% Down Payment 65% Due upon delivery of equipment Balance due after installation

(Doc. No. 5-1, at 7.) It is undisputed that CPI’s General Conditions of Sale were attached to this document8 and included the following relevant paragraphs: Acceptance and Price: Quotations are held open for (30) thirty days from the date on this proposal unless otherwise specified. All sales, use, excise of [sic] other similar taxes are for the account of the purchaser. All orders are subject to acceptance by the factories we [CPI] represent and subject to credit approval.

Cancellation: Wrongful cancellation of this order will result in the forfeiture of any down payment and the possible assessment of damages incurred by Concrete Plants Inc. or the Manufacturers we present.

(Doc. No. 5-2, Ex. 2.) It is undisputed (and reflected on Doc. No. 5-1, at 7) that Childers signed the “Accepted” line and returned the proposal to CPI. The date is uncertain on this record, but it was some time after August 22, 2017.9 (See Doc. No. 39-1, at 59 (“Probably in August, I think is when I [Childers] signed.”).) It is undisputed that Holmes never signed the “Approved” line and/or returned a signed copy to Childers Redimix; he testified that he did not believe it was necessary since it was his proposal and his approval could be assumed. (Doc. No. 40-1, at 82–83.) When Holmes was pressed

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Childers Redimix and Construction Supply Inc. v. Concrete Plants, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/childers-redimix-and-construction-supply-inc-v-concrete-plants-inc-ohnd-2023.