Chicago Sash, Door & Blind Manufacturing Co. v. Haven

63 N.E. 158, 195 Ill. 474, 1902 Ill. LEXIS 3205
CourtIllinois Supreme Court
DecidedFebruary 21, 1902
StatusPublished
Cited by2 cases

This text of 63 N.E. 158 (Chicago Sash, Door & Blind Manufacturing Co. v. Haven) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chicago Sash, Door & Blind Manufacturing Co. v. Haven, 63 N.E. 158, 195 Ill. 474, 1902 Ill. LEXIS 3205 (Ill. 1902).

Opinion

Mr. Justice Cartwright

delivered the opinion of the court:

This is an action of debt, brought by appellant against appellee, in the superior court of Cook county, on a bond executed by Frederick B. Stowell and Louis D. Beman, partners under the firm name of F. B. Stowell & Co., and by the defendant, in the sum of $4950, payable to the plaintiff, the condition whereof is as follows: “The condition of this obligation is such, that if, whereas, the said Chicago Sash, Door and Blind Manufacturing Company, as sub-contractors, by a contract with said F. B. Stowell & Co., contractors, dated December 4, 1896, agreed to furnish all materials required to complete mill work for United States government building at Meridian, Miss., consisting of all wood work except rough lumber, flooring and P. O. boxes, according to specifications of building and satisfactory to supervising architect of building'; material to be delivered at Meridian, Miss., and F. B. Stowell & Co. allowed §15 for taking materials from cars to building; said manufacturing company to furnish said materials as fast as building ready to receive it, but to have notice a reasonable time ahead, and to ship materials from Chicago in time to arrive at Meridian, Miss., as required at building, and not to be responsible for failure of transportation company to deliver in time if shipment made in time; all for the sum of four thousand nine hundred and fifty (4950) dollars at Chicago, Illinois, as follows: eighty-five per cent of said sum in installments as work on said building progresses, and remaining fifteen per cent of said amount to be paid at completion and acceptance of building: Now, if said F. B. Stowell & Co. shall well and truly perform its said contract with and make said payments to said Chicago Sash, Door and Blind Manufacturing Company as provided hereinbefore, then this obligation to be void, otherwise to remain in full force and virtue.” The declaration set out the bond, with assignments of breaches of the condition, to the effect that the plaintiff furnished to F. B. Stowell & Co. all materials required to complete mill work for United States government building at Meridian, Miss., as provided in said condition, and that the building had been completed and accepted, but that said F. B. Stowell & Co. had not paid the plaintiff the said installments or the amount to be paid at completion and acceptance of the building. Issues were made up and submitted to a jury upon pleas of the defendant, among which was a plea of want of consideration for the execution of the bond by her. The court admitted evidence on the part of the defendant under that plea and in rebuttal on the part of the plaintiff.

The contract between plaintiff and F. B. Stowell & Co. was dated December 4, 1896, and the bond was executed ' December 14, 1896. Defendant, in attempting to establish her plea, proved that plaintiff refused to go on and furnish the material without the bond, and that its manager said he would rather throw up the work and lose what had already been gotten out than go on with the work without the bond. The evidence on the part of the plaintiff tended to show that it refused to enter into the contract except upon condition that the bond should be given, and that the giving of the bond was a part of the original agreement. The defendant was not in the city of Chicago when the contract was made*, but when she arrived the bond was executed. There was no controversy about the fact that the plaintiff, after signing the contract, refused to go on with the work without the bond, and that, when it was given, plaintiff proceeded to carry out its contract and furnished the material.

The issues were found by the jury for the plaintiff, and the amount of the debt was found to be §4950, and plaintiff’s damages were assessed at §4468. Judgment was entered for the debt, to be discharged on payment of the damages, with interest and costs. The defendant appealed to the Appellate Court for the First District, and that court reversed the judgment without remanding the cause, and entered in its judgement the following finding of fact: “The court finds that there was no consideration for the execution by the defendant, Jane S. Haven, of the bond in suit.” The Appellate Court made no finding of fact as to any other issue in the case, and therefore found the other controverted facts in issue as they were found by the trial court.

The finding of fact by the Appellate Court that there was no consideration for the execution by the defendant, Jane S. Haven, of the bond in suit, is final and conclusive in this court. We can only examine the case upon questions of law, and the question arising upon the finding here is, whether it authorized and justified the judgment rendered by the Appellate Court which reversed the judgment obtained by the plaintiff in the superior court. The question is whether, conceding the fact to be as found by the Appellate Court, the judgment in that court was such as the law required. (Hawk v. Chicago, Burlington and Northern Railroad, Co. 147 Ill. 399.) If the plea that there was no consideration for the execution of the bond by the defendant was a good plea and the fact found by the Appellate Court was a good defense to the action, the judgment reversing the judgment of the superior court was right, and, as there could never be any recovery, it was proper to not remand the cause. If, on the other hand, the plea constituted no defense and the fact was not a bar to the action, the judgment of the Appellate Court was wrong.

A want of consideration could not, by the common law, be pleaded in bar of an action on the bond. The rule was, that a seal imported a consideration for the execution of the bond, and the presumption in favor of the consideration was held conclusive. (3 Ency. of Pl. & Pr. 665.) The well established rule was that a bond was valid without reference to consideration, because the seal implied or imported a consideration, and a declaration on a sealed bond need not aver any other. (Evans v. Edwards, 26 Ill. 279.) The action of debt is very broad in its scope, and it can be maintained on simple contracts, notes and a great variety of legal liabilities, where the amount to be recovered is certain or can be readily rendered certain by computation. If the action is upon any form of simple contract the defendant is permitted to put in issue the existence of the debt and put the plaintiff on proof of all the allegations of his declaration by the plea of nil débet, but if the action is on a bond, a plea in denial of the debt is of a nature which is not permissible. (Caldwell v. Richmond, 64 Ill. 30; Mix v. People, 92 id. 549.) In this case the bond is the foundation of the action, and not mere inducement to the action. (King v. Ramsay, 13 Ill. 619.) If the averment in the declaration that the defendant signed and sealed the bond is true, a plea disputing the debt is no defense. (Davis v. Burton, 3 Scam. 41.) The plea did not deny that the materials were furnished by the plaintiff and not paid for, or that the damages had accrued to the plaintiff, and unless the established rule of law has been modified by some statute, the plea of a want of consideration for the execution of the bond and assuming the oblig-ation is no defense to the action. 4 Am. & Eng. Ency. of Law, (2d ed.) 664.

It does not seem to be denied that the plea of want of consideration was not admissible at common law, but it is contended that it constitutes a good defense under the provisions of chapter 98 of the Revised Statutes, entitled “Negotiable Instruments.” (Rev.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Globe Indemnity Co. v. Kesner
203 Ill. App. 405 (Appellate Court of Illinois, 1917)
Killean v. Beaupre
187 Ill. App. 407 (Appellate Court of Illinois, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
63 N.E. 158, 195 Ill. 474, 1902 Ill. LEXIS 3205, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chicago-sash-door-blind-manufacturing-co-v-haven-ill-1902.