Chicago & Illinois Midland Railway Co. v. Marsh

577 F. Supp. 798
CourtDistrict Court, C.D. Illinois
DecidedJanuary 9, 1984
Docket81-1028
StatusPublished
Cited by5 cases

This text of 577 F. Supp. 798 (Chicago & Illinois Midland Railway Co. v. Marsh) is published on Counsel Stack Legal Research, covering District Court, C.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chicago & Illinois Midland Railway Co. v. Marsh, 577 F. Supp. 798 (C.D. Ill. 1984).

Opinion

ORDER

MIHM, District Judge.

In 1973, a massive flood partially destroyed sections of the levees and inundated much adjacent farm land in the vicinity of the Mackinaw River. A group of individual farmers who owned the land adjacent to the river approached the United States Army Corps of Engineers to obtain relief following the 1973 flood. Feasibility studies by the Corps developed several possible alternatives, including channelization of the river. The Corps states, however, that it decided to limit its response to a contract for restoration of the destroyed levees, a contention which the Plaintiffs dispute. William Hellemann was the successful bidder on the Corps project. In the meantime, Hellemann was also in contact with individual farmers and with officials of Tazewell County, seeking to form separate contracts for channelization of the river. Shortly after the Corps contract was approved, Hellemann entered into contracts with the group of individual farmers and with Tazewell County for channelization on this section of the river. The Tazewell contract was limited to channelizing one segment in the vicinity of a highway bridge which was vulnerable to flooding.

On or about March 7, 1979, Bridge No. 171, owned by Chicago and Illinois Midland Railway Company (“Midland”) was washed out and on June 3, 1980, Bridge No. 168 was washed out. Plaintiff Midland Railway Company brought a four count complaint under the Rivers and Harbors Act (“Act”), alleging violations of 33 U.S.C. § 401, § 403, § 407, and § 565. Midland alleges that the damming and channelization of the Mackinaw River caused the river waters to flow with increased force and velocity. Midland claims that it was forced to spend substantial sums of money to repair the damage to the two bridges and that additional amounts of money were lost because train traffic had to be halted and diverted over other railroad lines. The complaint named Corps officials, individual farmers, and William Hellemann and Roecker Bros., both contractors, as Defendants. In addition to its claim for money damages to the two damaged bridges, which Midland alleges were caused by the actions of the Defendants in 1973 to 1975, the Plaintiff seeks injunctive relief to restore the levee elevations to original configurations with reference to the 1973 to 1975 work of Hellemann on property owned by Defendant Horn, and the 1981 Corps related work on the property south and east of Bridge No. 171.

After the initial complaint was filed, there began a real “buck passing” contest. First, the Corps officials cross-claimed against the individual landowners (except for B. Knachstedt), Hellemann, and Roecker Bros, under Federal Rule of Civil Procedure 13(g). The Corps officials claim that Hellemann and Roecker Bros, agreed to obtain all the necessary permits required for the work on the river and also agreed to indemnify the Corps officials from liability arising out of their own negligence. The Corps officials also claim that the individual landowners agreed to hold the Corps harmless from all liability. Second, Roecker Bros, filed a cross claim for indemnification from the Corps officials and the individual landowners as joint tortfeasors. Third, remnants of the group of individual landowners filed a third party complaint against three other Tazewell County landowners who allegedly participated in the damming and channelization of the river. These landowners are Goldsmith, Look, and Clayton. Finally, Mabel Oberle, a landowner Defendant named in the original complaint, brought a third party complaint against eight other Tazewell County landowners who allegedly participated in the damming and channelization. On July 29, 1982, this Court entered an order dismissing Roecker Bros, from this case on the grounds that Roecker Bros, signed a repair contract merely as an accommodation party and not as a joint venturer. Summary judgment was also later granted on cross *801 claims naming Roecker Bros, as a cross defendant.

Defendants John O. Marsh, Jr., Secretary of the Department of the Army of the United States, the United States Corps of Engineers, Lt. General William C. Gribble, General Robert Moore, Colonel James M. Miller, and Angelo Zerbonia, hereinafter referred to as “federal defendants”, have moved for an order granting them summary judgment. Defendant William Hellemann has also moved for summary judgment on the complaint and on the first cross-claim filed by the federal defendants against him.

The federal defendants assert that there are three grounds upon which summary judgment should be granted in their favor. First, the federal defendants claim that the District Court lacks subject matter jurisdiction in that the Plaintiff could only be pursuing its claim under the Federal Tort Claims Act, 28 U.S.C. § 1346(b), and the Corps action in this ease in repairing the levees comes within the discretionary function exception of 28 U.S.C. § 2680(a). Second, the federal defendants argue that the Rivers and Harbors Act does not provide for a private right of action, citing California v. Sierra Club, 451 U.S. 287, 101 S.Ct. 1775, 68 L.Ed.2d 101 (1981). Finally, the federal defendants allege that the United States is exempt from liability for all flood damages under 33 U.S.C. § 702c which provides that “no liability of any kind shall attach to or rest upon the United States for any damage from or by flood or flood waters at any place”.

Defendant Hellemann, in his motion for summary judgment, adopts and incorporates the portion of the memorandum filed by the federal defendants in support of their motion for summary judgment upon the grounds that the Rivers and Harbors Act does not authorize a private right of action. Second, Defendant Hellemann sought summary judgment based on the argument that he, as an independent contractor, owed no duty to third persons for damages resulting from the performance by an independent contractor in a workmanlike manner of plans, specifications, and instructions which the contractor has contracted to follow. At a hearing before this Court on October 19, 1983, this Court denied Hellemann’s motion for summary judgment based on this independent contractor argument holding that genuine disputes as to material facts existed.

RIVERS AND HARBORS ACT

In California v. Sierra Club, 451 U.S. 287, 101 S.Ct. 1775, 68 L.Ed.2d 101 (1981), the United States Supreme Court held that both the language of the Rivers and Harbors Act and its legislative history give no evidence that Congress intended to create a private cause of action under the Act. In that case, private parties sought injunctive relief to prohibit the construction and operation of water diversion facilities under the authority of 33 U.S.C. § 403. The Court held that the plaintiffs had no cause of action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Keyes v. Lynch
214 F. Supp. 3d 267 (M.D. Pennsylvania, 2016)
Berwind Corp. v. Apfel
94 F. Supp. 2d 597 (E.D. Pennsylvania, 2000)
Hagemeier v. Block
806 F.2d 197 (Eighth Circuit, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
577 F. Supp. 798, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chicago-illinois-midland-railway-co-v-marsh-ilcd-1984.