Chicago Great Western Railroad v. American McKenna Process Co.

200 Ill. App. 166, 1916 Ill. App. LEXIS 45
CourtAppellate Court of Illinois
DecidedFebruary 8, 1916
DocketGen. No. 6,161
StatusPublished
Cited by7 cases

This text of 200 Ill. App. 166 (Chicago Great Western Railroad v. American McKenna Process Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chicago Great Western Railroad v. American McKenna Process Co., 200 Ill. App. 166, 1916 Ill. App. LEXIS 45 (Ill. Ct. App. 1916).

Opinion

Mr. Justice Carnes

delivered the opinion of the court.

The appellant, Chicago Great Western Railroad Company, brought this action of replevin for about 122 tons on its rails in the possession of the appellee, American McKenna Process Company, which held them on claims of liens for labor. A jury trial resulted in a judgment in the alternative, as provided in section 22 of our Replevin Act (J. & A. 9207), that the plaintiff pay the amount claimed or make return of the property, from which judgment this appeal is prosecuted.

There is practically no controversy about the evidentiary facts. There was a written contract of July 13, 1911, that appellee should re-roll at its Joliet plant 5,000 tons of appellant’s rails, approximately 3,000 tons to be delivered immediately and work begun at once, the balance to be delivered not later than June 1,1912. The price was fixed at $5 per ton if appellant delivered the full amount of 5,000 tons, or $6 per ton if a less amount was delivered within the time named, payment to be made within thirty days from the date of shipment of finished rails by appellee. It is a fair construction of the contract that appellant should receive the rails from time to time as they were finished in the ordinary course of business. Appellant commenced to forward rails in August, and before December 11,1911, had shipped about 2,700 tons, which were received by appellee, sorted out into various grades prepared for re-rolling, and piled in its yard. For various reasons appellant did not wish the work done at the time contemplated by the contract, and on December 23,1911, a supplemental contract was, at the instance of appellant, executed providing that these rails in the yard of appellee might remain there the property of appellant until they should be re-rolled and reshipped. Appellant forwarded no more rails, and from time to time answered appellee’s urgent insistence that it be permitted to go on with the work with the request that it be deferred because it, appellant, was not in condition to receive and use the rails. Finally on July 29, 1912, appellee commenced re-rolling the rails and continued until about August 5,1912, finishing in that time about. 1,245 tons, which were inspected and passed by an agent of appellant, and eleven cars loaded for shipment, when appellant notified appellee that it would not then receive the rails and they were consequently unloaded and again stored in appellee’s yard. No more rails were re-rolled. What remained of the 2,700 tons was shipped out on appellant’s order and fifty cents a ton charged and paid for handling them. Appellant sold the finished rails to the Pere Marquette Railroad Company, and this sale made necessary another inspection by parties representing that company, which required much manual labor in handling the rails, and that labor was furnished by appellee at the request of appellant. Under the second inspection the rails were divided into different grades and some changes made by way of shortening some of the rails, and taking twists out of others. In November, 1912, while the finished rails were still in the yard, appellee requested payment at $6 a ton on an estimated amount of the finished rails, which appellant paid, and at the same time appellee shipped to the order of appellant all the finished rails except about 122 tons, which still remained in its yard. September 6,1913, appellee sent appellant a bill based on the actual weight of the finished rails, showing a balance due for re-rolling of $526.02, about which there is no controversy, and also included in the bill a charge of fifty ■ cents a ton ($666.33) for extra handling required bv said second inspection. Appellant objected to the charge for extra handling, and paid no part of the bill, but after demand and refusal to deliver, took the rails on the writ of replevin issued in this case. A declaration was filed in the usual form, and appellee’s defense rests on two special pleas in each claiming a lien, one setting up the charge of $526.02 for re-rolling, and the other a charge of $1 a ton ($1,332.67) for extra handling.

The controlling question is whether appellee was entitled to hold the rails until its charge for labor was paid. It is claimed that because of the provision in the original contract for thirty days ’ credit after shipment by appellee, no right of lien could exist, and many authorities are cited to the effect that a laborer waives his right of lien by giving time beyond the date of delivery for payment. This is no doubt the law. Stevens v. Faucet, 24 Ill. 483; 25 Cyc. 674. It is also obvious that if appellee was under an obligation to deliver these rails on demand and wait thirty days for payment, it could not ground a defense in a replevin suit on the fact that payment before delivery was refused. It is claimed by appellee that the stipulation in the original contract of July 13, 1911, for thirty days’ credit was waived by appellant and was not binding on appellee at the time of its refusal to deliver the rails. Appellee bases this contention on the consideration that the contract containing this stipulation provided for immediate delivery after July 13, 1911, of 3,000 tons of rails by appellant, which were to be immediately re-rolled and reshipped to appellant in the ordinary course of business, and paid for by appellant in thirty days after shipment; that appellant did not perform this essential part of its contract, but shipped 2,700 tons and asked for and obtained a written modification of the contract as to the time within which the work should be done, under which modification appellee was to do the work within a reasonable time, but that appellee from time to time deferred the work at the urgent insistence of appellant, leaving the rails stored in its yard and subjecting itself to much trouble and inconvenience in so doing, which was repeatedly stated to appellant and well understood by it; that finally long after these rails would have been re-rolled and reshipped and paid for if the original contract had been complied with, appellee, while the rails were still in its yard, requested payment based on an estimate which covered nearly all of its charge for re-rolling. By this request for payment without shipment, appellee treated the stipulation for credit as no longer in force, and appellant, by complying with this request, acquiesced in that construction. We think this position of appellee well taken. A party in order to obtain the benefit of a provision of a contract advantageous to him must conform to other provisions not in his favor. Babcock v. Farwell, 245 Ill. 39; Graham v. Holloway, 44 Ill. 385; Harrison v. Polar Star Lodge, 116 Ill. 279; Hale v. Bryant, 109 Ill. 34; Lasher v. Loeffler, 190 Ill. 150; Mount v. Williams, 11 Wend. (N. Y.) 77. A contract may be modified as to one of its provisions without affecting the liability of the parties under its other terms and conditions, unless such conditions are directly related to the modified condition, in which event the related conditions must be held also modified. (35 Cyc. 127.) Where a contract is varied by subsequent agreement so as to require more time and greater expenditure on the part of a plaintiff to complete the performance of it, he is not obliged to sue on the original contract but may recover on the common counts. 9 Cyc. 690; Huehl v. Monarch Refrigerating Co., 157 Ill. App. 145; Anglo-Wyoming Oil Fields v. Miller, 117 Ill. App. 552. But where the work is done under a special contract, as in this case, the price must be governed by the stipulations of that contract, even when the plaintiff is justified in abandoning the contract and bringing his action for the quantum meruit. W. H.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Midway Airlines v. Monarch Air Service
383 F.3d 663 (Seventh Circuit, 2004)
Nagle v. General Merchandising Corp.
374 N.E.2d 1137 (Appellate Court of Illinois, 1978)
Nat'l Bank of Joliet v. Bergeron Cadillac, Inc.
361 N.E.2d 1116 (Illinois Supreme Court, 1977)
National Bank v. Bergeron Cadillac, Inc.
347 N.E.2d 874 (Appellate Court of Illinois, 1976)
Swain v. Mehl
200 Ill. App. 496 (Appellate Court of Illinois, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
200 Ill. App. 166, 1916 Ill. App. LEXIS 45, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chicago-great-western-railroad-v-american-mckenna-process-co-illappct-1916.