Chevron U.S.A., Inc. v. Watt

564 F. Supp. 1256, 78 Oil & Gas Rep. 26, 1983 U.S. Dist. LEXIS 16875
CourtDistrict Court, E.D. Louisiana
DecidedMay 18, 1983
DocketCiv. A. 82-2840
StatusPublished
Cited by1 cases

This text of 564 F. Supp. 1256 (Chevron U.S.A., Inc. v. Watt) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chevron U.S.A., Inc. v. Watt, 564 F. Supp. 1256, 78 Oil & Gas Rep. 26, 1983 U.S. Dist. LEXIS 16875 (E.D. La. 1983).

Opinion

REASONS

ROBERT F. COLLINS, District Judge.

This action is brought by Chevron U.S.A., Inc. (hereinafter Chevron), challenging the administrative action by the Department of the Interior and the Minerals Management Service (hereinafter MMS) in assessing a civil penalty against Chevron for violations of certain provisions of an Outer Continental Shelf (hereinafter OCS) Order, issued pursuant to the Outer Continental Shelf Lands Act (hereinafter OCSLA), 43 U.S.C. § 1331, et seq. Chevron contends that the defendants exceeded their statutory authority in assessing a civil penalty for violations which occurred prior to notice and an opportunity to correct the violations.

The matter is now before the Court on cross motions for summary judgment. There are no issues of material fact outstanding, and the only contested issue is the construction of the particular statutory provision. Therefore, summary judgment is appropriate.

The uncontested facts indicate that Chevron is the lessee and designated operator of Lease OCS 0613, Grand Isle Block 38. The lease was issued by the Department of the Interior and affects a tract lying in the OCS adjacent to the Eastern District of Louisiana. On December 31, 1981, a drilling rig, Penrod 86, arrived at the aforementioned tract and commenced drilling the following day. MMS representatives boarded Penrod 86 on January 5, 1982 to inspect and determine whether the drilling operation complied with the safety and environmental standards set forth in the Gulf of Mexico OCS Order No. 2. The MMS inspectors found that the diverter system and the gas detection system did not comply with the order, and at approximately 11:00 a.m. on January 5, 1982, MMS served upon Chevron written Notice of Incidents of Non-Compliance Detected and Actions Taken. The notice advised Chevron of the two violations and directed Chevron to shut in drilling operations until the deficiencies were corrected. Operations on the rig were discontinued and the violations were rectified. Within approximately five hours of *1258 the notice of non-compliance, MMS authorized Chevron to resume drilling operations.

MMS then initiated civil penalty proceedings against Chevron pursuant to Section 24(b) of OCSLA, 43 U.S.C. § 1350(b). At a hearing held before MMS Reviewing Officer, Dan J. Bourgeois, on April 29, 1982, Chevron conceded the violations in question. Notwithstanding this admission, Chevron contended that the Act only imposes civil penalties following notification of violations and if the violations persist after a reasonable period of time given to correct the violations. By decision dated June 17,1982, the Reviewing Officer assessed a civil penalty against Chevron for failure to comply with the Gulf of Mexico OCS Order No. 2. He found that the diverter system violation occurred for two days and assessed a $500 fine for each day of this violation. He also held that gas detector violation occurred for six days and assessed a penalty of $5,000 per day for non-compliance. The total civil penalty assessed was $31,000. The escalated penalty for failure to comply with the gas detector requirements reflect both the seriousness of the violations and Chevron’s history of gas detection violations during drilling operations in the same general area since April, 1979.

Chevron had the right to appeal the Reviewing Officer’s decision to the MMS Director, pursuant to the applicable regulation. This appeal, however, did not suspend the operation of the Reviewing Officer’s decision, and Chevron would have been required to pay the penalty while awaiting further administrative action. Chevron elected not to pursue an administrative appeal and brought this action to set aside the Reviewing Officer’s decisions and for declaratory and injunctive relief. Chevron remitted the $31,000 civil penalty to MMS after this Court denied Chevron’s motion to stay the assessment of said penalty.

Standing to Sue

While it does not appear to be a contested issue on the cross motions for summary judgment, the defendants had originally challenged Chevron's standing to sue on the grounds that Chevron had not exhausted its administrative remedies in electing to bring this action without taking an administrative appeal. Section 10(c) of the Administrative Procedure Act (hereinafter A.P.A.), 5 U.S.C. § 704, provides in pertinent part:

Agency action made reviewable by statute and final agency action for which there is no other adequate remedy in a court are subject to judicial review .... Except as otherwise expressly required by statute, agency action otherwise final is final for the purposes of this section whether or not there has been presented or determined an application for a declaratory order, for any form of reconsideration or, unless the agency otherwise requires by .rule and provides that the action meanwhile is inoperative, for an appeal to superior agency authority.

Under this section, an agency has a certain degree of latitude in determining whether to require an appeal to superior agency authority as a prerequisite for judicial review. Nevertheless, if an agency intends to require an administrative appeal as a prerequisite to judicial review, it must also provide that the agency action be inoperative while the administrative appeal is pending. New England Coalition on Nuclear Pollution v. United States Nuclear Regulatory Commission, 582 F.2d 87, 99 (1st Cir. 1978); United States v. Consolidated Mines & Smelting, 455 F.2d 432,452 (9th Cir.1971).

In this case, Chevron could have appealed the Reviewing Officer’s decision to the Director of the MMS pursuant to 30 C.F.R. 250.80-1(1). The regulations, however, expressly provide that the assessed penalty must be paid within thirty days of the Reviewing Officer’s decision, even though an administrative appeal is pending. 30 C.F.R. § 250.80-1(0)(3). See also Exhibit D of the Complaint for Prohibitory Injunctive Relief, Declaratory Judgment, and Judicial Review of Administrative Action. Since the order assessing a penalty remains operative even during an appeal, the order constitutes a final agency action within the meaning of the A.P.A. Chevron, therefore, *1259 has standing to bring this action under 5 U.S.C. § 704. 1

Statutory Construction

The crux of this matter is the construction of Section 24(b) of the OCSLA, 43 U.S.C. § 1350(b), which provides as following:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Phillips Petroleum Co. v. Lujan
760 F. Supp. 882 (N.D. Oklahoma, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
564 F. Supp. 1256, 78 Oil & Gas Rep. 26, 1983 U.S. Dist. LEXIS 16875, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chevron-usa-inc-v-watt-laed-1983.