Cheramie v. J. Wayne Plaisance, Inc.
This text of 595 So. 2d 619 (Cheramie v. J. Wayne Plaisance, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Eldon CHERAMIE
v.
J. WAYNE PLAISANCE, INC. and T. Baker Smith & Son, Inc.
Supreme Court of Louisiana.
*620 Michael Osborne, Christopher Gobert, Osborne, McComiskey & Gobert, New Orleans, for applicant.
Robert L. Picou, Jr., Maginnis & Picou, Kenneth Blake Givens, Houma, for respondent.
Nathalie M. Walker, Professor Oliver A. Houck, New Orleans, for amicus curiae, Louisiana Wildlife Federation.
WATSON, Justice.
The issue is whether the employer of plaintiff Cheramie violated the Louisiana Environmental Quality Act in discharging Cheramie.
FACTS
Defendants, J. Wayne Plaisance, Inc. and T. Baker Smith & Son, Inc., entered a contractual Joint Venture on the Isles Dernieres Stabilization Project for the Louisiana Department of Transportation and Development (DOTD). The Isles Dernieres barrier island system consists of three uninhabited islands five miles off the coast of Terrebonne Parish, Louisiana. The islands are described as the East, Central and West or Last Island.
The Project was designed to stabilize the islands between Raccoon Point and Wine Island by restoring the dunes and washover areas and filling in the breaches. An artificial dune measuring approximately 110 feet wide and five feet high was to be constructed with fill from Lake Pelto and Caillou Bay. The contract was in three phases totaling $1,499,700. A map of the area is shown below:
*621
The contract required an assessment of environmental effects. A key part of this assessment was a description of the habitat, its animals and any endangered or threatened species. The assessment was included in Phase I of the contract but was scheduled and completed after the initial surveys.
Ted Joannen, a biologist with the Louisiana Department of Wildlife and Fisheries, has headed the brown pelican program in Louisiana since 1968. Because the native brown pelicans had disappeared, young birds were imported from Florida. In 1984, fifty birds were placed on the Isles Dernieres chain, an original nesting site of brown pelicans. The part of West Island where the birds were released is owned by the state of Louisiana. The fledglings were ten to twelve weeks old and had to be fed and nursed until they could fly. Pelicans mature in three years. In 1987, Joannen was delighted to see adult brown pelicans on Raccoon Point of West Island. There was a nesting attempt by the birds, which required solitude.
On May 22, 1987, Joannen received a report that the pelicans had abandoned their nest. Joannen contacted the Project Manager, Marc Rogers, and asked that the Joint Venture's workers stay off West Island until the damage could be assessed. Rogers agreed. On May 25, Rogers sent a letter to the DOTD confirming the agreement.
Joannen testified that a helicopter visited the island on May 26. The brown pelicans had abandoned their nest, the gulls had eaten the eggs and there were no live young. Survey tracks and flags and people tracks were present throughout the colony. However, it was hoped that the pelicans might re-nest if they were left alone.
Cheramie worked for the Project as an instrument man on a survey crew. His crew chief was John Robichaux. When Cheramie first visited West Island in the middle of May, he saw two or three brown pelicans and thousands of other birds, nests and eggs. His crew was driving an all-terrain four wheeler and pulling a wagon. They damaged a lot of nests and eggs. Cheramie expressed concern about the damage to Robichaux. Cheramie had learned on a previous survey job involving an eagle's nest that endangered species must be protected. Subsequently, Cheramie complained to regulatory officials about the damage, although his employer was apparently unaware of Cheramie's communications. Cheramie said he was attempting to discover if the surveying work on West Island was permitted.
On June 1, 1987, shortly after Rogers said the Joint Venture's workers would stay off the island, all four of its crews were mobilized to finish the work on West Island. The most probable explanation is found in Cheramie's quotation of Robichaux: "trying to complete it before they received papers stating not to go back on that particular island." (TR. 165).
On June 1, 1987, Cheramie's crew boarded a crew boat in Cocodrie, which took them to a quarter boat five or ten miles from the islands. Robichaux told Cheramie they were going to Raccoon Point on West Island. Cheramie was reluctant; he said the proposed work was illegal and asked *622 for alternate work. Robichaux told Cheramie he had no choice, go or be fired. Cheramie was fired at approximately 8:30 A.M. All of the other surveyors went to West Island. Shortly afterward, the DOTD called and instructed the Joint Venture to vacate West Island. About 10:30 A.M., the four crews were diverted to Central Island. Cheramie waited at the quarter boat until the crews returned from the day's work.
John Joseph Plaisance II, president of J. Wayne Plaisance, Inc., testified that Cheramie had worked for the company in 1985 and 1986, and on this job in 1987. John Plaisance said Cheramie, a good worker, was fired for refusing to work on West Island. Plaisance understood that Cheramie was concerned about the legality of the work. The West Island work was completed that fall.
A June 4, 1987, internal memo to Rogers states: "it appears that Mr. Cheramie was the one who first called the Fish & Wildlife and told them we were on the island destroying the eggs." (TR. 55).
William K. Mellor, a special agent with the United States Fish and Wildlife Service, testified by deposition that he received a complaint from Cheramie that the Joint Venture was disturbing nesting brown pelicans on West Island, in violation of the Endangered Species Act. Agent Mellor went to the island several times, once with Cheramie. He observed that all-terrain vehicles had traveled over nesting areas, destroying nests containing eggs and young birds. Members of a work crew admitted that they had rolled over some birds.
As a result of Mellor's investigation, a federal grand jury convened. Mellor recommended prosecution of the Joint Venture to the United States Attorney. The United States Fish and Wildlife Service was not aware of the DOTD's Project, which required a federal permit.
Cheramie was paid $6.00 an hour. In 1986, Cheramie had reported income of $7,014 and $3,248 in unemployment benefits. In 1987, he was paid $3,804.50 and compensation of $1,016. Before his discharge, Cheramie had been laid off but never fired. After he was fired, he was unsuccessful in getting another job, despite repeated applications. His truck was repossessed. He felt threatened. Some members of his family said he had made a mistake. Dr. Walter Birdsol of Galliano prescribed Xanax, an anti-anxiety drug.
Dr. Birdsol referred Cheramie to a clinical psychologist, Dr. Rafael Salcedo, for psychological evaluation. A Minnesota Multiphasic Personality Inventory (MMPI) indicated that Cheramie was experiencing internal stress and turmoil. The validity scale on Cheramie's MMPI profile revealed an open, straightforward attitude, without exaggeration or denial. Dr. Salcedo diagnosed Cheramie as having a depressive reaction to the stressful experience. The charge for three office visits, evaluation and testing was $240. Cheramie was unable to afford the further treatment recommended by Dr. Salcedo.
The trial court dismissed plaintiff's suit, holding that Cheramie was fired for refusing to work and not for reporting an environmental violation.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
595 So. 2d 619, 1992 WL 41928, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cheramie-v-j-wayne-plaisance-inc-la-1992.