Chenoweth v. Settle Engineers, Inc.

156 S.E.2d 297, 151 W. Va. 830, 1967 W. Va. LEXIS 128
CourtWest Virginia Supreme Court
DecidedJuly 11, 1967
Docket12633
StatusPublished
Cited by27 cases

This text of 156 S.E.2d 297 (Chenoweth v. Settle Engineers, Inc.) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chenoweth v. Settle Engineers, Inc., 156 S.E.2d 297, 151 W. Va. 830, 1967 W. Va. LEXIS 128 (W. Va. 1967).

Opinions

[831]*831BeowNING, Judge:

Sometime previous to April 19, 1960, the City of Elkins entered into the construction of a sanitary sewer system and engaged E. A. Taylor & Son, Inc., a general contractor, for the purpose of actual construction and Settle Engineers, Inc., who had previously drafted the plans and specifications for the project, as consulting engineers. The agreement with Settle provided that Settle should provide general engineering supervision including a resident engineer when required and also provide for an inspector under the supervision of the resident engineer but to be paid by the city. The contract between the City and Taylor provided in substance, with regard to matters here pertinent, that the contractor should: exercise precaution for the protection of all persons including employees and property; save the city harmless from all actions and suits by reason of any injury or death; comply with all laws, ordinances and regulations bearing on the conduct of the work; and continuously maintain adequate protection of the work and the city’s property. In connection with the above the contract provided that ‘ ‘ The contractor must furnish and put in place, at his own expense, such shores, braces, sheathing, etc., as may be required to support the sides and roof of the excavation and to prevent any movement which can in any way injure the masonry, diminish the necessary width of the excavation or otherwise injure or delay the work or endanger adjacent pavements, buildings, or other structures. If the Engineer is of the opinion that at any points, sufficient or proper supports have not been provided, he may order additional supports put in at the expense of the contractor and the compliance with such orders shall not release the contractor from his responsibility for the sufficiency of such supports. ...” The special conditions of the contract, under the title “Authority & Duties of Inspectors”, provide: “Inspectors, designated by the engineer, shall be authorized to inspect all work done and materials furnished. Such inspection may extend [832]*832to all or any part of the work and to the preparation or manufacture of the materials to he used. An inspector will be stationed on the work to report to the engineer as to the progress of the work and the manner in which it is being performed; also to report whenever it appears that the materials furnished and work performed by the contractor fail to fulfill the requirements of the specifications and the contract, and to call to the attention of the contractor any such failure or other default, but no inspection, nor any failure to inspect, at any time or place, however, shall relieve the contractor from any obligation to perform all of the work strictly in accordance with the requirements of the specifications. In case of any dispute arising between the contractor and the Inspector as to materials furnished or the manner of performing the work, the Inspector shall have authority to reject materials or suspend the work nntil the question at issue can be referred to and decided by the engineer. The Inspector shall perform such other duties as are assigned to him. He shall not be authorized to revoke, alter, enlarge, relax or release any requirements of these specifications, nor to approve or accept any portion of work, nor to issue instructions contrary to the plans and specifications. The Inspector shall in no case act as foreman or perform other duties for the contractor, nor interfere with the management of the work by the latter.” The ‘ ‘ Special Conditions ’ ’ also provide that the contractor “ . . . shall be strictly responsible for any and all damage or injury of every kind and description, which directly or indirectly may be done to any property or sustained by any persons during the prosecution of the work resulting from any wrong-doing, misconduct, want of care or skill, or any negligence of himself or his agents and/or employees in his manner or method of executing said work or due to his non-execution of said work. . . .” The contract again refers to inspectors under the heading “General Stipulation”, after providing that the [833]*833contractor shall execute the work only in the presence of the engineer or inspector but such presence shall in no way relieve the contractor of responsibility for the work or for the furnishing of poor material or workmanship, by stating “Necessary authority is granted the Engineer or inspector over men actually engaged in any work embraced in this Contract, as to compliance with these specifications, and these men must obey his directions. ...”

On April 19,1960, plaintiffs ’ decedents were working in a ditch nine and one-half feet deep and approximately three feet wide on the project when the sides of the ditch caved in completely covering them and resulting in their deaths. The widows, as administra-trices of their respective husbands’ estates, instituted individual actions for wrongful death in the Common Pleas Court of Kanawha County against the City of Elkins and Settle Engineers, Inc., who in turn im-pleaded Taylor as a third party defendant on the basis of the contractor’s indemnity. The three cases were consolidated for trial and, Settle having reached a compromise with plaintiffs in the meantime, the jury returned a verdict in favor of each plaintiff against the City of Elkins for the sum of $20,000.00. The verdicts were reduced by $5,000.00, the amount of the Settle compromise payments in each case and judgments were entered for each plaintiff in the sum of $15,000.00. On appeal to the Circuit Court of Ka-nawha County, the judgments were reversed with directions to enter judgment for the defendant, City of Elkins, in each case to which action this Court granted an appeal on December 5,1966. In addition to the contract between the City of Elkins and Taylor which was introduced in evidence, the “West Virginia Safety Code for Building Construction”, regulations of the West Virginia State Department of Labor, were introduced in evidence, the pertinent parts of which pertaining to excavation work are as follows:

“1.1 This Part on ‘Excavation Work’ provides for the protection of the public, employees, and [834]*834property during all excavation work in connection with, building and trenching operations, including related sub-surface or below grade-level work such as tbe underpinning, shoring, and bracing of foundations, retaining walls, and the like. í Í
“1.8 The sides of every excavation four (4) feet or more in depth, where there is danger of slides or cave-ins, shall be supported by substantially braced sheet piling or shoring unless the sides of the excavation are sloped to the angle of repose of the material being excavated. C i
“1.13 Excavated material shall not be placed on the ground surface nearer than eighteen (18) inches from the edge of the excavation. ’ ’

The portions of such regulations specifically dealing with trenches are substantially the same.

Testimony was introduced on the trial of the case to the following effect: In the course of construction the contractor had encountered different types of soil in varying parts of the city. At the point where the cave-in occurred witnesses for the plaintiff described the soil as “soapstone” while witnesses for the defendant identified it as “hard shale”. The propensities of soapstone and hard shale vary in their stability. Mr. Webb, the inspector employed by the city, was directly concerned with the depth and grade of the ditch and the material used.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

France v. SOUTHERN EQUIPMENT CO.
689 S.E.2d 1 (West Virginia Supreme Court, 2010)
Stillwell v. City of Wheeling
558 S.E.2d 598 (West Virginia Supreme Court, 2002)
Johnson v. C.J. Mahan Construction Co.
557 S.E.2d 845 (West Virginia Supreme Court, 2001)
Shaffer v. Acme Limestone Co., Inc.
524 S.E.2d 688 (West Virginia Supreme Court, 1999)
Brooks v. City of Weirton
503 S.E.2d 814 (West Virginia Supreme Court, 1998)
King v. Lens Creek Ltd. Partnership
483 S.E.2d 265 (West Virginia Supreme Court, 1996)
Thomson v. McGinnis
465 S.E.2d 922 (West Virginia Supreme Court, 1995)
Miller v. Lambert
467 S.E.2d 165 (West Virginia Supreme Court, 1995)
Taylor v. Sears, Roebuck and Co.
437 S.E.2d 733 (West Virginia Supreme Court, 1993)
Pasquale v. Ohio Power Co.
418 S.E.2d 738 (West Virginia Supreme Court, 1992)
Keiffer v. Exxon Corp.
647 F. Supp. 60 (S.D. West Virginia, 1986)
Pack v. Van Meter
354 S.E.2d 581 (West Virginia Supreme Court, 1986)
Moore v. Department of Highways
13 Ct. Cl. 148 (West Virginia Court of Claims, 1980)
Hubbs v. Department of Highways
12 Ct. Cl. 39 (West Virginia Court of Claims, 1977)
Sanders v. Georgia-Pacific Corp.
225 S.E.2d 218 (West Virginia Supreme Court, 1976)
In Re Silver Bridge Disaster Litigation
381 F. Supp. 931 (S.D. West Virginia, 1974)
Hall v. Nello Teer Company
203 S.E.2d 145 (West Virginia Supreme Court, 1974)
Hudgins v. Crowder and Freeman, Inc.
191 S.E.2d 443 (West Virginia Supreme Court, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
156 S.E.2d 297, 151 W. Va. 830, 1967 W. Va. LEXIS 128, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chenoweth-v-settle-engineers-inc-wva-1967.