Chayce v. Path Construction

CourtCourt of Appeals of Arizona
DecidedOctober 22, 2024
Docket1 CA-CV 24-0030
StatusPublished

This text of Chayce v. Path Construction (Chayce v. Path Construction) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chayce v. Path Construction, (Ark. Ct. App. 2024).

Opinion

IN THE ARIZONA COURT OF APPEALS DIVISION ONE

CHAYCE CONCRETE, LLC, Plaintiff/Appellee,

v.

PATH CONSTRUCTION SOUTHWEST, LLC, et al., Defendants/Appellants.

No. 1 CA-CV 24-0030 FILED 10-22-2024

Appeal from the Superior Court in Maricopa County No. CV2022-008136 The Honorable Bradley H. Astrowsky, Judge

VACATED AND REMANDED

COUNSEL

Husch Blackwell LLP, Phoenix By Brendan A. Melander Counsel for Defendants/Appellants

Thrasher Law PLLC, Phoenix By Bobby O. Thrasher, Jr. Co-Counsel for Plaintiff/Appellee

Hill, Hall & Deciancio, PLC, Phoenix By Christopher Robbins Co-Counsel for Plaintiff/Appellee CHAYCE v. PATH CONSTRUCTION, et al. Opinion of the Court

OPINION

Presiding Judge Jennifer B. Campbell delivered the opinion of the Court, in which Judge Kent E. Cattani and Judge Paul J. McMurdie joined.

C A M P B E L L, Judge:

¶1 This is an appeal from the superior court’s order vacating an arbitration award under A.R.S. § 12-3023(A)(1) and (A)(3). We vacate the court’s order because it hinges on unsupported findings. We remand for the trial court to confirm the arbitration award.

BACKGROUND

¶2 Path Construction Southwest, LLC, was the general contractor on a City of Scottsdale trailhead improvement project. Chayce Concrete, LLC, was a subcontractor hired to work on the project. Path sought damages related to Chayce’s alleged failure to complete its work, including damages arising from the project’s delayed completion. Chayce sought damages related to Path’s alleged failure to make payments. Both agreed to submit to binding arbitration to resolve the performance and payment disputes.

¶3 The parties agreed that the arbitration would be governed by the American Arbitration Association’s Construction Industry Arbitration Rules and Mediation Procedures (the AAA Rules), and that a private attorney would serve as the arbitrator. Consistent with AAA Rule R-24, the parties agreed to exchange all documents they intended to rely on, and that each could request production of additional relevant information.

¶4 Chayce served requests for production, and Path responded with more than 7,000 documents. Path also objected in writing to producing certain categories of requested documents. Path made general objections claiming the documents requested were irrelevant, information not in its possession, or were information to which both parties had access. Path also made specific objections indicating that it would not be producing documents related to third-parties’ work on the project. Path repeatedly confirmed that it would “be producing responsive documents related only to work completed by Chayce and/or to be completed by Chayce for [the project].”

2 CHAYCE v. PATH CONSTRUCTION, et al. Opinion of the Court ¶5 Three months after Path’s production and objections and only a few days before the arbitration hearing, Chayce raised issues with Path’s objections for the first time. In a pre-hearing brief, Chayce argued that Path’s objections constituted a deliberate refusal to provide exculpatory information about the possibility that third parties contributed to the project’s delayed completion and Path’s alleged damages. Chayce also argued that Path should have produced documents related to its contract with the City and the retention of a subcontractor to replace Chayce on the project. Chayce argued that it could be assumed that the undisclosed documents undercut Path’s narrative—but Chayce did not request that the arbitration be continued to allow resolution of the discovery issue. The arbitration hearing went forward as scheduled.

¶6 There is no transcript from the arbitration hearing. At the oral argument in the superior court on the motion to vacate the arbitration award, Chayce asserted that its counsel repeatedly requested a postponement at the arbitration hearing. But Chayce provided no evidence confirming that assertion. To the contrary, it was Path’s counsel who provided a sworn declaration stating that he did not recall any request for postponement being made.

¶7 In a post-hearing brief to the arbitrator, Chayce did not once refer to any previous request for postponement. Nor did it request a post-hearing continuance or any other proceedings at the arbitration level to address discovery issues. Chayce argued instead that Path’s nondisclosure of third-party information precluded an assessment of delay damages against Chayce. Chayce stated that witness Sean Lynch testified at the arbitration hearing that Path sought and recovered delay damages from other subcontractors. Chayce also argued—for the first time—that Path’s nondisclosure of information about its pay-application communications with the City entitled Chayce to an adverse inference. Chayce stated that Path presented no evidence that it submitted Chayce’s pay applications to the City.

¶8 The arbitrator issued a partial final award that addressed Chayce’s nondisclosure arguments without mentioning any postponement request. The arbitrator penalized Path for failing to disclose information about third parties’ possible contributions to the completion delay by precluding all delay damages. The arbitrator explained he ”refus[ed] to reward Path for preventing Chayce’s counsel from discovering potential, relevant information related to these delay issues.” In sum, Chayce prevailed on delay damages as a direct result of Path’s failure to produce relevant documents.

3 CHAYCE v. PATH CONSTRUCTION, et al. Opinion of the Court ¶9 The arbitrator concluded, however, that Chayce could not recover damages based on Path’s nondisclosure of information related to the status of the City’s progress payments on Chayce’s pay applications (which, the arbitrator noted, Chayce could have monitored by filing a request with the City under A.R.S. § 34-221(H)1). The arbitrator found that documentary evidence showed that one pay application was rejected by Path, and that Chayce then chose to abandon its work rather than submit a corrected application.

¶10 The arbitrator concluded that “Path did not materially breach the Subcontract by lawfully withholding submittal to the City or certification of Chayce’s Pay Applications pursuant to A.R.S. § 34-221(I),” which “allow[ed] Path . . . to withhold from the City a subcontractor’s pay application or the certification of a subcontractor’s pay application for a number of reasons including unsatisfactory job progress and defective construction work.” The arbitrator awarded Path nearly $95,000 in damages based on Chayce’s abandonment of its work under the subcontract, plus attorney’s fees and costs totaling about $77,000.

¶11 Path, along with its insurer, moved the superior court to confirm the arbitration award and enter judgment. Chayce objected and moved to vacate the award, arguing that the arbitrator “awarded damages to Path notwithstanding its withholding of critical evidence from Chayce” and “refused Chayce’s request to continue the matter in violation of A.R.S. § 12-3023(A)(3).” In briefing before the superior court, Chayce emphasized that Path refused to provide information regarding third-parties’ work despite Lynch’s testimony that Path had also blamed other subcontractors for the completion delay—information relevant to determining the delay damages that Path sought (but was not awarded).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fisher Ex Rel. Fisher v. National General Insurance
965 P.2d 100 (Court of Appeals of Arizona, 1998)
Clarke v. Asarco Inc.
601 P.2d 587 (Arizona Supreme Court, 1979)
Quine v. Godwin
646 P.2d 294 (Court of Appeals of Arizona, 1982)
Pawlicki v. Farmers Insurance
618 P.2d 1096 (Court of Appeals of Arizona, 1980)
Atreus Communities Group v. Stardust Development, Inc.
277 P.3d 208 (Court of Appeals of Arizona, 2012)
FIA Card Services, N.A. v. Levy
200 P.3d 1020 (Court of Appeals of Arizona, 2008)
Moore v. Olson
351 P.3d 1066 (Alaska Supreme Court, 2015)
J Hamblen Et Ux v. Hon. hatch/winslow Memorial
398 P.3d 99 (Arizona Supreme Court, 2017)
Russell Piccoli P.L.C. v. O'Donnell
344 P.3d 345 (Court of Appeals of Arizona, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Chayce v. Path Construction, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chayce-v-path-construction-arizctapp-2024.