Chavez v. Sedillo

284 P.2d 1026, 59 N.M. 357
CourtNew Mexico Supreme Court
DecidedJune 9, 1955
Docket5917
StatusPublished
Cited by12 cases

This text of 284 P.2d 1026 (Chavez v. Sedillo) is published on Counsel Stack Legal Research, covering New Mexico Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chavez v. Sedillo, 284 P.2d 1026, 59 N.M. 357 (N.M. 1955).

Opinions

McGHEE, Justice.

The lower court gave judgment for the defendants on the pleadings in this action to foreclose a mechanic’s lien upon the ground a fatal variance existed between the allegations of the plaintiff’s pleadings and the claim of lien upon which he relied. The plaintiff appeals.

The order granting motion for judgment on the pleadings did not specify the nature of the fatal variance, but it appears from the briefs of counsel here that argument was made to the lower court respecting variance between the statement in the claim of lien as to the terms, time given and conditions of the contract under which the labor and materials were supplied, required to be set forth in the claim of lien under § 61-2-6, 1953 Comp., and those matters as alleged in the complaint and answer to counter-claim of defendants

Section 61-2-6, 1953 Comp., provides:

“Every original contractor, within one hundred and twenty (120) days after the completion of his contract, and every person, save the original contractor, claiming the benefit of this article must within ninety (90) days after the completion of any building, improvement, or structure, or after the completion of the alteration or repair thereof, or the performance of any labor in a mining claim, file for record with the county clerk of the county in which such property or some part thereof is situated, a claim containing a statement of his demands, after deducting all just credits and off-sets, with the name of the owner or reputed owner, if known, and also the name of the person by whom he was employed, or to whom he furnished the materials, with a statement of the terms, time given and the conditions of his contract, and also a description of the property to be charged with the lien, sufficient for identification, which claim must be verified by the oath of himself or of some other person.” (Emphasis supplied.)

To determine whether a fatal variance does exist it is necessary to examine in some detail the claim of lien and the pleadings of the plaintiff.

Omitting portions of the lien claim regarding the designation of persons and description of the land, it reads as follows:

“That the lien claimant herein, Arthur Chavez, pursuant to agreement, furnished materials and labor in the construction of a residence on the premises hereinbefore described, during the period October 13, 1950, to January 27, 1951. A statement of the cost of the materials furnished, the cost of the labor furnished and the credits thereon for amounts paid by said Dan R. Sedillo and Emilia Sedillo, is as follows:
“Total for labor and materials furnished $18,102.60
* * * * * *
(Here follows itemized credits)
“Total Credits $16,600.00
“Balance............... $1,502.60
‡ ‡ ‡ ‡ ‡ $
“That said work was performed under a contract which provided that claimant was to be paid for said labor and materials upon completion of claimant’s work, and that his work terminated on Jan. 27, 1951, and that said labor was performed upon said residence or building constructed by claimant on the premises hereinbefore described.
******
“That on March 2, 1951, the lien claimant herein and said Dan R. Sedillo and Emilia Sedillo, his wife, agreed that the amount owing claimant for said labor and materials furnished in the construction of said residence by lien claimant was $1502.60.
“That the amount for which this lien is claimed is the sum of $1502.60 and that said sum is owing the claimant for said labor and materials after deducting all offsets and credits. * * * ”

In resume, this claim asserts: (1) Materials and labor in the construction of a residence for the defendants Sedillo were furnished pursuant to agreement. (2) The total cost of materials and labor so furnished was $18,102.60 and the balance still-owing is $1,502.60. (3) The work was performed under a contract providing claimant was to be paid for labor and materials at completion of Ms work. (4) On March 2, 1951 (a date after completion of the work), claimant and defendants Sedillo agreed the amount owing claimant for labor and materials furnished was $1,502.60.

The allegations of the complaint setting forth the agreement under which the work was done and the arrangement for payment read as follows:

“5. That on the 13th day of October, 1950, a building contract was entered into by plaintiff on the one part and said defendants Dan R. Sedillo and Emelia Sedillo on the other part, which said contract provided for the construction and erection of a residence and garage on said real estate hereinbefore described by plaintiff, the plaintiff to construct said residence and garage and furnish all labor and materials necessary therefor, the said defendants to pay the plaintiff all cost of said labor and materials and an additional sum of 10% of the cost of said labor and materials, but which 10% was not to exceed the sum of $1500.00. Copy of said contract is hereto attached, marked Exhibit ‘A’ for identification, and is incorporated by reference herein the same as though said contract were set forth in full herein.
“6. That pursuant to said contract, plaintiff did furnish materials and did work and labor on said building and garage and did fully and completely perform said contract with its terms; that plaintiff, in addition to said contract and at the special instance and request of said defendants Dan R. Sedillo and Emelia Sedillo, furnished additional materials and labor for the erection, construction and completion of said building as requested by said defendants from time to time. That plaintiff furnished defendants a full and complete statement of the bills for said labor and materials during the progress of the work, construction and completion of said building. That all of the furnishing of said labor and materials and plaintiff’s work was completed on or about January 27, 1951; that the total cost of labor and material furnished by plaintiff herein was the sum of $18,102.60; that said defendants paid on said sum the total sum of $16,600.00, leaving a balance due on March 2, 1951, in the sum of $1502.60; that on the 2nd day of March, 1951, said defendants and the plaintiff agreed that the amount owing plaintiff for said labor and materials furnished in the construction of said residence and garage was $1502.60, and said sum of $1502.60 became a stated account owing by said defendants to plaintiff on account of the construction of said building. Plaintiff attaches hereto copy of statement of account dated February 7, 1951, with an indicated balance of $1502.60, which was the agreed balance due on said contract on March 2, 1951, said copy being marked Exhibit ‘B’ for identification, and which is incorporated by reference herein as though set forth in full herein.

The written contract set forth as Exhibit “A” is brief and is quoted below:

“This agreement made and entered into, in triplicate, this 13 day of October, 1950, by and between Mr. and Mrs. Dan R.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Szantho v. Casa Maria of N.M., LLC
New Mexico Court of Appeals, 2025
Sonida, LLC v. Spoverlook, LLC
2016 NMCA 026 (New Mexico Court of Appeals, 2015)
Ulibarri v. Gee
748 P.2d 10 (New Mexico Supreme Court, 1987)
Crego Block Co. v. D. H. Overmyer Co.
458 P.2d 793 (New Mexico Supreme Court, 1969)
Hall v. Budagher
417 P.2d 71 (New Mexico Supreme Court, 1966)
Jones v. International Union of Operating Engineers
383 P.2d 571 (New Mexico Supreme Court, 1963)
Lembke Construction Co. v. JD Coggins Company
382 P.2d 983 (New Mexico Supreme Court, 1963)
Gonzales v. Gackle Drilling Company
371 P.2d 605 (New Mexico Supreme Court, 1962)
Jernigan v. New Amsterdam Casualty Company
367 P.2d 519 (New Mexico Supreme Court, 1961)
Terry v. Pipkin
340 P.2d 840 (New Mexico Supreme Court, 1959)
Chavez v. Sedillo
284 P.2d 1026 (New Mexico Supreme Court, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
284 P.2d 1026, 59 N.M. 357, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chavez-v-sedillo-nm-1955.