Chavelle v. Island Gun Club

137 P. 511, 77 Wash. 304, 1914 Wash. LEXIS 893
CourtWashington Supreme Court
DecidedJanuary 7, 1914
DocketNo. 11301
StatusPublished
Cited by10 cases

This text of 137 P. 511 (Chavelle v. Island Gun Club) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chavelle v. Island Gun Club, 137 P. 511, 77 Wash. 304, 1914 Wash. LEXIS 893 (Wash. 1914).

Opinion

Ellis, J.

This action was instituted by one L. C. Hall, for the purpose of foreclosing a lien upon certain premises in Skagit county, owned by the defendants Bacon. The Island Gun Club, Suess and wife, Campbell and wife, and Stormfeltz and wife, were made defendants as holders of a contract for the purchase of the premises from the Bacons. The Everett Construction Company, a corporation, was made a defendant because of its having previously filed a notice of claim of lien against the same premises. It filed an answer and cross-complaint, to which a demurrer was sustained. In the meantime, Hall had been adjudged a bankrupt, and Edward H. Chavelle, as trustee in bankruptcy, was substituted as plaintiff. From an order dismissing its cross-complaint, the defendant Everett Construction Company appeals.

The facts admitted by the demurrer to the cross-complaint are as follows: On May 9, 1910, Hall, under a written contract with the defendants Suess, Campbell, and Stormfeltz, and the Island Gun Club, entered upon the work of constructing a dyke around the property in question. The Island Gun Club is an unincorporated association, composed of the defendants Suess, Campbell, and Stormfeltz. In carrying out his contract, the principal contractor, Hall, entered into an oral agreement with the appellant, Everett Construction Com[306]*306pany, whereby that company was to do the work of dredging, furnish its own dredger and operating crew, and supervise the building of the dyke, for the sum of $40 a day of nine working hours. Hall completed the dyke, performing work alleged to be of the value of $8,016.87, of which he received $4,750, leaving a balance unpaid of $3,266.87. The appellant, under its oral agreement with Hall, furnished the dredger and crew for a period of time sufficient to entitle it to $2,478.46, of which $400 has been paid, leaving a balance owing to it of $2,078.46, with interest. On October 24, 1910, it filed its notice of lien against the premises; and on November 9, 1910, Hall filed his notice of lien. Subsequently, the present action was begun in the lower court, with the result above noted. The sole question presented for our consideration is whether or not the oral agreement entered into between Hall and the appellant here and the work performed thereunder was such as to entitle the appellant to a lien on the premises.

The statute under which the appellant claims the right of lien contains the following provisions material to this inquiry (references are to the section numbers of Rem. & Bal. Code) :

“Sec. 1129: Every person performing labor upon or furnishing material to be used in the construction, alteration or repair of any . . . dyke . . . has a lien upon the same for the labor performed or material furnished by each, respectively, whether performed or furnished at the instance of the owner of the property subj ect to the lien or his agent; and every contractor ... or person having charge, of the construction, alteration or repair of any property subject to the lien as aforesaid, shall be held to be the agent of the owner for the purposes of the establishment of the lien created by this chapter.”
“Sec. 1139: The contractor shall be entitled to recover upon the claim filed by him only such amount as may be due him according to the terms of his contract, after deducting all claims of other parties for labor performed and materials furnished . . .”
“Sec. 1141: In every case in which different liens are claimed against the same property, the court, in the judgment, [307]*307must declare the rank of such lien or class of liens, which shall be in the following order:
“1. All persons performing labor;
“2. All persons furnishing material;
“3. The subcontractors;
“4. The original contractor.”
“Sec. 1147: The provisions of law relating to liens created by this chapter, and all proceedings thereunder, shall be liberally construed with a view to effect their objects.” (P. C. 309 §§ 53, 73, 77, 89).

A reading of these sections, and an application of the liberal rule of construction prescribed by the section last quoted, induces the view that it was the intention of the law makers to provide a lien for every person furnishing materials going directly into the given structure, or performing labor directly upon it. The provision first quoted (§ 1129) accords a lien to every person performing labor or furnishing materials, and § 1141 classifies all persons doing either, and prescribes the rank of their liens. Section 1139, taken in connection with § 1141, must be construed as using the word “contractor” in its generic sense, and including both the principal contractor and subcontractors, else there would be no lien for a subcontractor as such, and no lien whatever for a subcontractor except as he might also be a laborer or a materialman. The latter cannot be the intention, because, in § 1141, the subcontractor’s lien is subordinated to that of laborers and material-men, which would be wholly senseless unless there were a distinction between the lien of a subcontractor and that of a laborer or materialman.

Construing these three sections together and giving a meaning to each, it is clear that a subcontractor as such is entitled to a lien for labor or materials or both, furnished and paid for by him in the performance of some specific part of the work under contract with the principal contractor, as distinguished from the lien prescribed for laborers and material-men as such. The recovery on a subcontractor’s lien is, [308]*308therefore, like that of any other contractor given under § 1139 “according to his contract;” otherwise it has no independent existence, though expressly subordinated to, and hence distinguished from, the liens of laborers and materialmen under § 1141. It follows that the only sensible distinction between the lien accorded to the principal contractor and the subcontractor is found in the fact that, in marshaling liens, the latter ranks the former and receives a preference in the distribution of the proceeds of the sale of property subject to the liens on foreclosure, just as the latter is subordinated to the liens of laborers and materialmen as such.

There is, and can be, no distinction as to the character of the items going to make up the lien claim of the principal contractor and that of a subcontractor without destroying the lien of the latter as a distinct lien. Each is entitled to recover upon his lien claim the amount due according to his contract, “after deducting all claims of other parties for labor performed or materials furnished.” Unquestionably, the principal contractor who undertakes a given work and contracts to furnish labor, materials, tools and instrumentalities for the purpose, is entitled to a lien for all labor performed and materials furnished and paid for by him in the performance of his contract; and the amount of his lien is determined by the amount due him according to the terms of his contract and neither this amount nor the lienability of his claim is affected by the fact that he also agrees to furnish, as part of the consideration for his contract on the-given terms, the instrumentalities and tools used in the work and by which the labor is made effective and the materials handled, molded, fitted and adjusted to the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cordell v. Regan
598 P.2d 416 (Court of Appeals of Washington, 1979)
Norris Industries v. Halverson-Mason Constructors
529 P.2d 1113 (Court of Appeals of Washington, 1974)
A.A.C. Corp. v. Reed
483 P.2d 1293 (Court of Appeals of Washington, 1971)
Willett v. Davis
193 P.2d 321 (Washington Supreme Court, 1948)
Fergusson v. Guy
276 P. 855 (Washington Supreme Court, 1929)
Davidson v. National Can Co.
273 P. 185 (Washington Supreme Court, 1928)
Ellis-Mylroie Lumber Co. v. Bratt
205 P. 398 (Washington Supreme Court, 1922)
Adams v. Dose
152 P. 9 (Washington Supreme Court, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
137 P. 511, 77 Wash. 304, 1914 Wash. LEXIS 893, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chavelle-v-island-gun-club-wash-1914.