Chase Orchards v. Gerber Construction, No. Cv 0596922 S (Aug. 22, 2002)

2002 Conn. Super. Ct. 10495
CourtConnecticut Superior Court
DecidedAugust 22, 2002
DocketNo. CV 0596922 S
StatusUnpublished

This text of 2002 Conn. Super. Ct. 10495 (Chase Orchards v. Gerber Construction, No. Cv 0596922 S (Aug. 22, 2002)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chase Orchards v. Gerber Construction, No. Cv 0596922 S (Aug. 22, 2002), 2002 Conn. Super. Ct. 10495 (Colo. Ct. App. 2002).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION
The plaintiff Chase Orchards, LLC, is a developer and builder of a residential real estate development in South Windsor. For purposes of this case, the principal member of the LLC is John Doran. This action involves a dispute with Gerber Construction, Inc., whose principal officer is Ron Gerber. The court trial spanned six hearing days in March, 2002, and the last brief was filed on May 3, 2002. In August, when the decision was being written, the plaintiff alleged in a motion that certain testimony, which had been accepted as factually accurate by both CT Page 10496 sides, was in fact erroneous. I allowed brief additional testimony on August 20, 2002.

Doran had in the mid-1990's developed another subdivision, Chase Farms, which consisted of seventeen homes. Toward the end of the work at Chase Farms Doran hired Gerber1 to perform excavation work on approximately ten lots, and there were no problems with that work.

Chase Orchards was a more ambitious project. The project was built on approximately sixty acres in South Windsor near the town line with Vernon. Doran received subdivision approval for 51 residential lots. Much of the land was on a hill which contained significant ledge rock, and therein lies the rub. Most, but not all, of the dispute in this action concerns the costs of and charges for the removal of rock and associated activities.

In October, 1997, Doran sent invitations to bid on the site construction work to three subcontractors, including Gerber. The "request for bid" listed the work to be performed. It included clearing the land, installation of erosion controls, "cuts fills", "trucking if required", sanitary and storm sewer installation, trenches for various utilities, grading, paving, water mains and more. The request specified that the bid "shall include all work including labor and materials, required to complete the subdivision improvements as shown on plans prepared by (the engineering firm)." The request for bid further provided that the "contractor shall provide a cost for trench rock and mass rock removal per cubic yard. If rock is encountered the contractor shall be responsible to uncover rock required for removal and the owner shall, at no expense to the contractor, have his surveyor cross section the rock to be removed."

Gerber responded to the request to bid by submitting separate proposals for Phase I and Phase II. The amount of the proposal for Phase I initially was $904,700.00; for Phase II it was $519,067.000. After some discussion, the signed contract for Phase I was for the amount of $751,355.00; this contract was signed in August, 1998, and incorporated three change orders that had already been authorized. There never was a final, signed version of the Phase II agreement, but after some items were excluded from the proposal because Doran thought he could do better by independently contracting with someone else for those items, the final amount was approximately $350,000.00.

From the beginning of the negotiating process, everyone knew that blasting of rock would be required and it was apparent that the amount of rock was significant. Some ledge rock could be seen at the surface. Before virtually any work was done, Doran asked an employee to dig a CT Page 10497 number of test holes roughly in the center of the future roadway to determine the depth of the rock: the shallower the hole before one reached rock, the more rock would have to be removed. The request to bid and the various proposals submitted by Gerber specifically exclude blasting itself. Indeed, Gerber apparently suggested that the blasting be done by Ravizza Brothers, and Doran then contracted directly with Ravizza for those services. Gerber arranged for Botticello, Inc., to crush rock on the premises and negotiated with Doran a price per yard for crushing, which was paid by Doran to Gerber.

One of the primary subjects in dispute is who was responsible for the trucking of blasted rock. Once rock was blasted, from the roadway, trenches and, later, individual lots, the blasted rock had to be transported to a rock crusher, which was installed on site, and the resulting product had to be transported as well, either for use as fill or gravel on other parts of the development or to be disposed off site. Because of the massive amounts of rock involved, the trucking cost was considerable. Both principal parties testified about the contractual arrangement for the cost of trucking, and the testimony was diametrically opposed.

Doran testified that in a meeting shortly after Gerber submitted his bid proposals the issue came up. During that meeting, Doran took some notes on a copy of the request for bid which he had prepared, and that copy was introduced into evidence (Exhibit 2). Included in the bid was the item "trucking if required"; on the request to bid, this item appeared directly beneath the item "cuts fills". Next to "trucking if required", Doran wrote "in cuts fills". Doran testified that this note memorialized for him the understanding he had reached with Gerber that the cost for all trucking, including hauling blasted rock, was included in Gerber's category of "cuts and fills as shown" in his various proposals.

Gerber agreed that there was such a meeting and that the subject of rock was a topic covered at the meeting. Gerber's position was that by the terms of the request for bid, his bid proposals and their conversations, trucking the blasted rock was not part of his bid but was specifically excluded. The request for bid does not include in the list of tasks to be included in the contract blasting or items expressly related to blasting, and all of Gerber's various "proposals" state specifically that the proposal does not include "ledge excavation, blasting, and backfill". Gerber testified that Doran's notation "trucking if required" next to the "cuts fills" category simply meant that if trucking were needed to carry material away from areas high areas or to low areas, that trucking activity was included in his contract and was not an extra. Gerber's consistent position was that all activity associated with CT Page 10498 blasting, including the blasting itself, transporting the blasted rock to the crusher, crushing, and transporting the crushed product to its destination was excluded from the contract. The destination of the crushed rock, according to Gerber, was variously on-site locations, to provide fill or gravel, and off-site locations, where it was either discarded or sometimes traded for material which was needed on location.

In any event, Doran agreed to hire Gerber as the site construction contractor. They determined that there was too much rock to cart it off site in its blasted state, because, among other reasons, some of the chunks of rock would be too large to fit in standard trucks. Gerber subcontracted the crushing operation and arranged for Botticello, Inc., to supply an on site rock crusher. There was dispute at trial regarding the cost of the rock crushing operation. Doran testified that he thought the agreed upon amount was $4.00 per yard that he would pay Gerber and that the cost included associated items such as the loader and hammer. Gerber testified that the agreed upon price was $5.00 per yard and did not include the associated activities.

Work began on the project physically early in 1998, although the signed contract for Phase I was not signed until November, 1998, and the contract for the second phase was never actually signed. There apparently was little dispute at first.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Federal Trade Commission v. Sperry & Hutchinson Co.
405 U.S. 233 (Supreme Court, 1972)
Conaway v. Prestia
464 A.2d 847 (Supreme Court of Connecticut, 1983)
Tomasetti v. Maryland Casualty Co.
169 A. 54 (Supreme Court of Connecticut, 1933)
McLaughlin Ford, Inc. v. Ford Motor Co.
473 A.2d 1185 (Supreme Court of Connecticut, 1984)
Atlantic Richfield Co. v. Canaan Oil Co.
520 A.2d 1008 (Supreme Court of Connecticut, 1987)
Daddona v. Liberty Mobile Home Sales, Inc.
550 A.2d 1061 (Supreme Court of Connecticut, 1988)
A-G Foods, Inc. v. Pepperidge Farm, Inc.
579 A.2d 69 (Supreme Court of Connecticut, 1990)
State v. Yurch
654 A.2d 1246 (Connecticut Appellate Court, 1995)
Meyers v. Cornwell Quality Tools, Inc.
674 A.2d 444 (Connecticut Appellate Court, 1996)
Citino v. Redevelopment Agency
721 A.2d 1197 (Connecticut Appellate Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
2002 Conn. Super. Ct. 10495, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chase-orchards-v-gerber-construction-no-cv-0596922-s-aug-22-2002-connsuperct-2002.