Charter Oak Fire Insurance Company v. Bremermann Mechanical, Inc

CourtDistrict Court, E.D. Louisiana
DecidedMarch 31, 2025
Docket2:21-cv-01486
StatusUnknown

This text of Charter Oak Fire Insurance Company v. Bremermann Mechanical, Inc (Charter Oak Fire Insurance Company v. Bremermann Mechanical, Inc) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Charter Oak Fire Insurance Company v. Bremermann Mechanical, Inc, (E.D. La. 2025).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF LOUISIANA

THE CHARTER OAK FIRE CIVIL ACTION INSURANCE COMPANY and TRAVELERS PROPERTY CASUALTY COMPANY OF AMERICA, as subrogees of WRIGHT BROS., LLC.

VERSUS NO: 2:21-1486

BREMERMANN MECHANICAL, INC., SECTION: T (4) SIEMENS INDUSTRY, INC., KINSALE INSURANCE COMPANY, and HDI GLOBAL INSURANCE COMPANY.

ORDER AND REASONS Before the Court are three Motions for Summary Judgment filed by Defendants Bremermann Mechanical, Inc. (“BMI”), Siemens Industry, Inc. (“Siemens”), Kinsale Insurance Company (“Kinsale”), and HDI Global Insurance Company (“HDI”). R. Docs. 185, 186, 187. For the following reasons, the motions are GRANTED. BACKGROUND This years-long litigation asks who is responsible for a water leak from a drain valve (the “Subject Valve”) on the tenth floor of the Hale Boggs Federal Building. Plaintiffs, The Charter Oak Fire Insurance Company (“Charter Oak”) and Travelers Property Casualty Company of America (“Travelers”), are subrogees of Wright Bros., LLC (“WB”), the general contractor. Defendants are BMI and Siemens, the subcontractors, (collectively, “Subcontractors”) and their insurers, HDI and Kinsale. 1 A. Factual History The United States General Services Administration (“GSA”), the building owner, and WB contracted for WB to serve as the general contractor to create office space on the tenth floor of the building (the “Project”). Under the general contract, WB was responsible for providing all

materials, services and labor to both design and construct the office space. R. Doc. 185-3. There are two relevant subcontracts. On September 19, 2019, WB subcontracted with BMI to provide HVAC installation on the Project (“WB-BMI Subcontract”). R. Doc. 201-2. On October 10, 2019, BMI subcontracted with Siemens to provide products and services to facilitate the installation (“BMI-Siemens Subcontract”). R. Doc. 185-4 at pp. 15-19. As part of its work, Siemens provided mechanical submittals to BMI starting on October 14, 2019 (“the Submittal”). R. Doc. 185-6. The Submittal contained technical data and diagrammatic representations of a Nexus Model BD-025 Blowdown/Drain Valve (the “Subject Valve” or generally, the “drain valve”) that was incorporated into a Nexus UltraY Model UY Ball Valve, Y-Strainer (the “y-strainer”), and the Subject Valve’s associated thread cap (the “cap(s)”),

(collectively, the “Valve System”). Id. Five Valve Systems were to be installed in the tenth-floor ceiling. All systems used composite caps. Plaintiffs introduced evidence from the Valve System’s manufacturer that the installed composite caps or any caps on the Valve System were not designed to contain water flow. R. Doc. 218-1 at p. 9 (emphasis supplied); R. Doc. 218-16 (information from the drain valve manufacture stating “the cap IS NOT designed to contain flow”); R. Doc. 218-18 (“[n]or is the brass cap” intended to hold water pressure). Plaintiffs’ expert, Joseph Kresovsky, explained: (a) that the manufacturer designed the caps to protect the threads on the 2 drain outlet and to catch drips, rather than hold pressure, and (b) that the Project’s specifications do not expressly require brass caps over composite caps. R. Doc. 218-9 at p. 16. On October 24, 2019, after Siemens transmitted two submittals to BMI, BMI provided a submittal to WB for approval. WB referred this submittal to its selected engineer, Griffith

Engineering (“Griffith”), and GSA for review and approval. Griffith reviewed this submittal. It is also undisputed that WB returned it to BMI and the submittal contained 40 pages related to the Project. R. Doc. 185-6 at pp. 98-145. On December 26, 2019, WB then directed BMI to purchase all necessary equipment—including the Subject Valve that was incorporated into the y-strainer. Id. at pp. 12-17. BMI began installation of the Valve System—including the Subject Valve with a composite cap (the “Subject Cap”) on June 10, 2020. WB’s site superintendent, Donny Phillips, supervised the installation. Phillips, as WB’s Quality Assurance and Quality control representative, was responsible for ensuring that all work complied with the plan specifications, and contract documents. R. Doc. 185-9 at pp. 10-11. The supply, return, valves and VAV

connections were all pressure tested in front of Phillips and no leaks were detected. Id. at pp. 14- 15. Plaintiffs, however, dispute whether BMI performed the test as required under Project specifications. R. Doc. 218-1 at pp. 13-14. GSA marked that the work was completed on June 24, 2020. No party has directed the Court to evidence refuting that, when BMI finished the installation, the Subject Valve was closed and the Subject Cap was secured onto the Subject Valve. Phillips

3 accepted BMI’s work on June 24, 2020, as “necessarily being completed.”1 Phillips testified that he evaluated all valves and ensured the work was in conformity with the Project’s specifications. R. Doc. 185-9 at pp. 22-25. He did not identify any leaks. Phillips also testified that: (a) he knew the Subject Cap was properly attached to the Subject Valve, (b) the Subject Cap was a composite

cap, and (c) composite caps are routinely used on drain valves. Id. at p. 64. From June 10, 2020, to August 7, 2020, it is undisputed that multiple other entities performed work within inches to feet of the Subject Valve. See, e.g., R. Doc. 185-9 at pp. 31 (testifying to some work that was performed within inches of the Subject Valve). On August 7, 2020, Siemens employee Robert Sparks performed work in the tenth-floor ceiling on a different piece of equipment that was located about three feet away from the Subject Valve. The record testimony indicates that the other entities, mostly, performed their work closer to the Subject Valve than Sparks’s work. See, e.g., R. Doc. 185-9 at pp. 31, 35, 40. Phillips was present during Sparks’s work. Id. at pp. 67-69. Sparks testified that he did not touch the Subject Valve, because his work did not require him to have any contact with it, and that he saw no water discharge. R. Doc. 185-

10 at pp. 19-20. Sparks also worked on the other side of the light fixture and at a different angle than the Subject Valve. Expert testimony shows that Sparks could not have physically reached the

1 Plaintiffs assert that WB did not accept Subcontractors work as complete but rather only suggested it was “necessarily [] complete” or “substantially complete prior to the Incident.” However, these assertions are irrelevant because Plaintiffs do not point the Court to any evidence that Subcontractors had any more work to do for the valve system. Rather the alleged uncomplete work belonged to WB, as they had “doors to replace, paint to complete, and had not even developed a punch list.” See R. Doc. 218-1 at p. 19. 4 Subject Valve from his location, let alone opened the Subject Valve.2 R. Doc. 185-17. Phillips also testified that he did not see Sparks open or touch the Subject Valve or Subject Cap but that “anyone” could have opened them. R. Doc. 185-9 at pp. 73-74. He also testified that he did not see any leaks or discharges and that Sparks was working on the other side of the light fixture away

from the Subject Valve. Id. From August 7th onward until the leak, neither BMI nor Siemens did any work in the tenth-floor ceiling. Phillips, however, worked on the tenth floor every day the following week of August 10-August 14. His work required him to enter the tenth floor twice a day. Id. at pp. 47-49. On August 16, 2020, WB received a call from building security about water coming from the tenth floor. When Phillips reported to the site, he found pressured water jetting from the Subject Valve (“the Incident”). Phillips found (a) the Subject Valve was fully open, (b) the Subject Cap removed from the Subject Valve, and (c) water leaking from the Subject Valve. R. Doc. 1, ¶ 34; R. Doc. 185-9 at p. 60-61.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Little v. Liquid Air Corp.
37 F.3d 1069 (Fifth Circuit, 1994)
Martinez v. Bally's Louisiana, Inc.
244 F.3d 474 (Fifth Circuit, 2001)
Daubert v. Merrell Dow Pharmaceuticals, Inc.
509 U.S. 579 (Supreme Court, 1993)
L & a CONTRACTING v. Ram Indus. Coatings, Inc.
762 So. 2d 1223 (Louisiana Court of Appeal, 2000)
LeBlanc v. Gibbens Pools, Inc.
447 So. 2d 1195 (Louisiana Court of Appeal, 1984)
Roberts v. Benoit
605 So. 2d 1032 (Supreme Court of Louisiana, 1992)
Lemann v. Essen Lane Daiquiris, Inc.
923 So. 2d 627 (Supreme Court of Louisiana, 2006)
IberiaBank v. Darryl Broussard
907 F.3d 826 (Fifth Circuit, 2018)
Michael Germain v. US Bank National Association, e
920 F.3d 269 (Fifth Circuit, 2019)
Robin v. Hebert
157 So. 3d 63 (Louisiana Court of Appeal, 2013)
Kinch v. Our Lady of Lourdes Regional Medical Center
181 So. 3d 900 (Louisiana Court of Appeal, 2015)
Favrot v. Favrot
68 So. 3d 1099 (Louisiana Court of Appeal, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Charter Oak Fire Insurance Company v. Bremermann Mechanical, Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/charter-oak-fire-insurance-company-v-bremermann-mechanical-inc-laed-2025.