CHARLESTON NAT. BANK OF CHARLESTON v. Sims

70 S.E.2d 809
CourtWest Virginia Supreme Court
DecidedMay 27, 1952
Docket10468
StatusPublished
Cited by6 cases

This text of 70 S.E.2d 809 (CHARLESTON NAT. BANK OF CHARLESTON v. Sims) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CHARLESTON NAT. BANK OF CHARLESTON v. Sims, 70 S.E.2d 809 (W. Va. 1952).

Opinion

70 S.E.2d 809 (1952)

CHARLESTON NAT. BANK OF CHARLESTON
v.
SIMS, Auditor.

No. 10468.

Supreme Court of Appeals of West Virginia.

Submitted April 8, 1952.
Decided May 27, 1952.

*810 Philip H. Hill, Chas. Ritchie, Charleston, for relator.

Chauncey Browning, Atty. Gen., W. Bryan Spillers, Asst. Atty. Gen., for respondent.

LOVINS, Judge.

By this original proceeding, the Charleston National Bank, executor and trustee of the estate of B. E. Fisher, deceased, relator, seeks a writ of mandamus to compel Edgar B. Sims, State Auditor, respondent, to pay the claim of B. E. Fisher, deceased, against the State Board of Control, in the amount of $2,759.43, the aggregate of an alleged balance due for work performed by decedent under contract and compensation for additional services performed and materials furnished. An award has been heretofore recommended by the State Court of Claims, after a hearing held during the lifetime of decedent. The above amount of $2,759.43 was appropriated by the Legislature for payment of the claim, Chapter 8, Title 2, Section 4, Acts of the Legislature, Regular Session, 1951, and the claim was declared to be a moral obligation of the State, Chapter 28, idem.

The respondent has refused to pay the requisition of the State Board of Control, hereinafter referred to as "board", contending that such payment would be a gift of public funds in contravention of Article X, Section 6 of the State Constitution. He bases that contention on the grounds that decedent failed to complete his performance of the contract within the time specified; that there was an incomplete and faulty performance by him; that payment of a substantial portion of the contract price, made prior to the above award, adequately compensated decedent; and that the State has suffered a loss of $1,535.75, caused by the alleged breach and the necessity of completing the work contemplated by the contract.

The proceeding is considered here upon the petition, the answer of respondent, and a record of the hearing held by the Court of Claims. A stipulation of the parties has made a transcript of the evidence taken at that hearing a part of the record in the present proceeding.

On October 31, 1947, relator's decedent was engaged by the board to move six buildings from Point Pleasant, West Virginia, to Lakin, West Virginia, the site of Lakin State Hospital. A written contract was entered into, in the form of a letter from decedent to the board, wherein the decedent agreed to move the buildings for the sum of $12,434.25. Work was to commence *811 on November 5, 1947, and was to be completed "on or by November 30, 1947. Unless the required materials cannot be purchased immediately." The decedent undertook to "move and place building on foundation with concrete floors similar to floors at present location. Install plaster board on exterior walls and ceilings, paint inside and outside two coats. Sewer, water, steam and electricity [sic] lines will be run to inside of buildings and connected to service all existing fixtures. Will change door openings into windows, replacing either windows and doors as required." The board agreed to furnish decedent with "as many as twelve prison laborers to dig ditches, footers, ect., if needed."

The work was commenced immediately and within thirty days the buildings had been moved to the site at Lakin. Thereafter, work slowed to a virtual standstill and was far from finished on November 30, 1947, the date specified for completion. This period of inactivity extended through the following winter into the spring of 1948, and was attributed by decedent and his witnesses to bad weather, inability to obtain materials, and the failure of the board to furnish prison labor as required by the contract. Such testimony is refuted by the board's construction engineer, who stated that the weather was good until late February, 1948, and that he had found that on similar work undertaken by the board in the same area, during the same period, the weather was no obstacle to expeditious performance and there was no serious shortage of materials. The same witness further testified that prison laborers had been furnished decedent for a period of three weeks, but that such laborers had been withdrawn after the work to be done by them under the provisions of the contract had been completed, and after decedent had attempted to use them for other tasks. Witnesses for the board contended that at least part of the delay was caused by the absence of decedent in Florida during the winter months, from December 10, 1947, to March 13, 1948. The decedent testified that he had left the work in charge of his foreman, who had authority to finish the project.

Decedent's witnesses testified that the work was completed in August, 1948, with the exception of the installation and painting of fifteen windows. Shortly thereafter, at the suggestion of the board, a statement was rendered by the decedent in the amount of $10,000, which was approximately eighty percent of the contract price. A witness for the board testified that it was the policy of the board in such projects to pay that percentage upon apparent completion of the work and the balance after inspection by the board. Decedent was paid $10,000.

After an inspection of the work, the board notified decedent that it considered the contract breached by him, and that he had been adequately compensated for work performed.

Decedent's claim is for the balance of the contract price, $2,434.25, and compensation for extra services and materials, amounting to $1,075.18. Decedent asserted that he had expended $250 to complete ditch digging which the prison laborers were supposed to have done; that he had spent $500 for fill work in order to make possible the pouring of concrete for floors; and that he had performed some additional electrical work at the request of an employee of the Lakin hospital, for which he was entitled to $93.30. He also claimed payment for windows and window frames which he supplied in the amount of $231.88.

The board contends that decedent was not entitled to the additional compensation which he claims for extra services and materials; that all necessary digging of ditches and footers was done by prison labor; that the fill work done by decedent was within his commitments under the contract; that he was likewise obligated under the express contract to supply and install windows and window frames; and that the extra electrical service was not authorized.

An inspection of the work after decedent's alleged completion showed that the plumbing and electrical work, and the materials used therein, were defective. Steam pipes were laid without expansion joints and without return lines, and the outlets were placed without regard to future use of the buildings. Wiring was run only to *812 the outside of the buildings and not connected with the internal fixtures. Painting, inside and out, was unsatisfactory. To remedy those defects, it was necessary for the board to expend an additional $3,970.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
70 S.E.2d 809, Counsel Stack Legal Research, https://law.counselstack.com/opinion/charleston-nat-bank-of-charleston-v-sims-wva-1952.