Charles R. Monroe & Co. v. Hannan

18 D.C. 197
CourtDistrict of Columbia Court of Appeals
DecidedApril 8, 1889
DocketNo. 11,172
StatusPublished
Cited by1 cases

This text of 18 D.C. 197 (Charles R. Monroe & Co. v. Hannan) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Charles R. Monroe & Co. v. Hannan, 18 D.C. 197 (D.C. 1889).

Opinion

Mr. Justice Hagner

delivered the opinion of the Court:

This bill was filed by C. R. Monroe & Co. to enforce a mechanic’s lien against Edward J. Hannan. Hannan, the proprietor of sundry lots, in February, 1888, entered into a contract with Goodwin, under which the latter undertook to build eleven houses on these lots for $13,683. In the [200]*200same month Ward & Mockabee made an offer to Goodwin to do the brick-work under his contract on the buildings, .in these words:

“Mr. Goodwin: We will agree to furnish material and to build and complete the brick-work on eleven houses on the corner of Tenth and G streets southeast, according to plans and specifications, for $4,481. Ward & Mockabee.”

Goodwin not being acquainted with these parties, required them to execute a bond to secure the owner; and on the 15th of February Ward & Mockabee entered into a bond with Monroe, one of the plaintiffs, as their surety, with this condition : “Whereas, the said Ward & Mockabee, on the 15th day of February, 1888, have agreed to build all the brick-work on eleven houses on the corner of Tenth and G streets southeast, in Washington, D. C., for the sum of $4,481 in a complete and workmanlike manner: Now, if the said Ward & Mockabee shall well and truly keep and .perform all and each of the covenants herein contained, then this obligation to be null and void, otherwise to be and remain in full force, effect, and virtue in law.”

The buildings were commenced, and the work proceeded until early in April, when some differences about payment occurring between Hannan and Ward & Mockabee, the latter, according to Hannan’s statement, declared they had abandoned the job and proceeded to tear down the scaffolding and throw down the ladders. Hannan appeared on the ground and asked for an explanation of their conduct; whereupon Ward declared they did not intend to do another particle of work there, and he was actually engaged in throwing down the poles, etc., when Hannan interfered and Ward was then put off the buildings.

Hannan further testified that he went at once and informed Monroe that Ward & Mockabee had thrown up the contract, and called upon him as surety on the bond to complete the buildings, and declared that in default he would hold him on the bond.

[201]*201Monroe & Co. had previously made a subcontract with Ward & Mockabee to supply all'the brick which were to be placed in the buildings, and had furnished a considerable amount up to that time. After Hannan’s visit Monroe went to the buildings and assumed charge of them, and placed O’Neal, who had been the foreman of Ward & Mockabee, in control of the work. The houses were finished in due course of time; payments for bricks being made to Monroe during the progress of the work, of considerable amounts by Goodwin, and also by Hannan.

Many of these allegations of Hannan are controverted by the plaintiffs. They deny that they voluntarily abandoned the work, but insist that Hannan wrongfully discharged them. They also insist that Monroe completed the work under a special employment "by Hannan, after Ward & Mockabee left the buildings, and not in his character as surety on the bond. There is a corisiderable mass of testimony on these points, but we have no hesitation in saying that the weight of the evidence is decidedly in support of the statement of Hannan upon each of the controverted points. After the work was completed the complainants made out their bill for $1,184.66 as the balance due them, after giving the proper credits, with the heading, “Ward & Mockabee to C. It. Monroe & Co., Dr.and Monroe & Co. brought suit upon the account and recovered a judgment against Ward & Mockabee for this amount. Hannan al-leged in his answer that he had paid all of the $4,481, stipulated to be paid for all the brick-work, excepting the sum of $200. Afterwards he said that on a recast of the account it appeared he owed but $83, and that amount he then deposited in court. At a later period, after he and Goodwin had re-examined the accounts, it was testified that only $53 was due. But it is plainly proved that Hannan has paid all of the $4,481 except a small sum, and that no such amount as $1,184 remains unpaid by him on the contract with Ward & Mockabee.

[202]*202If Hannan were decreed to pay the complainant’s claim, it would not be because he has not paid all he contracted to pay, and the full value of the work, but because the claimants have secured a legal advantage by force of the statute that would compel him to pay again a part of what he has once paid.

The bill presents the important question, whether the subcontractors under subcontractors have the right to invoke the provisions of the Act of 1884, which gives a lien, upon the property of the house-owner to the contractor, subcontractors, materialman, journeymen, and laborers, for work done and materials furnished.

It is one that concerns a large class of people in this community, and its proper decision is a matter of general interest. No such claim could have been entertained in this District prior to the passage of the Act of 1884; although laws to secure mechanics’ liens have been in operation here for a longer time perhaps than in other jurisdiction.

Mr. Sargent in his work on Mechanics’ Liens, claims that the earliest legislation in this country or in England securing a lien to mechanics, was the Pennsylvania law of 1806. But the Maryland Act of 1791, Ch. 45, designed to apply to the future Federal City, in the Territory of Columbia, as it was then called, allowed a lien for work on houses in Washington to be performed under a written contract with the owner, by bricklayers, carpenters, joiners, or other .workingmen, fifteen years .before the Pennsylvania law. But that act only protected those who had made written contracts directly with the .land-owner.

In 1833 Congress passed a law which was almost identi* cal in terms with the Pennsylvania Acts of 1806 and 1808. But those acts were uniformly construed by the courts of that State as not embracing the case of a subcontractor; and the Act of 1833 could admit of no wider construction. Indeed it received a still narrower interpretation by the Supreme Court in the case of Winder vs. Caldwell, in 14 How., [203]*203434. , The act enumerated the classes of persons who should have the benefit of the lien; and although in one part of the act the word “ contractor ” is mentioned, yet as this word did not appear in that enumeration,-it was held that a contractor was excluded from its benefits.

Then came the Act of 1857, which constituted the whole of Chap. 20 of the Revised Statutes relating to the District of Columbia, excepting the last two sections, which are taken from the Act of 1870. Under neither of these acts had the subcontractor any lien. By the Act,of 1870, the word “subcontractor ” was introduced for the first time into our law; but that act only gave to the subcontractor the right to claim from the owner, after due notice, the value of services rendered ; but gave no lien against the property.

The Act of 1884, Ch. 143, for the first time gave a lien to the subcontractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wilmington Trust FSB v. A1 Concrete Cutting & Demolition, LLC
289 P.3d 1199 (Nevada Supreme Court, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
18 D.C. 197, Counsel Stack Legal Research, https://law.counselstack.com/opinion/charles-r-monroe-co-v-hannan-dc-1889.