Charleroi Lumber Co. v. Bentleyville Borough School District

6 A.2d 88, 334 Pa. 424, 1939 Pa. LEXIS 656
CourtSupreme Court of Pennsylvania
DecidedMarch 27, 1939
DocketAppeal, 71
StatusPublished
Cited by20 cases

This text of 6 A.2d 88 (Charleroi Lumber Co. v. Bentleyville Borough School District) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Charleroi Lumber Co. v. Bentleyville Borough School District, 6 A.2d 88, 334 Pa. 424, 1939 Pa. LEXIS 656 (Pa. 1939).

Opinion

Opinion by

Mr. Justice Stern,

This appeal is by a contractor corporation which was defeated in the court below in an attempt to recover from a school district for labor and material furnished in the erection of a public school building. Two defenses were presented, the one that the cost of the building exceeded the amount authorized by the vote of the electors, the other that plaintiff’s contract carried the debt of the district beyond its constitutional limit. The court, upholding the adjudication of the trial judge sitting without a jury, decided — in our opinion properly— that both of these defenses had been sustained. As, however, either one is conclusive against plaintiff’s cause of action, the present discussion will be limited to the first.

In 1920, the main school building having been destroyed by fire, it became necessary to erect a new structure. Accordingly the electors were called upon to vote upon a proposed creation of indebtedness in the sum of $85,000 “for the purpose of erecting, completing and equipping a new school building in the School District of the Borough of Bentleyville.” A majority of the votes being favorable, bonds were issued from the sale of which $86,759.50 was realized. The board of school directors employed an architect who prepared plans and specifications which the board approved, and due advertising was had. When the bids were examined they were found to be considerably in excess of $85,000 — as high as $120,000 or $125,000 — and it was obvious, or should have been, that the project could not proceed as planned, there being insufficient money available for the purpose and the proposed cost going far beyond the debt limit.

As the result of consultations, conferences, and advice from various quarters as to how to meet the situation, a device was adopted whereby the original plans for the building were retained but the specifications were changed by omitting plumbing and electric wiring, as *427 well as plastering and hardware for the first and second floors; the exterior walls, the roof, and rough interior floors, stairs and partitions, were left undisturbed. Contractors were requested to bid again on the revised specifications, and the main contract was. awarded to plaintiff on the basis of a net cost of $81,631; at the same time a heating contract in the sum of $15,000 was awarded to another contractor. Of course it would have been impossible to use such a skeletonized building other than for at most a temporary emergency period, the president of plaintiff company himself testifying that he understood that the purpose in changing the specifications was to put up “a shell of a building.” Carrying out the new scheme, the school board, a few months after the execution of the contract with plaintiff, awarded plumbing and wiring contracts, and accepted a proposal of plaintiff “to furnish all labor and material necessary to complete the first and second stories of the Bentleyville school building according to plans and specifications of H. W. Altman, architect, for the sum of $27,900,” thus covering, in substance, the items which had been excluded from the original contract. Without any competitive bidding or advertising, plaintiff then furnished this and some other additional work and material at a total price of $30,475.30 (of which $1,866.07 is admitted by defendant to have been for legitimate extras). The entire cost of the building when completed, including architect’s fees, heating, wiring and plumbing, was close to $136,000, and with land and equipment nearly $147,000. Defendant made various payments to plaintiff on account, aggregating $78,794.82, and paid interest on the balance of its claim down to 1931 (at which time the new building met the fate of the old one and was destroyed by fire), leaving a balance of $34,329.08, to recover which, with interest since 1931, the present suit was brought.

Even a guileless person could scarcely fail to understand and properly appraise the maneuver attempted to *428 evade the constitution and laws of the Commonwealth. Its failure was predetermined by the decision in the case of Raff v. Philadelphia, 256 Pa. 312. There the electors voted for an increase of the indebtedness of the City of Philadelphia in the sum of $9,750,000, tvliich embraced, inter alia, an item of $1,500,000 “for the erection of a convention hall.” An architect was employed, plans were prepared, an estimate of $2,225,000 was submitted, and the city authorities were about to advertise for bids and proceed for its construction at that approximate cost, when an injunction was issued by this court, in the exercise of its original jurisdiction, preventing them from entering into contracts for the erection in whole or in part of a convention hall the total cost of which would exceed the amount which the electors had authorized to be borrowed therefor. The court pointed out that the public notice of the election contained, in accordance with statutory requirement, a statement of the purpose and amount of the proposed increase, and that this clause was to enable the voter to act intelligently upon the question submitted to him. The court said (p. 317) : “They [the voters] have a right to insist that what the city authorities so clearly gave them to understand was to be the cost of the hall when they, cast their ballots in favor of the increase of the city indebtedness for that purpose, shall not now be ignored by those authorities, for who can say that they would have voted for the increases if they had known the convention hall was to cost hundreds of thousands of dollars more than the sum indicated in the ordinances and in the notices of the elections held in pursuance of them?” In McAnulty v. City of Pittsburgh, 284 Pa. 304, the same principle was applied, the court saying (p. 307) : “It is a matter of no moment that the municipal authorities may have thought, when they submitted to the electors the question of increasing the debt for this improvement, that the sum specified would cover the entire expense thereby imposed on the city. *429 When the contracts were made, they knew the $801,000 would he far from sufficient, and they had no right to then provide for an unlawful increase of the debt. The contractors knew this also, and hence have only themselves to blame if they have commenced performance; for the contracts must be declared void in their entirety.” The court further said (p. 309) : “Can the city effectively substitute for the requirements of article IX, section 8 of the Constitution of the State, a statement . . . that an indebtedness which violates this provision will, at some indefinite time in the future, ‘be provided for from the general city funds’? If it can, then a municipality need only submit to its electors whether or not they will authorize an increase of indebtedness of $1,000, or any greater or lesser sum, and add the excess, however great, to its indebtedness, without providing any means for its payment; thus making of the constitutional provision a rope of sand, wholly insufficient to rescue the electors from the financial wreck of the municipality, which was the only purpose of its adoption.”

In Miller & Sons’ Co. v. Mt. Lebanon Township (No. 1), 309 Pa. 216, the voters authorized increases of $225,000 in the indebtedness for the purpose of erecting a townhouse. In pursuance of this authority bonds were issued from the sale of which $238,000 was realized.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

FLINT DILLE v. GEER
E.D. Pennsylvania, 2020
Bucci v. Wachovia Bank, N.A.
591 F. Supp. 2d 773 (E.D. Pennsylvania, 2008)
Chainey v. Street
Third Circuit, 2008
Lichtenstein v. Kidder, Peabody & Co. Inc.
840 F. Supp. 374 (W.D. Pennsylvania, 1993)
J. A. & W. A. Hess, Inc. v. Hazle Township
400 A.2d 1277 (Supreme Court of Pennsylvania, 1979)
Whitehall Township v. Rothrock
9 Pa. D. & C.3d 750 (Lehigh County Court of Common Pleas, 1979)
J. A. & W. A. Hess, Inc. v. Hazle Township
363 A.2d 844 (Commonwealth Court of Pennsylvania, 1976)
School District v. Framlau Corp.
328 A.2d 866 (Commonwealth Court of Pennsylvania, 1974)
Montgomery v. Philadelphia
139 A.2d 347 (Supreme Court of Pennsylvania, 1958)
Carr-Consolidated Biscuit Company v. Moore
125 F. Supp. 423 (M.D. Pennsylvania, 1954)
Carr-Consolidated Biscuit Co. v. Moore
125 F. Supp. 423 (M.D. Pennsylvania, 1954)
Coyle v. Pittsburgh
25 A.2d 707 (Supreme Court of Pennsylvania, 1942)
Innes v. Nanticoke City School District
20 A.2d 225 (Supreme Court of Pennsylvania, 1941)
Commonwealth v. Zang
16 A.2d 741 (Superior Court of Pennsylvania, 1940)
Wilds v. McKeesport City School District
9 A.2d 338 (Supreme Court of Pennsylvania, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
6 A.2d 88, 334 Pa. 424, 1939 Pa. LEXIS 656, Counsel Stack Legal Research, https://law.counselstack.com/opinion/charleroi-lumber-co-v-bentleyville-borough-school-district-pa-1939.