Champlain Parkway Wetland Determination - Decision on Motions

CourtVermont Superior Court
DecidedJune 4, 2019
Docket39-3-18 Vtec
StatusPublished

This text of Champlain Parkway Wetland Determination - Decision on Motions (Champlain Parkway Wetland Determination - Decision on Motions) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Champlain Parkway Wetland Determination - Decision on Motions, (Vt. Ct. App. 2019).

Opinion

STATE OF VERMONT SUPERIOR COURT ENVIRONMENTAL DIVISION Environmental Division Unit Docket No. 39-3-18 Vtec

Champlain Parkway Wetland Determination DECISION ON MOTIONS

The City of Burlington (“City”) seeks the full complement of permits needed for construction of the Champlain Parkway, a proposed two-lane highway with an associated multi- use path (“Project”). The Vermont Agency of Natural Resources (“ANR”) has granted the City permits for the Project’s stormwater discharges and its impacts to a Class II wetland, Wetland H/I.1 In October 2017, Fortieth Burlington, LLC (“Fortieth”), an owner of property near the Project, submitted a complaint to ANR alleging that the Project’s stormwater discharges cause impacts to Wetlands G and Y that require a wetland permit. In the decision that is the subject of this appeal, ANR concluded that no wetland permit was necessary because the City did not propose to “conduct or allow to be conducted an activity” in Wetlands G or Y, or their buffer zones. The Court here considers ANR’s motion for summary judgment, which the City joins, asserting its position that no wetland permit is required for any alleged impacts to Wetlands G and Y from the Project’s stormwater discharges.2 Judith L. Dillon, Esq., appears on behalf of Fortieth. Hannah Smith, Esq., and Randy J. Miller, II, Esq., represent ANR. Brian S. Dunkiel, Esq., and Jonathan T. Rose, Esq., represent the City.

1 As discussed further below, ANR’s decision to approve the renewal of the City’s amended stormwater discharge permit is the subject of a concurrent appeal pending before this Court. See Champlain Parkway SW Discharge Permit, No. 76-7-18 Vtec. 2 The City joins ANR’s motion and its reply in support of the motion. The City also writes separately to submit additional evidence and comment on certain discrete issues. While this Court largely considers their arguments to be aligned, we note the City’s additional commentary where relevant.

1 Legal Standard A moving party will prevail on summary judgment if there is no genuine dispute of material fact and they are entitled to judgment as a matter of law. V.R.C.P. 56(a), applicable here through V.R.E.C.P. 5(a)(2). A party asserting that a fact cannot be disputed or, conversely, that a fact is genuinely disputed, must support that assertion with admissible evidentiary material. V.R.C.P. 56(c); White v. Quechee Lakes Landowners’ Ass’n, Inc., 170 Vt. 25, 28 (1999). In evaluating factual assertions, we draw all reasonable inferences and resolve all reasonable doubts in the nonmoving party’s favor. Mellin v. Flood Brook Union Sch. Dist., 173 Vt. 202, 212 (2001) (citation omitted). Conclusory statements of fact, or disputes that are not material, do not preclude a decision on summary judgment. Robertson v. Mylan Labs., Inc., 2004 VT 15, ¶ 41, 176 Vt. 356.

Factual Background We recite the following facts for the sole purpose of resolving the pending motions. These are not factual findings, which can only be reached after a trial. Blake v. Nationwide Ins. Co., 2006 VT 48, ¶ 21, 180 Vt. 14 (citing Fritzeen v. Trudell Consulting Eng’rs, Inc., 170 Vt. 632, 633 (2000) (mem.)). 1. Fortieth owns property along Lakeside Avenue in Burlington, Vermont, near the two wetlands at the center of this appeal, Wetlands G and Y. 2. The City proposes construction of the Champlain Parkway Project, a two-lane highway with accompanying recreational, traffic, and stormwater development in Burlington, Vermont. 3. The Project would connect I-189 to Lakeside Avenue, then follow Lakeside Avenue east and Pine Street north to Main Street in Burlington’s City Center District. 4. The Project does not involve any construction in Wetlands G and Y or their buffer zones. 5. Over the past few years, the City has applied for and received a number of environmental and land use permits for the Project.

The City’s Stormwater Discharge Permit 6. On March 23, 2012, the City applied to amend its stormwater permit for the Project’s stormwater discharges. The amendment application requested coverage of additional stormwater discharges from the Project into the Pine Street Barge Canal watershed.

2 7. ANR granted the City the amended permit on October 11, 2012. This decision was not appealed. 8. Under the permit, stormwater from the Project will discharge from three points. At one of these points, called “S/N 003,” stormwater will be treated according to the permit conditions. The stormwater from S/N 003 will then discharge into the Pine Street Barge Canal. 9. Wetlands G and Y are proximal to the Pine Street Barge Canal. 10. Stormwater discharges from the Project will likely flow into Wetlands G and Y to some extent.3 11. ANR has not formally assessed whether Wetlands G or Y are significant, or Class II, wetlands. 12. The Project’s stormwater management plan does not entail any treatment practices, or construction of any stormwater infrastructure, in Wetlands G and Y or their buffers. 13. The City applied for renewal of its stormwater discharge permit on September 15, 2017. 14. ANR issued the renewal on June 19, 2018, and Fortieth appealed that decision to this Court on July 18, 2018. The permit is currently the subject of a separate pending appeal before this Court. See Champlain Parkway SW Discharge Permit, No. 76-7-18 Vtec.

The City’s Wetland Conditional Use Determination 15. The City applied for a wetland Conditional Use Determination (“CUD”) in 2010 for impacts to Wetland H/I and its buffer zone. 16. The City’s CUD application contained a map showing Wetland H/I, the surrounding area, and Wetlands G and Y. 17. ANR issued the City the CUD permit on January 14, 2011. No appeal followed. 18. The City requested an extension of the CUD permit in 2015. 19. ANR, this Court, and the Vermont Supreme Court approved the extension. See Champlain Parkway Wetland CU Determination, No. 123-10-16 Vtec (Vt. Super. Ct. Envtl. Div. Apr. 14, 2017) (Durkin, J.); In re Champlain Parkway Wetland Conditional Use Determination, 2018 VT 123.

3 Given the summary judgment standard, for purposes of the present motion we assume that stormwater from the Project will reach Wetlands G and Y. Because the parties dispute whether stormwater impacts to a wetland that derive from development outside of the wetland require a wetland permit, the question of whether or to what extent the Project’s stormwater impacts Wetlands G and Y is not material to the ultimate legal question before us.

3 20. While Wetlands G and Y were considered tangentially in the CUD determination, they are not addressed in the CUD permit and did not play a part in the extension decision.

The Present Appeal 21. On October 23, 2017, Fortieth sent a letter to ANR requesting that ANR require the City to obtain a wetland permit to cover alleged impacts to Wetlands G and Y from the Project’s stormwater discharges, or prohibit those discharges. Fortieth’s letter included a memorandum drafted by Vanasse Hangen Brustlin, Inc., entitled “Champlain Parkway – Wetland Impact Review.” 22. ANR responded to Fortieth’s request on February 27, 2018. ANR determined that a wetland permit was not required for the City’s stormwater discharges because the City did not propose to conduct any activities in Wetlands G or Y as part of the Project. 23. Fortieth appealed ANR’s decision to this Court on March 29, 2018.

Discussion ANR and the City move to dismiss all nine Questions in Fortieth’s Statement of Questions. Questions 1, 2, 3, 6, 7, and 8 are all variations on the question of whether the Project’s potential stormwater impacts to Wetlands G and Y require a wetland permit. ANR and the City assert that no wetland permit is necessary because ANR’s wetland permitting jurisdiction is only triggered by development, construction, or other physical activities within the boundaries of a wetland or wetland buffer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Ambassador Ins. Co., Inc.
2008 VT 105 (Supreme Court of Vermont, 2008)
Mollica v. Division of Property Valuation & Review
2008 VT 60 (Supreme Court of Vermont, 2008)
In Re Woodford Packers, Inc.
2003 VT 60 (Supreme Court of Vermont, 2003)
Bacon v. Lascelles
678 A.2d 902 (Supreme Court of Vermont, 1996)
Trombley v. Bellows Falls Union High School District No. 27
624 A.2d 857 (Supreme Court of Vermont, 1993)
Levine v. Wyeth
2006 VT 107 (Supreme Court of Vermont, 2008)
Town of Killington v. State
776 A.2d 395 (Supreme Court of Vermont, 2001)
Robertson v. Mylan Laboratories, Inc.
2004 VT 15 (Supreme Court of Vermont, 2004)
Fritzeen v. Trudell Consulting Engineers, Inc.
751 A.2d 293 (Supreme Court of Vermont, 2000)
Blake v. Nationwide Insurance
2006 VT 48 (Supreme Court of Vermont, 2006)
Mellin v. Flood Brook Union School District
790 A.2d 408 (Supreme Court of Vermont, 2001)
In Re Vermont Verde Antique International, Inc.
811 A.2d 181 (Supreme Court of Vermont, 2002)
Jacobus v. Department of PATH
2004 VT 70 (Supreme Court of Vermont, 2004)
In Re Appeal of Lunde
688 A.2d 1312 (Supreme Court of Vermont, 1997)
State v. Pitts
2009 VT 51 (Supreme Court of Vermont, 2009)
In Re Appeals of ANR Permits in Lowell Mountain Wind Project
2014 VT 50 (Supreme Court of Vermont, 2014)
Agency of Natural Resources v. Hugh McGee & Eileen McGee
2016 VT 90 (Supreme Court of Vermont, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Champlain Parkway Wetland Determination - Decision on Motions, Counsel Stack Legal Research, https://law.counselstack.com/opinion/champlain-parkway-wetland-determination-decision-on-motions-vtsuperct-2019.