Champlain College, Inc. 304-306 Maple St. College Project

Vermont Superior Court·Decided March 20, 2007·No. 145-07-05 Vtec·Published

Opinion

STATE OF VERMONT

ENVIRONMENTAL COURT

}

In re Champlain College, Inc. } 304-306 Maple Street Dormitory Project } Docket No. 145-7-05 Vtec (Appeal of Baker, et al.) } }

Decision and Order

Appellants Faye Baker, Mary Ellen Manock, Jerrold Manock, Linda Jones, Bruce L.

Hewitt, Robert Leidy, Anne Geroski, Michael Rooney, Norman Williams, Susan Dorn and Carol Hewitt appealed from a decision of the Development Review Board (DRB) of the City of Burlington, approving the application of Champlain College to renovate an existing building and construct a new building at 304-306 Maple Street for student housing consisting of a total of 49 student rooms plus a head resident’s apartment. Appellants are represented by Todd D. Schlossberg, Esq.; Appellee-Applicant Champlain College, Inc. (the College) is represented by Mark G. Hall, Esq.; and the City of Burlington is represented by Kimberlee J. Sturtevant, Esq.

An evidentiary hearing was held in this matter before Merideth Wright, Environmental Judge, who took a site visit after the conclusion of the hearing, alone by agreement of the parties.

Appellants are a group of eleven Burlington residents asserting standing pursuant to 24 V.S.A. §4465(b)(4). Applicant Champlain College also filed a cross-appeal; however, the City and Champlain College reached agreement on the cross-appeal issues and proposed that the Court accept their agreed revisions to the DRB decision in resolution of the cross-appeal issues. Appellants were given the opportunity to object to the City’s and Champlain College’s proposed settlement of the cross-appeal issues in their post-trial

memoranda. To the extent that the settlement of the cross-appeal addresses issues not raised in Questions 1, 4, 5, 6, 7, and 9 of the Appellants’ Amended Statement of Questions, it is hereby accepted by the Court as resolving the issues in the cross-appeal. Otherwise, its issues are addressed and resolved in this decision.

Appellants’ Amended Statement of Questions raised ten issues in this appeal, four of which were withdrawn on the record at trial: Question 2 (addressing lot coverage), Question 3 (addressing the proposed height of the project buildings), Question 8 (addressing stormwater) and Question 10 (addressing the impact of the project on the present or future growth patterns of the City). After the evidentiary hearing the parties were given the opportunity to submit written memoranda and requests for findings. Upon consideration of the evidence as illustrated by the site visit, and of the written memoranda and requests for findings filed by the parties, the Court finds and concludes as follows.

The 4.6-acre property that is the subject of this application is owned by Champlain College, Inc.; it was created by the merger of seven smaller parcels. The project property is located in an underlying University Campus (UC) zoning district, and within the Champlain College Core Campus Overlay (CCO) zoning district of the City of Burlington. The property as a whole has frontage on Maple Street, South Willard Street, and Main Street, but due to its topography has access only to Maple Street and South Willard Street. The property as a whole now contains nine existing college buildings and their associated parking lots. The property as a whole adjoins City-owned property containing the Edmunds Elementary School and Middle School, its playing fields, its parking lot and a driveway and walkway to its parking lot from Maple Street.

The portion of the property that is proposed for the present development had the address of 304 Maple Street and contains a 3,600-square-foot residential building known as the Levi Smith house. Appellee-Applicant Champlain College has applied to renovate

the existing building (304 Maple Street) and to construct a new 18,000 square foot building (306 Maple Street) for student housing at the project property. The project proposes 49 new student rooms to house 94 students: 39 rooms in the new building and ten in the renovated building, with shared bathroom facilities for the student rooms, plus a self- contained apartment with kitchen and bathroom facilities in the new building for the head resident.

The 4.6-acre parcel already contains a number of residential uses. The building at 308 Maple Street contains four student apartments. Whiting Hall and McDonald Hall are in use as student dormitories. Whiting Hall contains 17 rooms housing 39 students. McDonald Hall contains 18 rooms housing 39 students, with shared bathroom facilities for the student rooms, as well as one self-contained apartment for the head resident, with kitchen facilities and bathroom, which is proposed to be discontinued when or before the proposed project is built. Meal service for the students is provided in a different building.

The Champlain College Core Campus Overlay is part of the larger institutional University Campus district, which also includes the University of Vermont and the Medical Center campuses.

Over the past ten years the demographic distribution of the student body at Champlain College has changed from a two-year, Vermont-based commuting student population, to a more traditional four-year college, having a substantial out-of-state resident student population, on the one hand, and an increase in the numbers of so-called “distance learning” or on-line students, taking courses by computer from remote locations. In keeping with the change in demographics, the demand for on-campus residential housing has risen.

The actual numbers of students physically attending Champlain College has remained fairly constant since 1988, ranging up and down from slightly under 1,900 students to slightly over 2,000 students. Over that time frame there has been an increase

in full-time (and hence residential) students and a decrease in part-time (and hence commuter) students. The majority of part-time students have tended to be night students, that is, they do not drive to campus during peak daytime commuting hours. There has also been an increase in on-line students since the on-line program began in 1993, which by definition does not generally bring students to the campus. Similarly, Champlain College is moving towards a larger proportion of full-time faculty who would be on-campus during the whole work day, as compared with adjunct faculty who commute to and from the campus more frequently during the day. However, the growth in the number of full-time employees is small.

Champlain College presented evidence that its physical limitations related to classroom space and to the dining facility make it unlikely that the College will expand beyond the 1,800-to-2,000 on-campus student population contemplated in the College’s current Strategic Plan. Under that plan it is shifting its administrative offices out of the Core Campus (Hill) area and plans in the longer term to develop housing for juniors and seniors in the central business district of Burlington, with shuttle bus service to the College’s Core Campus area.

Question 1 of the Statement of Questions: Whether the proposed project complies with the density requirements of the Zoning Ordinance The parties dispute several factors in the applicable methodology for determining density for a dormitory1 project in the Champlain College Core Campus Overlay zoning district.

If the plain meaning of the Zoning Ordinance does not provide sufficient guidance,

1 While in the present case the Court’s task is to determine whether the present proposal meets the density requirements of the Ordinance as it now exists, it is to be hoped that the City will consider clarifying the density-determination methodology applicable to dormitories when considering any amendments to the Zoning Ordinance.

Free access — add to your briefcase to read the full text and ask questions with AI

Champlain College, Inc. 304-306 Maple St. College Project, (Vt. Ct. App. 2007).

Champlain College, Inc. 304-306 Maple St. College Project (Champlain College, Inc. 304-306 Maple St. College Project) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In Re Stowe Club Highlands
668 A.2d 1271 (Supreme Court of Vermont, 1995)
In Re Appeal of Casella Waste Management, Inc.
2003 VT 49 (Supreme Court of Vermont, 2003)
In Re Dunnett
776 A.2d 406 (Supreme Court of Vermont, 2001)
Stevenson v. Capital Fire Mutual Aid System, Inc.
661 A.2d 86 (Supreme Court of Vermont, 1995)
In re Appeal of Korbet
2005 VT 7 (Supreme Court of Vermont, 2005)