Chamberlain, L.l.c. Vs. City Of Ames, Iowa And Ames Board Of Appeals

Supreme Court of Iowa·Decided November 21, 2008·No. 06–1487·Published

Opinion

IN THE SUPREME COURT OF IOWA No. 06–1487

Filed November 21, 2008

CHAMBERLAIN, L.L.C., Appellant, vs.

CITY OF AMES, IOWA and AMES BOARD OF APPEALS,

Appellees.

On review from the Iowa Court of Appeals.

Appeal from the Iowa District Court for Story County, Dale E.

Ruigh, Judge.

Appellant challenges summary judgment dismissal of its suit challenging the denial of an occupancy permit. DECISION OF COURT OF APPEALS AND JUDGMENT OF DISTRICT COURT AFFIRMED.

John F. Lorentzen and John T. Clendenin of Nyemaster, Goode, West, Hansell & O’Brien, Des Moines, for appellant.

William A. Wickett and Jason W. Miller of Patterson Law Firm, L.L.P., Des Moines, and Jason C. Palmer and Andrew C. Johnson of Bradshaw, Fowler, Proctor & Fairgrave, P.C., Des Moines, for appellees.

STREIT, Justice.

An Ames developer planned to build an apartment complex with loft space that could be used for sleeping or storage. Uncertain whether the lofts were permissible under the Ames Municipal Code, the developer requested an interpretation of the code from the city’s building official, who concluded the lofts were permissible. When the building was

completed, the city denied the developer’s application for a certificate of occupancy because it found the lofts violated the ceiling height

requirements for habitable space. The developer appealed to the city’s board of appeals which upheld the denial of certification. The developer then filed actions in the district court on this issue as well as asserting recovery on the basis of promissory estoppel, equitable estoppel, and vested rights. The district court and court of appeals rejected all claims on summary judgment dismissal. On further review, the developer maintains issue preclusion bars the city from essentially withdrawing the building official’s interpretation of the code. Because the interpretation was not a final decision, it is not entitled to preclusive effect. Further, because the building official’s interpretation was contrary to the building

code, the developer did not acquire vested rights in the interpretation. We affirm the decision of the court of appeals and the judgment of the

district court.

I. Facts and Prior Proceedings.

The owners of Chamberlain, L.L.C. planned to build a four-story mixed-use complex near the Iowa State campus. The first floor would contain retail space, and the upper floors would contain apartment units. The design for some of the apartments included a loft or shelf area that could be used as sleeping or storage space. The lofts provided 184 square feet of surface area, forty-five inches from the ceiling, and

were accessible by stair-ladders. The lofts had electrical outlets, data

ports for internet access, lighting (and light switches), and carpeting. Since Chamberlain was uncertain whether the loft-shelf areas would

comply with the city’s building code requirements, it sought approval from the Ames building official before proceeding with the project.

In August or September 2003, two Chamberlain representatives and the company’s architectural consultant met with the Ames building official and the Ames fire inspector. While the parties dispute whether actual design drawings with dimensions were reviewed during the meeting, all agree the topic of the meeting centered on whether the loft areas would be acceptable under the building and fire codes. The fire inspector expressed concern that additional protections would be needed

if the spaces would be used for sleeping. The building official then sought input on the design at a staff meeting of city building inspectors.

The building official called Chamberlain and indicated the lofts were permissible so long as Chamberlain installed smoke detectors and sprinklers above and below the lofts. The building official interpreted the

loft areas to be extensions of other code-compliant rooms, thus excluded from ceiling height restrictions. He believed this interpretation was consistent with the building code’s intent and purpose. Chamberlain

continued to develop the concept, and the city issued a building permit in January 2004 after reviewing Chamberlain’s phased project plans.

Chamberlain built the structure and secured tenants for the units.

When the building was nearly complete, the Ames fire chief/acting building official1 stated in a letter that the loft areas did “not meet minimum height requirements for habitable space” and a certificate of

1The building official who provided Chamberlain with his interpretation of the code no longer worked for the city.

occupancy would not be issued unless significant modifications were

made to the apartments. A memo from the fire chief to the city manager stated inspectors began noticing that the loft areas would be treated as

living space in May 2004, and some tenants and parents of tenants had complained to the city due to concerns about the reduced height in the loft areas.

Chamberlain appealed the fire chief’s determination to the city’s board of appeals. The board found the fire chief’s interpretation “not unreasonable” and determined the certificate of occupancy was properly withheld. The city issued a certificate of occupancy only after Chamberlain barricaded the loft areas to prevent their use.

Chamberlain filed two actions in district court. First, it filed a petition for writ of certiorari seeking a declaration that Chamberlain was illegally denied a certificate of occupancy when it justifiably relied on a valid code interpretation made by an authorized building official. A second petition was filed in equity, contending the city was prevented from applying a new interpretation of the building code through the doctrines of equitable estoppel, vested rights, or promissory estoppel.

The cases were consolidated, and both parties moved for summary judgment.2 The district court held there were no false representations or

exceptional circumstances to support an equitable estoppel claim, and Chamberlain’s promissory estoppel claim failed because there was no “clear and definite promise” to enforce the interpretation as to the lofts. Further, the court determined Chamberlain did not have vested rights in the building permit because the building did not comply with the building code. Lastly, the court rejected Chamberlain’s claim the original

2The district court did not issue a ruling with regard to the petition for writ of certiorari, and therefore, it is not before us.

building official’s determination prevented a new interpretation by the

board of appeals through issue preclusion. Chamberlain appealed each of these conclusions.

We transferred the case to the court of appeals, which affirmed the district court’s decision in its entirety. Chamberlain sought further review, claiming the building official’s initial determination of the building code was an adjudication entitled to preclusive effect. We granted further review.

II. Scope of Review.

A ruling on a motion for summary judgment is reviewed for correction of errors at law. City of Johnston v. Christenson, 718 N.W.2d 290, 296 (Iowa 2006). Summary judgment is properly granted

if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.

Iowa R. Civ. P. 1.981(3). We examine the facts “in the light most favorable to the party opposing the motion for summary judgment.” Richardson v. The Commodore, Inc., 599 N.W.2d 693, 696 (Iowa 1999).

When presented with an application for further review from the court of appeals, we may consider “all of the issues properly preserved and raised in the original briefs.” Bokhoven v. Klinker, 474 N.W.2d 553, 557 (Iowa 1991). “[W]e may review any or all of the issues initially raised on appeal . . . whether or not they are specifically brought to our attention in the applications for further review.” Id.

III. Merits.

Free access — add to your briefcase to read the full text and ask questions with AI

Chamberlain, L.l.c. Vs. City Of Ames, Iowa And Ames Board Of Appeals, (iowa 2008).

Chamberlain, L.l.c. Vs. City Of Ames, Iowa And Ames Board Of Appeals (Chamberlain, L.l.c. Vs. City Of Ames, Iowa And Ames Board Of Appeals) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

City of Johnston v. Christenson
718 N.W.2d 290 (Supreme Court of Iowa, 2006)
B. & H. INVESTMENTS, INC. v. City of Coralville
209 N.W.2d 115 (Supreme Court of Iowa, 1973)
City of Lamoni v. Livingston
392 N.W.2d 506 (Supreme Court of Iowa, 1986)
Hunter v. City of Des Moines
300 N.W.2d 121 (Supreme Court of Iowa, 1981)
Richardson v. Commodore, Inc.
599 N.W.2d 693 (Supreme Court of Iowa, 1999)
City of New Hampton v. Blayne-Martin Corp.
594 N.W.2d 40 (Supreme Court of Iowa, 1999)
Bokhoven v. Klinker
474 N.W.2d 553 (Supreme Court of Iowa, 1991)
Iowa Electric Light & Power Co. v. Lagle
430 N.W.2d 393 (Supreme Court of Iowa, 1988)