CFJ Associates of New York, Inc. v. Hanson Industries
This text of 260 A.D.2d 917 (CFJ Associates of New York, Inc. v. Hanson Industries) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Appeal from an order of the Supreme Court (Coutant, J.), entered January 26, 1998 in Broome County, which, inter alia, denied defendants’ motion for partial summary judgment dismissing the first, second and fourth causes of action of the complaint.
On April 26, 1994, plaintiff contracted with defendant Endicott Johnson Corporation (hereinafter EJ) for the purchase of real property located in Broome County in connection with its plans for the construction of an outlet mall. This dispute centers upon the parties’ rights and obligations under those contractual provisions relating to environmental review and cleanup, and the cost associated therewith, summarized as follows. Within 9Q days of the contract’s execution, EJ was to direct its environmental consultant to provide plaintiff with a “Phase II Site Assessment Report” (hereinafter Phase II report) and cleanup cost estimate, if any. If the cleanup cost estimate was less than $1 million, EJ would be responsible for the total cost even if the cleanup cost ultimately exceeded $1 million. If the cleanup cost estimate exceeded $1 million, EJ had the right to terminate the contract by giving plaintiff written notice within 10 days of its receipt of the estimate. Plaintiff would then have the option to reinstate the contract upon agreeing to assume liability for all cleanup costs in excess of $1 million. In the event that plaintiff disputed the sufficiency of the cleanup plan or estimate, it was required to serve EJ with detailed notice of its objections within 30 days of its receipt thereof.
On March 12, 1996, EJ delivered a Phase II report which, according to plaintiff, made reference to, but did not include, a cleanup cost estimate.
Defendants thereafter moved for partial summary judgment dismissing the causes of action for specific performance and injunctive relief on the ground that plaintiff, by not serving a reinstatement notice within the requisite time period, failed to comply with a condition precedent of the contract and thereby waived its right to specific performance and injunctive relief. Defendants also sought cancellation of the notice of pendency. Plaintiff opposed the motion and cross-moved for leave to amend its complaint to add causes of action for fraudulent misrepresentation, tortious interference with the contract and with prospective contractual relations. Supreme Court denied defendants’ motion in its entirety and granted plaintiffs motion to the extent of authorizing the addition of a cause of action for tortious interference with contractual relations. Defendants appeal.
Supreme Court properly denied defendants’ motion for summary judgment, as there are a number of unresolved factual issues which impact upon the parties’ respective claims. Although defendants insist that plaintiffs failure to serve a reinstatement notice is fatal to the challenged causes of action, as Supreme Court trenchantly observed, acceptance of this argument entails determination of one of the ultimate issues in the action, i.e., whether defendants’ termination of the contract was valid. Plaintiff maintains that EJ waived any right to terminate the contract on the stated basis by failing to provide a Phase II report within 90 days of the execution of the contract or, in any event, by failing to serve a notice of termination within 10 days of its receipt of the cleanup cost estimate on March 11, 1996. Defendants, on the other hand, insist that [919]*919the estimate was not in their possession until February 20, 1997, and that notice of termination was timely served. Clearly, resolution of these factual disputes must precede determination of the parties’ obligations under the contract. Also, contrary to defendants’ assertions, there has been no prior finding that defendants properly terminated the contract, or any court-ordered directive that plaintiff serve a reinstatement notice. Prior orders extended the time within which plaintiff was permitted, but not necessarily required, to file such a notice.
Further, although the contract expressly provided that EJ, as seller of the subject property, “is, and at [c]losing shall be, the sole owner in fee simple of the [pjroperty and shall not have assigned, pledged, leased, transferred or otherwise encumbered its interest therein”, it is uncontroverted that on September 25, 1996, EJ transferred the subject property to defendant MHC, Inc. Plaintiff alleges that this transfer constituted a breach of contract and that the termination notice, sent by MHC rather than EJ, was inoperative to either terminate the contract or trigger plaintiff’s obligation to serve a reinstatement notice. Defendants take the position that this transfer represented only a technical change in the form of ownership as part of a corporate restructuring, which did not breach the contract since MHC remained at all times ready, willing and able to perform thereunder, and which was, in any event, implicitly waived by plaintiffs seeking specific performance of the contract and joining MHC as a party defendant. Notably, little or no discovery has yet been conducted and Supreme Court was thus unable to resolve, as a matter of law, the effect of this transfer upon the parties’ rights and obligations under the contract.
Supreme Court also properly declined to cancel plaintiffs notice of pendency. Cancellation is mandatory where the action has been “settled, discontinued or abated” (CPLR 6514 [a]) and permissible where an action has not been “commenced or prosecuted * * * in good faith” (CPLR 6514 [b]). Neither provision has application here.
Nor do we find merit in defendants’ contention that Supreme Court erred in permitting plaintiff to amend its complaint by adding a cause of action for tortious interference with contractual relations. Leave to amend a pleading should be freely given (CPLR 3025 [b]) in the sound discretion of the trial court (see, Edenwald Contr. Co. v City of New York, 60 NY2d 957, 959; Murray v City of New York, 43 NY2d 400, 404-405).
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
260 A.D.2d 917, 688 N.Y.S.2d 836, 1999 N.Y. App. Div. LEXIS 4224, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cfj-associates-of-new-york-inc-v-hanson-industries-nyappdiv-1999.