Century Indemnity Co. v. Esso Standard Oil Co.

79 S.E.2d 625, 195 Va. 502, 1954 Va. LEXIS 128
CourtSupreme Court of Virginia
DecidedJanuary 25, 1954
DocketRecord 4150
StatusPublished
Cited by12 cases

This text of 79 S.E.2d 625 (Century Indemnity Co. v. Esso Standard Oil Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Century Indemnity Co. v. Esso Standard Oil Co., 79 S.E.2d 625, 195 Va. 502, 1954 Va. LEXIS 128 (Va. 1954).

Opinion

Buchanan, J.,

delivered the opinion of the court.

The city of Charlottesville entered into a written contract dated June 7, 1950, with Lehman-Hoge and Scott, a partnership, herein referred to as the contractor, for the construction and installation of a pipe line for the transmission of natural gas. On the same day the contractor, as principal, entered into a bond to the city, as obligee, with the appellant, The Century Indemnity Company, as surety thereon. Esso Standard Oil Company, the appellee, furnished to the contractor for use on the job certain materials of the value of $2,005.23, for which the contractor did not pay Esso. The installation of the pipe line was completed by the contractor to the satisfaction of the city, which paid the contractor the full amount due under the contract without notice of Esso’s claim against the contractor. Esso brought this action against Century and obtained a judgment for the amount of its claim. 1

*504 On this appeal Century contends that the bond was solely for the benefit of the city, the obligee named therein, and that no action thereon accrued to Esso.

Esso asserts that the bond and contract are to be read together, and that when this is done an intention is disclosed to protect suppliers and materialmen such as Esso, thereby making Esso a third party beneficiary entitled to maintain this action under § 55-22 of the Code. 2

The bond provides that the contractor, called the principal, and Century, called the surety, are held and firmly bound unto the city, called the obligee, in the sum of $90,000, the principal having entered into a written contract d.ated June 7, 1950, with the obligee for the construction of a natural gas transmission line, “which contract is hereby referred to and made a part hereof, as fully as if recited at length herein.

“Now, Therefore, The condition of this obligation is such, that if the Principal [contractor] shall indemnify the Obligee [city] against any loss or damage directly arising by reason of the failure of the Principal to faithfully perform said contract, then this obligation shall be void; otherwise to remain in full force and effect.

“Provided, however, and upon the Express Conditions, the performance of each of which shall be a condition precedent to any right to recovery hereon:” following which the conditions are set forth in six numbered paragraphs, those pertinent here being summarized or quoted in full as follows:.

First: In event of any default on the part of the principal, a written statement describing same shall be given to the' surety, and the surety shall have the right within thirty days thereafter to proceed with the performance of the contract, *505 whereupon all money due at the time of the default or thereafter to become due to the principal shall be paid to the surety, which shall be subrogated to all rights of the principal.

“Fifth: That the Obligee [city] shall faithfully perform all the terms, covenants and conditions of such contract on the part of the Obligee to be performed; and shall also retain that proportion, if any, which such contract specifies the Obligee shall or may retain of the value of all work performed or materials furnished in the prosecution of such contract (not less, however, in any event, than ten per centum of such value), until the complete performance-by the Principal of all the terms, covenants and conditions of said contract on the Principal’s part to be performed; # # .

“Sixth: That no right of action shall accrue upon or by reason hereof, to or for the use or benefit of any one other than the Obligee [city] herein named; nor shall any interest herein or right of action hereon, be assigned without the prior consent, in writing, of the Surety.”

The written contract between the city and the contractor did not require the execution of a bond, and there is no statute in this State which required its execution, such as § 33-101 of the Code and § 11-20 as amended, 1952 Cumulative Supplement, require with respect to certain contracts with the State and its agencies. The circumstances of the execution of the bond are not disclosed but it is very clear from the parts quoted, and there is nothing in any part of the bond itself to indicate otherwise, that it is a bond to idemnify the city alone, not a performance or labor and material payment bond such as this appellant also issues. Taken by itself this bond does not purport and cannot be construed to promise anything to Esso as a supplier of material to the contractor.

But the bond provides that the contract is made- a part of it as fully as if recited at length therein. The bond and the contract therefore are to be construed together to *506 determine the character and extent of the obligations assumed by the surety; and if when so read and construed together it thereby fairly appears that it was the intent and purpose of the parties at the time the bond was executed that suppliers and materialmen were to be protected by the bond, then the judgment complained of must be sustained.

Esso relies on Article III, § 21, and Article IV, § 12(3) (d)(e), of the construction contract and the Fifth condition of the bond to establish such purpose and intent.

Article III, § 21, of the contract provides that the contractor shall “promptly and satisfactorily settle all claims for labor, equipment, materials and supplies, and for all damage claims of every nature, which it is obligated to pay hereunder, and to furnish affidavits or other suitable evidence satisfactory to the Company [city] that all such claims have been settled. * # .”

Article IV, § 12(3) (d)(e) provides that the city shall retain 20% of the contract price for work done until final settlement is made, and after final completion and acceptance of the work, and the city has been furnished satisfactory evidence that all bills for labor, equipment and materials and all claims payable by the contractor have been paid or settled, the amount retained shall be paid to the contractor.

The Fifth condition of the bond is quoted above.

The argument of Esso runs thus: These provisions of the contract that the contractor should pay for the materials and that the city should retain part of the contract price until all bills for materials had been paid, did not benefit either the contractor or the city; therefore, the only persons for whose benefit they could have been intended were the suppliers of materials, such as Esso; Century’s bond was given to assure that the undertakings of the contract would be fully performed; Century recognized the undertaking to protect materialmen when in the Fifth condition of the bond it conditioned its liability on the city’s performance of its undertaking to retain part of the contract price until completion of the contract; the intention to protect material- *507

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
79 S.E.2d 625, 195 Va. 502, 1954 Va. LEXIS 128, Counsel Stack Legal Research, https://law.counselstack.com/opinion/century-indemnity-co-v-esso-standard-oil-co-va-1954.